Condo, residential tower (mixed-use, multi-family elevator) [derived]
Eliza's Court Condominium
2073 8TH AVENUE · BIN 1086220
💬 Discuss this project
2003Year Built
7Stories
RMBuilding Class
R8AZoning
7,622 sfGross Floor Area
7Units
Rent Stabilized1 Active Violation 2 old, status unconfirmed ▸FISP: SAFE
Condo, residential tower (mixed-use, multi-family elevator) [derived] · 2,550 sf lot · 2.99 FAR built · Flood zone X
Locations of Work
EquipmentGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Site & exteriorSupported pipe scaffold and sidewalk shed5p · 2 filings · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
2073 Equities2703/21/2026
Eliza's Court Condominium603/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Ikra Consulting211/23/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AK Consulting Services403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Rennon ConstructionScaffold403/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Ikra Consulting7032111/23/2020
Building Lifecycle
All (47)Filed (2)Permit Issued (2)Signed Off (2)Facade (FISP) (9)Violation (31)Special Inspection (1)
05/08/2026
Violation issued (HPD, closed)
A
06/30/2025
Signed off — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 2073 8TH AVENUE, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M00430951-I1
06/30/2025
Signed off — Alteration
INSTALLATION OF PIPE SCAFFOLD AT 2073 8TH AVENUE, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M00430956-I1
02/26/2025
Violation issued (ECB, closed)
Construction
02/26/2025
Violation issued (ECB, closed)
Unknown
02/26/2025
Violation issued (ECB, closed)
Construction
02/26/2025
Violation issued (ECB, closed)
Construction
02/26/2025
Violation issued (ECB, closed)
Unknown
02/26/2025
Violation issued (ECB, closed)
Construction
02/12/2025
Cycle 9 facade report signed — SAFE
12/20/2024
Cycle 9 facade report submitted
12/03/2024
Cycle 9 facade inspection completed
04/16/2024
Violation issued (HPD, closed)
A
04/11/2024
Violation issued (ECB, open)
Local Law
03/30/2023
Violation issued (HPD, closed)
A
02/22/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/08/2022
Violation issued (HPD, closed)
A
11/24/2020
Permit issued — Supported Scaffold
M00430956-I1-SF
11/23/2020
Filed — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 2073 8TH AVENUE, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M00430951-I1
11/23/2020
Filed — Alteration
INSTALLATION OF PIPE SCAFFOLD AT 2073 8TH AVENUE, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M00430956-I1
11/23/2020
Permit issued — Sidewalk Shed
M00430951-I1-SH
11/19/2020
Special inspection requirement — Post-installed Anchors
MD MOSTAFA
11/04/2019
Violation issued (HPD, closed)
I
09/06/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/31/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/25/2018
Violation issued (HPD, closed)
I
10/21/2018
Cycle 8 facade report signed — SWARMP
02/21/2018
Cycle 8 facade report submitted
01/31/2018
Cycle 8 facade inspection completed
12/01/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/19/2015
Violation issued (HPD, closed)
I
12/20/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/21/2013
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/30/2013
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/21/2013
Cycle 7 facade report submitted
02/15/2013
Cycle 7 facade report signed — SAFE
02/07/2013
Cycle 7 facade inspection completed
08/25/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
06/06/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/21/2006
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
01/31/2005
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/21/2004
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/18/2003
Violation issued (ECB, closed)
Site Safety
02/25/2003
Violation issued (ECB, closed)
Construction
02/25/2003
Violation issued (ECB, closed)
Site Safety
02/25/2003
Violation issued (ECB, closed)
Construction
02/25/2003
Violation issued (ECB, closed)
Site Safety
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldSigned-offRennon Construction11/24/2020
DOB NOWSidewalk ShedSigned-offRennon Construction11/23/2020
BISOTISSUEDRennon Construction09/24/2021
BISOTISSUEDRennon Construction11/27/2020
BISSDISSUEDJulian Plumbing & Heating01/21/2004
BISPLISSUEDJulian Plumbing & Heating12/30/2003
BISPLISSUEDJulian Plumbing & Heating09/08/2003
BISEQISSUEDXolle Demo07/28/2003
BIS—ISSUEDXolle Demo07/28/2003
BISEQRE-ISSUEDLilly Construction Co04/01/2003
BIS—ISSUEDXolle Demo02/10/2003
BISEQISSUEDXolle Demo01/02/2003
BISEQISSUEDLilly Construction Co12/24/2002
BISSPISSUEDJulian Sprinkler10/17/2002
BISPLISSUEDJulian Plumbing & Heating10/17/2002
BISPLISSUEDJulian Plumbing & Heating09/30/2002
BISEQISSUEDXolle Demo09/05/2002
BIS—ISSUEDXolle Demo09/05/2002
BISOTISSUEDXolle Demo07/18/2002
BISEQISSUEDXolle Demo07/18/2002
BISOTISSUEDXolle Demo06/10/2002
BISEQISSUEDXolle Demo06/10/2002
1 project · most recent 12/16/2020
FiledStatusContractorScope
12/16/2020Permit IssuedGreen Power Electric—
▾Special Inspection Requirements (DOB NOW) — 1
DateRequirementInspectorRole
11/19/2020Post-installed AnchorsMD MOSTAFAspecial
▾Documents — 25 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/04/2026M00430956-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/04/2026M00430951-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
10/09/2020140964204Open ↗
▸BISWORK PERMIT APPLICATION1
11/27/2020140964204Open ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026M00430951-I1Open ↗
08/13/2026M00430956-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
10/09/2020140964204Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
10/09/2020140964204Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
10/09/2020140964204Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/26/2026M00430956-I1Open ↗
▸Safety & Tenant Protection3
▸DOB NOWTenant Protection Plan2
08/13/2026M00430951-I1Open ↗
08/13/2026M00430956-I1Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
10/09/2020140964204Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
10/09/2020140964204Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
12/15/2021140964204Open ↗
10/09/2020140964204Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
10/09/2020140964204Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
12/15/2021140964204Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY2
12/15/2021140964204Open ↗
10/09/2020140964204Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
11/27/2020140964204Open ↗
▸Approvals, Objections & Sign-offs1
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
12/15/2021140964204Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
12/15/2021140964204Open ↗
10/09/2020140964204Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
10/09/2020140964204Open ↗