← Back
Two family brick
2074 61 STREET
BROOKLYN · Mapleton-Midwood (West) · BIN 3132622
💬 Discuss this project
1925Year Built
2Stories
B1Building Class
R5Zoning
2,480 sfGross Floor Area
2Units
7 Open Violations 6 unresolved · 1 paperwork only ▸FDNY Report ↗
Two family brick · Owner of record: 2074 61ST LLC · 2,500 sf lot · 0.99 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction37p · 1 filing · 20 docs
Floor 3Under Construction23p · 1 filing · 20 docs
Floor 2Under Construction34p · 1 filing · 20 docs
Floor 1Under Construction33p · 1 filing · 20 docs
CellarUnder Construction33p · 1 filing · 20 docs
Site & exteriorUnder Construction5p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
J G CONSTRUCTION SRVCS404/09/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/11/2024$1.9M—— → —$766/sf building
11/07/2013$918K—Private party → Private party$370/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MARK WEINBERGER ARCHITECT PLLC907/08/2026
STRUCTURAL ENGINEERING TECHNOLOGIES102/05/2026
ASHRAF CORP112/26/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EXPEDITER GROUP1603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CLASSIC BUILDERS CORPGeneral Contractor607/29/2026
WIZ FIRE SPRINKLERS LLCFire Protection106/28/2026
J & G CONSTRUCTION SVCSGeneral Contractor104/09/2026
ORBIT PLBG & HTG INCPlumbing107/03/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ENGINEERING CONSULTING SE2050707/08/2026
SHAHRISH SHUVO ENGINEERIN8524202/05/2026
AA BUILDING & INSPECTION1519103/19/2025
Building Lifecycle
All (125)Filed (11)Permit Issued (9)Signed Off (1)Violation (8)Inspection (22)Objection (44)Special Inspection (30)
07/28/2026
Permit issued — Earth Work
B01164821-S4-FO-EA
07/21/2026
Permit issued — Mechanical Systems
B01164821-S1-MS
07/21/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/15/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/08/2026
Filed — Alteration CO
PROPOSED HORIZONTAL AND VERTICAL ENLARGEMENT FILED HEREWITH.
B01164821-P3
07/01/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
07/01/2026
Special inspection requirement — Permanent certificate
PAUL MARINO
07/01/2026
Special inspection requirement — HVAC-R and service water heating equipment
PAUL MARINO
07/01/2026
Special inspection requirement — Maintenance information
PAUL MARINO
07/01/2026
Special inspection requirement — HVAC-R and service water heating system controls
PAUL MARINO
07/01/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
PAUL MARINO
07/01/2026
Special inspection requirement — Energy Code Compliance Inspections
PAUL MARINO
06/30/2026
Objection resolved — Addressed
06/11/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
B01339619-I1
05/28/2026
Objection raised — Other
05/26/2026
Filed — Alteration CO
PROPOSED HORIZONTAL AND VERTICAL ENLARGEMENT FILED HEREWITH.
B01164821-P2
05/20/2026
Violation issued (ECB, open)
Construction
05/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
05/20/2026
Special inspection requirement — Permanent certificate
PAUL MARINO
05/20/2026
Special inspection requirement — HVAC-R and service water heating equipment
PAUL MARINO
05/20/2026
Special inspection requirement — Maintenance information
PAUL MARINO
05/20/2026
Special inspection requirement — HVAC-R and service water heating system controls
PAUL MARINO
05/20/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
PAUL MARINO
05/20/2026
Special inspection requirement — Energy Code Compliance Inspections
PAUL MARINO
04/30/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/29/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/29/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/27/2026
Permit issued — Sprinklers
B01164821-S5-EW-SP
04/24/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/22/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
03/13/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
03/13/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
03/11/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/04/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
03/04/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
03/03/2026
Permit issued — Plumbing
B01164821-S6-PL
02/05/2026
Filed — Alteration CO
PROPOSED HORIZONTAL AND VERTICAL ENLARGEMENT FILED HEREWITH.
B01164821-S3
02/05/2026
Filed — Alteration CO
PROPOSED HORIZONTAL AND VERTICAL ENLARGEMENT FILED HEREWITH.
