Locations of Work
ArchitectureStructuralElectricalMechanicalFire ProtectionEquipmentGeneral
Roof7p · 5 filings · 12 docs
Floor 121 filing · 4 docs
Floor 11
Floor 10
Floor 9
Floor 82p · 1 filing · 5 docs
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 25p · 3 filings · 5 docs
Floor 12p · 2 filings · 5 docs
Cellar4p · 1 filing · 3 docs
Site & exterior9 filings · 20 docs
Filed — no permit issued1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
VERIZON7007/08/2026
NEW YORK TELEPHONE COMPANY203/21/2026
NYNEX103/21/2026
BELL ATLANTIC RM 802103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SPRING SCAFFOLDING LLCGeneral Contractor2507/08/2026
TISHMAN INTERIORS CORPGeneral Contractor1007/08/2026
ON-TRAC CONSTRUCTION ASSOGeneral Contractor907/08/2026
YORK SCAFFOLD EQUIPMENT CORP.General Contractor407/08/2026
STARR INDUSTRIES LLCGeneral Contractor407/08/2026
MATTHEW PARKERElectrical203/21/2026
ANTHONY MATRONEElectrical103/21/2026
MATRONE ANTHONYElectrical103/21/2026
UNIVERSAL BUILD SUPP LLCGeneral Contractor104/09/2026
ASHLAR MECHANICAL CORPFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CROSSCHECK INSPECTION SER544601/09/2025
MERRITT ENGINEERING CONSU460304/10/2023
Building Lifecycle
All (199)Filed (28)Permit Issued (32)Signed Off (22)Facade (FISP) (15)Violation (60)Inspection (4)Objection (8)Special Inspection (30)
08/11/2026
Signed off — Alteration
TEAR OFF ROOF REPLACEMENT PROJECT, REPLACE WITH SIPLAST ROOFING SYSTEM AS SHOWN ON DRAWINGS. INSTALLATION OF OPTIM-R INSULATION PANEL WITH R VALUE=33. INSTALLATION OF BALLAST PAVERS ABOVE NEW ROOFING SYSTEM. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01259455-I1
08/11/2026
Signed off — Alteration
TEAR OFF ROOF REPLACEMENT PROJECT, REPLACE WITH SIPLAST ROOFING SYSTEM AS SHOWN ON DRAWINGS. INSTALLATION OF OPTIM-R INSULATION PANEL WITH R VALUE=33. INSTALLATION OF BALLAST PAVERS ABOVE NEW ROOFING SYSTEM. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01259451-I1
07/20/2026
Signed off — Alteration
Instillation of new chillers, dry coolers, and air conditioning units as per plans herewith. No change to use, egress, or occupancy.
M01083056-S1
06/30/2026
Signed off — Alteration
Instillation of new chillers, dry coolers, and air conditioning units as per plans herewith. No change to use, egress, or occupancy.
M01083056-I1
06/30/2026
Signed off — Alteration
Additions/Modifications to existing sprinkler system. No change to use, egress, or occupancy.
M01163047-I1
02/11/2026
Signed off — Alteration
M01150077-I1
11/17/2025
Signed off — Alteration
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259515-I1
11/13/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SUPPORTED SCAFFOLD FOR BETAMAX HOIST AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259554-I1
11/13/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SUPPORTED SCAFFOLD FOR BETAMAX HOIST AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259554-S1
11/13/2025
Signed off — Alteration
INSTALLATION OF A TEMPORARY CONSTRUCTION FENCE ENCLOSURE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. FENCE ENCLOSURE INSTALLED IN ACCORDANCE WITH 2022 NYC DOB CODE, CHAPTER 33.