B01164821-S4
01/20/2026
Objection resolved — Addressed
12/31/2025
Violation issued (ECB, open)
Unknown
12/31/2025
Violation issued (ECB, open)
Unknown
12/31/2025
Violation issued (ECB, open)
Unknown
12/30/2025
Special inspection requirement — Concrete - Cast-In-Place
Shahrish Shuvo
12/30/2025
Special inspection requirement — Masonry
Shahrish Shuvo
12/30/2025
Special inspection requirement — Structural Steel - High Strength Bolting
Shahrish Shuvo
12/30/2025
Special inspection requirement — Structural Steel - Welding
Shahrish Shuvo
12/30/2025
Special inspection requirement — Post-installed anchors in masonry
Shahrish Shuvo
12/29/2025
Permit issued — Sidewalk Shed
B01339619-I1-SH
12/26/2025
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
B01339619-I1
12/22/2025
Objection raised — Energy
12/17/2025
Filed — Alteration CO
PROPOSED HORIZONTAL AND VERTICAL ENLARGEMENT FILED HEREWITH.
B01164821-P1
12/17/2025
Objection raised — Zoning
12/17/2025
Objection resolved — Addressed
12/17/2025
Objection raised — Scope
12/17/2025
Objection resolved — Addressed
12/08/2025
Special inspection requirement — Fenestration areas
PAUL MARINO
12/08/2025
Special inspection requirement — Energy Code Compliance Inspections
PAUL MARINO
12/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
12/08/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
PAUL MARINO
12/08/2025
Special inspection requirement — Fire-Resistance Rated Construction
PAUL MARINO
Latest 60 of 125 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWEarth WorkPermit IssuedCLASSIC BUILDERS CORP07/28/2026
DOB NOWMechanical SystemsPermit IssuedCLASSIC BUILDERS CORP07/21/2026
DOB NOWSprinklersPermit IssuedWIZ FIRE SPRINKLERS LLC04/27/2026
DOB NOWPlumbingPermit IssuedORBIT PLBG & HTG INC03/03/2026
DOB NOWSidewalk ShedSigned-offJ & G CONSTRUCTION SVCS12/29/2025
DOB NOWGeneral ConstructionPermit IssuedCLASSIC BUILDERS CORP11/06/2025
DOB NOWConstruction FencePermit IssuedCLASSIC BUILDERS CORP08/05/2025
DOB NOWGeneral ConstructionPermit IssuedCLASSIC BUILDERS CORP04/24/2025
DOB NOWConstruction FencePermit IssuedCLASSIC BUILDERS CORP08/08/2024
BISPLISSUEDDYCKMAN PLBG & HTG INC08/06/2009
1 project · most recent 07/08/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
07/08/2026Permit IssuedCLASSIC BUILDERS CORPHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric MXZ-SM48NAMHZ2-U1 48,000 BTU · Heat Pump Outdoor ×2
MXZ-SM60NAM2-U1 60,000 BTU · Heat Pump Outdoor ×1
Ventilation
— SP-B80 46 CFM · Exhaust Fan ×6
1 project · most recent 07/08/2026
Sprinkler System
FiledStatusContractorScope
07/08/2026Permit IssuedWIZ FIRE SPRINKLERS LLCSprinkler System
1 project · most recent 07/08/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
07/08/2026Permit IssuedORBIT PLBG & HTG INCGas, Storm, Water/Sanitary
2 projects · most recent 05/07/2026
FiledStatusContractorScope
05/07/2026Permit IssuedB.P. ELECTRIC CORP1 meters
12/31/2025CompleteRICHARD NEU—
1 project · most recent 07/08/2026
Steel Concrete Masonry
FiledStatusContractorScope
07/08/2026Permit IssuedCLASSIC BUILDERS CORPSteel, Concrete, Masonry
2 projects · most recent 12/26/2025
Sidewalk Shed Fence
FiledStatusContractorScope
12/26/2025Signed-offJ & G CONSTRUCTION SVCSSidewalk Shed
07/30/2024Permit IssuedCLASSIC BUILDERS CORPFence
▾Field Inspections (DOB CAP) — 22
DateTypeResultReport
07/21/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
07/15/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/30/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/29/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/29/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/24/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/22/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
03/13/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
03/13/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
03/11/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/04/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
03/04/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
06/24/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
06/18/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
06/18/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/27/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
05/27/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/16/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
08/16/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
08/01/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