M01276832-I1
10/21/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/22/2025
Permit issued — General Construction
M01259451-I1-GC
09/22/2025
Permit issued — General Construction
M01259455-I1-GC
09/15/2025
Filed — Alteration
TEAR OFF ROOF REPLACEMENT PROJECT, REPLACE WITH SIPLAST ROOFING SYSTEM AS SHOWN ON DRAWINGS. INSTALLATION OF OPTIM-R INSULATION PANEL WITH R VALUE=33. INSTALLATION OF BALLAST PAVERS ABOVE NEW ROOFING SYSTEM. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01259455-I1
09/15/2025
Filed — Alteration
TEAR OFF ROOF REPLACEMENT PROJECT, REPLACE WITH SIPLAST ROOFING SYSTEM AS SHOWN ON DRAWINGS. INSTALLATION OF OPTIM-R INSULATION PANEL WITH R VALUE=33. INSTALLATION OF BALLAST PAVERS ABOVE NEW ROOFING SYSTEM. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01259451-I1
08/27/2025
Filed — Alteration
INSTALLATION OF A TEMPORARY CONSTRUCTION FENCE ENCLOSURE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. FENCE ENCLOSURE INSTALLED IN ACCORDANCE WITH 2022 NYC DOB CODE, CHAPTER 33.
M01276832-I1
08/27/2025
Permit issued — Construction Fence
M01276832-I1-FN
08/07/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
07/31/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SUPPORTED SCAFFOLD FOR BETAMAX HOIST AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259554-I1
07/31/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SUPPORTED SCAFFOLD FOR BETAMAX HOIST AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259554-S1
07/31/2025
Permit issued — Protection and Mechanical Methods
M01259554-S1-PMM
07/31/2025
Permit issued — Supported Scaffold
M01259554-I1-SF
07/29/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/29/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/28/2025
Filed — Alteration
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259515-I1
07/28/2025
Permit issued — Sidewalk Shed
M01259515-I1-SH
07/22/2025
Special inspection requirement — Fenestration air leakage
Christopher Krepcio
07/22/2025
Special inspection requirement — Final
Christopher Krepcio
07/22/2025
Special inspection requirement — Energy Code Compliance Inspections
Christopher Krepcio
07/22/2025
Special inspection requirement — Air barrier - visual inspection
Christopher Krepcio
07/22/2025
Special inspection requirement — Fenestration air leakage
Christopher Krepcio
07/22/2025
Special inspection requirement — Final
Christopher Krepcio
07/22/2025
Special inspection requirement — Energy Code Compliance Inspections
Christopher Krepcio
07/22/2025
Special inspection requirement — Air barrier - visual inspection
Christopher Krepcio
05/14/2025
Cycle 9 facade report signed — SAFE
03/19/2025
Permit issued — Sprinklers
M01163047-I1-EW-SP
02/20/2025
Cycle 9 facade report submitted
02/19/2025
Cycle 9 facade inspection completed
02/10/2025
Signed off — Alteration
M00886530-I1
02/04/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01123662-I1
01/22/2025
Objection raised — Scope
01/22/2025
Objection resolved — Addressed
01/22/2025
Objection raised — Scope
01/22/2025
Objection resolved — Addressed
01/16/2025
Permit issued — Supported Scaffold
M01150077-I1-SF
01/15/2025
Signed off — Alteration
M00820989-I1
01/09/2025
Filed — Alteration
Additions/Modifications to existing sprinkler system. No change to use, egress, or occupancy.
M01163047-I1
01/06/2025
Special inspection requirement — Sprinkler Systems
EUGENE BIFULCO
01/03/2025
Permit issued — Suspended Scaffold
M01107962-I1-SC
12/04/2024
Filed — Alteration
M01150077-I1
11/26/2024
Filed — Alteration
INSTALLATION OF A TEMPORARY SCAFFOLD AS PER PLANS IN CONJUNCTION WITH GENERAL CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH 2022 NYC BUILDING CODE, CHAPTER 33.
M01145679-I1
11/20/2024
Permit issued — Protection and Mechanical Methods
M01123662-I1-PMM
10/31/2024
Permit issued — Mechanical Systems
M01083056-S1-MS
10/17/2024
Permit issued — General Construction
M01083056-I1-GC
10/08/2024
Filed — Alteration
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01123662-I1
10/02/2024
Permit issued — Sidewalk Shed
M00886530-I1-SH
09/12/2024
Violation issued (ECB, closed)
Unknown
09/11/2024
Permit issued — Suspended Scaffold
M01107962-I1-SC
09/10/2024
Filed — Alteration
M01107962-I1
09/04/2024
Filed — Alteration
Instillation of new chillers, dry coolers, and air conditioning units as per plans herewith. No change to use, egress, or occupancy.
M01083056-S1
Latest 60 of 199 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offTISHMAN INTERIORS CORP09/22/2025
DOB NOWGeneral ConstructionSigned-offTISHMAN INTERIORS CORP09/22/2025
DOB NOWConstruction FenceSigned-offSTARR INDUSTRIES LLC08/27/2025
DOB NOWProtection and Mechanical MethodsSigned-offSTARR INDUSTRIES LLC07/31/2025
DOB NOWSupported ScaffoldSigned-offSTARR INDUSTRIES LLC07/31/2025
DOB NOWSidewalk ShedSigned-offSTARR INDUSTRIES LLC07/28/2025
DOB NOWSprinklersSigned-offASHLAR MECHANICAL CORP03/19/2025
DOB NOWSupported ScaffoldSigned-offUNIVERSAL BUILD SUPP LLC01/16/2025
DOB NOWSuspended ScaffoldPermit IssuedH & H RESTORATION CORP01/03/2025
DOB NOWProtection and Mechanical MethodsSigned-offSPRING SCAFFOLDING LLC11/20/2024
DOB NOWMechanical SystemsSigned-offTISHMAN INTERIORS CORP10/31/2024
DOB NOWGeneral ConstructionSigned-offTISHMAN INTERIORS CORP10/17/2024
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC10/02/2024
DOB NOWSuspended ScaffoldPermit IssuedH & H RESTORATION CORP09/11/2024
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC06/08/2023
DOB NOWGeneral ConstructionSigned-offON-TRAC CONSTRUCTION ASSO05/05/2023
DOB NOWGeneral ConstructionSigned-offTISHMAN INTERIORS CORP10/18/2022
DOB NOWGeneral ConstructionSigned-offTISHMAN INTERIORS CORP08/04/2022
DOB NOWMechanical SystemsSigned-offTISHMAN INTERIORS CORP08/04/2022
DOB NOWGeneral ConstructionSigned-offON-TRAC CONSTRUCTION ASSO07/15/2022
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC07/01/2022
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC06/30/2022
DOB NOWConstruction FenceSigned-offSPRING SCAFFOLDING LLC06/27/2022
DOB NOWGeneral ConstructionSigned-offON-TRAC CONSTRUCTION ASSO06/08/2022
DOB NOWGeneral ConstructionSigned-offON-TRAC CONSTRUCTION ASSO02/25/2022
DOB NOWProtection and Mechanical MethodsSigned-offSPRING SCAFFOLDING LLC02/18/2022
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC07/01/2021
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC07/01/2021
DOB NOWGeneral ConstructionSigned-offON-TRAC CONSTRUCTION ASSO05/25/2021
DOB NOWSidewalk ShedSigned-offYORK SCAFFOLD EQUIPMENT CORP.10/10/2019
DOB NOWSidewalk ShedSigned-offYORK SCAFFOLD EQUIPMENT CORP.02/13/2019
DOB NOWSidewalk ShedSigned-offYORK SCAFFOLD EQUIPMENT CORP.04/20/2018
BISSPISSUEDSIRINA FIRE PROT CORP02/18/2020
BISMHISSUEDTISHMAN CONSTRUCTION CORP11/21/2019
BISOTISSUEDTISHMAN CONSTRUCTION CORP09/23/2019
BISOTISSUEDTISHMAN CONSTRUCTION CORP09/23/2019
BISMHISSUEDTISHMAN CONSTRUCTION CORP09/23/2019
BISOTISSUEDON-TRAC CONSTRUCTION ASSO04/01/2019
BISSPISSUEDCODE FIRE PROTECTION CORP01/15/2019
BISSPISSUEDCODE FIRE PROTECTION CORP01/14/2019
+ 42 more permits on file
1 project · most recent 01/09/2025
FiledStatusContractorScope
01/09/2025Signed-offASHLAR MECHANICAL CORP5 heads
9 projects · most recent 08/01/2025
General Wiring Lighting
FiledStatusContractorScope
08/01/2025CompleteJ.A. LEE ELEC SVCS LLCGeneral Wiring
09/26/2024CompleteJAMES F. VOLPE ELEC'LGeneral Wiring
06/01/2023CompleteTOP SHELF ELECTRIC CORP—
02/07/2023CompleteALLAN/BRITE-WAY ELEC'L COGeneral Wiring
09/28/2022CompletePINTO & TEGER ELEC. CORP.General Wiring
05/27/2021CompleteTOP SHELF ELECTRIC CORP—
02/25/2021CompletePINTO & TEGER ELEC. CORP.General Wiring, Lighting
02/04/2019Permit IssuedSTANCO SYSTEM ELEC'L CONT—
04/12/2018CompleteSTANCO SYSTEM ELEC'L CONT—
1 project · most recent 11/26/2024
Scaffold
FiledStatusContractorScope
11/26/2024——Scaffold
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
10/21/2025Pass-Final CND-Occupancy InspectionPassView ↗