08/01/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/23/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 42
DateRequirementInspectorRole
07/01/2026Fire-Resistant Penetrations and JointsPAUL MARINOspecial
07/01/2026Permanent certificatePAUL MARINOenergy_progress
07/01/2026HVAC-R and service water heating equipmentPAUL MARINOenergy_progress
07/01/2026Maintenance informationPAUL MARINOenergy_progress
07/01/2026HVAC-R and service water heating system controlsPAUL MARINOenergy_progress
07/01/2026HVAC-R and service water piping design and insulationPAUL MARINOenergy_progress
07/01/2026Energy Code Compliance InspectionsPAUL MARINOprogress
05/20/2026Fire-Resistant Penetrations and JointsPAUL MARINOspecial
05/20/2026Permanent certificatePAUL MARINOenergy_progress
05/20/2026HVAC-R and service water heating equipmentPAUL MARINOenergy_progress
05/20/2026Maintenance informationPAUL MARINOenergy_progress
05/20/2026HVAC-R and service water heating system controlsPAUL MARINOenergy_progress
05/20/2026HVAC-R and service water piping design and insulationPAUL MARINOenergy_progress
05/20/2026Energy Code Compliance InspectionsPAUL MARINOprogress
12/30/2025Concrete - Cast-In-PlaceShahrish Shuvospecial
12/30/2025MasonryShahrish Shuvospecial
12/30/2025Structural Steel - High Strength BoltingShahrish Shuvospecial
12/30/2025Structural Steel - WeldingShahrish Shuvospecial
12/30/2025Post-installed anchors in masonryShahrish Shuvospecial
12/08/2025Fenestration areasPAUL MARINOenergy_progress
12/08/2025Energy Code Compliance InspectionsPAUL MARINOprogress
12/08/2025Fire-Resistant Penetrations and JointsPAUL MARINOspecial
12/08/2025Structural Stability – Alterations of existing buildingsPAUL MARINOspecial
12/08/2025Fire-Resistance Rated ConstructionPAUL MARINOprogress
12/08/2025Interior lighting powerPAUL MARINOenergy_progress
Latest 25 of 42.
▾Documents — 82 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/24/2026B01086974-I1Request digital key ↗
08/19/2026B01339619-I1Request digital key ↗
08/16/2026B01164821-S6Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits3
▸BISWORK PERMIT APPLICATION2
08/07/2009320049782Open ↗
08/04/2009320049782Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
07/07/2009320049782Open ↗
▸Zoning, Tax Lot & Property Records8
▸DOB NOWZD1: DOB Zoning Diagram3
08/16/2026B01164821-P3Open ↗
08/13/2026B01164821-I1Open ↗
08/13/2026B01164821-P1Open ↗
▸DOB NOWZoning Exhibit form (1-5)3
08/16/2026B01164821-P3Open ↗
08/13/2026B01164821-I1Open ↗
08/13/2026B01164821-P1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/13/2026B01164821-P1Open ↗
08/13/2026B01164821-I1Open ↗
▸Seals & Professional Certifications26
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/24/2026B01086974-I1Open ↗
08/16/2026B01164821-S6Open ↗
08/16/2026B01164821-S4Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
09/29/2026B01164821-S3Open ↗
09/01/2026B01164821-P1Open ↗
09/01/2026B01164821-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/29/2026B01164821-S3Open ↗
09/29/2026B01164821-S3Open ↗
09/01/2026B01164821-P1Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
07/07/2009320049782Open ↗
▸Trade Schedules & Equipment3
▸BISSELF-CERT PLUMBING NOTICE2
11/09/2009320049782Open ↗
10/29/2009320049782Open ↗
▸BISSCHEDULE B - PLUMBING1
07/07/2009320049782Open ↗
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist3
08/16/2026B01164821-P3Open ↗
08/13/2026B01164821-P1Open ↗
08/13/2026B01164821-I1Open ↗
▸BISSTREET TREE CHECKLIST1
07/07/2009320049782Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/16/2026B01164821-S4Open ↗
08/16/2026B01164821-S3Open ↗
08/16/2026B01164821-S1Open ↗
Showing 3 of 9 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
07/07/2009320049782Open ↗
▸Approvals, Objections & Sign-offs1
▸BISADMINISTRATIVE OBJECTIONS1
07/07/2009320049782Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
07/07/2009320049782Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
07/07/2009320049782Open ↗
▸Other Documents14
▸DOB NOWPlot Diagram4
08/16/2026B01164821-P3Open ↗
08/13/2026B01164821-S4Open ↗
08/13/2026B01164821-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSite Survey: Initial3
08/16/2026B01164821-P3Open ↗
08/13/2026B01164821-P1Open ↗
08/13/2026B01164821-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/16/2026B01164821-P3Open ↗
08/13/2026B01164821-P1Open ↗
08/13/2026B01164821-I1Open ↗
▸DOB NOWProperty Ownership Certification3
08/16/2026B01164821-I1Open ↗
08/16/2026B01164821-P3Open ↗
08/16/2026B01164821-P1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026B01164821-S4Open ↗