08/07/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/29/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/29/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
07/22/2025Fenestration air leakageChristopher Krepcioenergy_progress
07/22/2025FinalChristopher Krepcioprogress
07/22/2025Energy Code Compliance InspectionsChristopher Krepcioprogress
07/22/2025Air barrier - visual inspectionChristopher Krepcioenergy_progress
07/22/2025Fenestration air leakageChristopher Krepcioenergy_progress
07/22/2025FinalChristopher Krepcioprogress
07/22/2025Energy Code Compliance InspectionsChristopher Krepcioprogress
07/22/2025Air barrier - visual inspectionChristopher Krepcioenergy_progress
01/06/2025Sprinkler SystemsEUGENE BIFULCOspecial
08/19/2024Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
08/15/2024FinalEUGENE BIFULCOprogress
01/30/2023Fenestration air leakageChristopher Krepcioenergy_progress
01/30/2023FinalChristopher Krepcioprogress
01/30/2023Energy Code Compliance InspectionsChristopher Krepcioprogress
01/30/2023Air barrier - visual inspectionChristopher Krepcioenergy_progress
01/30/2023MasonryChristopher Krepciospecial
01/30/2023Structural Stability – Alterations of existing buildingsChristopher Krepciospecial
05/05/2022HVAC-R and service water piping design and insulationEUGENE BIFULCOenergy_progress
05/05/2022Maintenance informationEUGENE BIFULCOenergy_progress
05/05/2022Shutoff dampersEUGENE BIFULCOenergy_progress
05/05/2022Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
05/05/2022HVAC-R and service water heating system controlsEUGENE BIFULCOenergy_progress
05/05/2022Duct leakage testing, insulation and designEUGENE BIFULCOenergy_progress
05/05/2022HVAC-R and service water heating equipmentEUGENE BIFULCOenergy_progress
03/28/2022MasonryChristopher Krepciospecial
Latest 25 of 34.
▾Documents — 555 on file (BIS + DOB NOW)
▸Plans & Drawings28
▸DOB NOWPlans/Sketch25
09/06/2026M00033729-I1Request digital key ↗
09/03/2026M00529281-P1Request digital key ↗
09/03/2026M00529281-I1Request digital key ↗
Showing 3 of 25 on file for this type
▸DOB NOWPlans/Sketch - General Construction2
09/04/2026M00474171-P1Request digital key ↗
08/15/2026M00474171-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00126936-I1Request digital key ↗
▸Applications & Permits120
▸BISPLAN / WORK APPROVAL APPLICATION70
05/04/2020123257411Open ↗
03/25/2020123239575Open ↗
03/19/2020123239584Open ↗
Showing 3 of 70 on file for this type
▸BISWORK PERMIT APPLICATION50
02/19/2020123239584Open ↗
11/22/2019123239600Open ↗
09/24/2019123239593Open ↗
Showing 3 of 50 on file for this type
▸Seals & Professional Certifications114
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION58
02/24/2020123128864Open ↗
02/14/2020123239575Open ↗
02/14/2020123239575Open ↗
Showing 3 of 58 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature27
09/06/2026M00033729-I1Open ↗
09/02/2026M00550084-I1Open ↗
09/02/2026M00645845-I1Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWProgress Inspector Seal & Signature15
09/01/2026M01259455-I1Open ↗
09/01/2026M01259455-I1Open ↗
08/31/2026M00550084-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/31/2026M01083056-I1Open ↗
08/30/2026M00820989-I1Open ↗
08/29/2026M00645847-I1Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
03/12/2019123128864Open ↗
Showing 1 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
03/12/2019123128864Open ↗
Showing 1 of 4 on file for this type
▸Trade Schedules & Equipment33
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE11
03/25/2020123239575Open ↗
03/19/2020123239584Open ↗
03/13/2020123239584Open ↗
Showing 3 of 11 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA7
08/14/2020123257439Open ↗
08/14/2020123257420Open ↗
04/03/2020123521894Open ↗
Showing 3 of 7 on file for this type
▸BISEQUIPMENT USE PERMITS6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISSCHEDULE B - PLUMBING5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSELF-CERT PLUMBING NOTICE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSPRINKLER INSP REPORT : FP-851
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos33
▸BISASBESTOS: CERTIFICATION (DEP ACP5)16
08/18/2020123257439Open ↗
04/03/2020123521894Open ↗
03/11/2020123521894Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
09/02/2026M00645845-I1Open ↗
09/01/2026M00777561-I1Open ↗
08/31/2026M00820989-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
08/26/2026M01083056-I1Open ↗
08/26/2026M01083056-S1Open ↗
08/21/2026M01259451-I1Open ↗
Showing 3 of 5 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance36
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS19
02/24/2020123128864Open ↗
03/12/2019123128864Open ↗
08/09/2018123553920Open ↗
Showing 3 of 19 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
05/28/2020123239593Open ↗
05/28/2020123239600Open ↗
05/26/2020123142731Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
05/28/2020123239593Open ↗
05/28/2020123239593Open ↗
05/28/2020123239600Open ↗
Showing 3 of 4 on file for this type
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026M00474171-I1Open ↗
08/15/2026M00645847-I1Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/26/2026M01083056-S1Open ↗
▸Inspections & Test Reports20
▸BISTECHNICAL REPORT: RESPONSIBILITY16
08/18/2020123257420Open ↗
07/14/2020123239575Open ↗
06/24/2020123239584Open ↗
Showing 3 of 16 on file for this type
▸BISHYDRO FLOW TEST LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
01/25/2018123239593Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs47
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST16
08/18/2020123257439Open ↗
08/18/2020123257420Open ↗
07/14/2020123239575Open ↗
Showing 3 of 16 on file for this type
▸BISADMINISTRATIVE OBJECTIONS14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
09/02/2026M00550084-I1Open ↗
09/02/2026M00764665-I1Open ↗
08/31/2026M00886530-I1Open ↗
Showing 3 of 7 on file for this type
▸BISSUPERSEDING LETTER5
02/19/2020123239584Open ↗
07/30/2019123239575Open ↗
07/30/2019123239575Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
05/04/2020123257402Open ↗
02/24/2020123128864Open ↗
Showing 2 of 4 on file for this type
▸BISLANDMARKS APPROVAL1
03/11/2020123521894Open ↗
▸Cost, Insurance & Ownership49
▸BISCOST AFFIDAVIT49
08/18/2020123257439Open ↗
07/14/2020123239575Open ↗
07/08/2020123239584Open ↗
Showing 3 of 49 on file for this type
▸Filing & Intake Forms71
▸BISEFILING COVER SHEET35
03/12/2019123128864Open ↗
07/10/2018123521894Open ↗
06/18/2018123553920Open ↗
Showing 3 of 35 on file for this type
▸BISBOROUGH INTAKE FORM22
05/04/2020123257411Open ↗
04/03/2020123521894Open ↗
03/25/2020123239575Open ↗
Showing 3 of 22 on file for this type
▸BISADDITIONAL INFORMATION14
07/10/2020123239575Open ↗
07/07/2020123239584Open ↗
04/20/2020123239584Open ↗
Showing 3 of 14 on file for this type
▸Other Documents4
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
12/26/2017123239575Open ↗
▸DOB NOWCalculations1
08/13/2026M01107962-I1Open ↗
▸DOB NOWPro Cert Restriction Exception (LL158/17)1
08/13/2026M01145679-I1Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026M01107962-I1Open ↗