← Back
BuildNYC
Telephone utility
208 EAST 79TH STREET
MANHATTAN · BIN 1044182
💬 Discuss this project
0Year Built
—Stories
U4Building Class
R10AZoning
0 sfGross Floor Area
0Units
2 Active Violations 0 unresolved · 2 paperwork only ▸FISP: SAFE
Telephone utility · Owner of record: Verizon New York · 14,684 sf lot · 0 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Whole building & multi-floor projectsVerizon3 filings
RoofVerizon7p · 5 filings · 9 docs
BulkheadVerizon2p · 1 filing · 10 docs
Floor 12Verizon Communications LLC1 filing · 3 docs
Floor 11
Floor 10
Floor 9
Floor 8Verizon2p · 1 filing · 5 docs
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2Verizon4p · 2 filings · 4 docs
Floor 1Verizon2p · 3 filings · 5 docs
CellarCellar and first floor removal and protection4p · 1 filing · 2 docs
Site & exteriorVerizon9 filings · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Verizon15907/08/2026
Bell Atlantic503/21/2026
New York Telephone Co203/21/2026
Nynex103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Spring ScaffoldingScaffold2507/08/2026
Tishman InteriorsGeneral Contractor1007/08/2026
On-Trac Construction AssociatesGeneral Contractor907/08/2026
Starr IndustriesScaffold407/08/2026
York Scaffold EquipmentScaffold407/08/2026
Pinto and Teger ElectricElectrical203/21/2026
Ashlar MechanicalFire Protection107/08/2026
Matrone AnthonyElectrical103/21/2026
Universal Builders SupplyScaffold104/09/2026
James F. Volpe ElectricalElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Crosscheck Inspection Services544601/09/2025
Merritt Engineering Consulting460304/10/2023
Building Lifecycle
All (198)Filed (28)Permit Issued (32)Signed Off (22)Facade (FISP) (15)Violation (60)Inspection (3)Objection (8)Special Inspection (30)
08/11/2026
Signed off — Alteration
TEAR OFF ROOF REPLACEMENT PROJECT, REPLACE WITH SIPLAST ROOFING SYSTEM AS SHOWN ON DRAWINGS. INSTALLATION OF OPTIM-R INSULATION PANEL WITH R VALUE=33. INSTALLATION OF BALLAST PAVERS ABOVE NEW ROOFING SYSTEM. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01259455-I1
08/11/2026
Signed off — Alteration
TEAR OFF ROOF REPLACEMENT PROJECT, REPLACE WITH SIPLAST ROOFING SYSTEM AS SHOWN ON DRAWINGS. INSTALLATION OF OPTIM-R INSULATION PANEL WITH R VALUE=33. INSTALLATION OF BALLAST PAVERS ABOVE NEW ROOFING SYSTEM. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01259451-I1
07/20/2026
Signed off — Alteration
Instillation of new chillers, dry coolers, and air conditioning units as per plans herewith. No change to use, egress, or occupancy.
M01083056-S1
06/30/2026
Signed off — Alteration
Instillation of new chillers, dry coolers, and air conditioning units as per plans herewith. No change to use, egress, or occupancy.
M01083056-I1
06/30/2026
Signed off — Alteration
Additions/Modifications to existing sprinkler system. No change to use, egress, or occupancy.
M01163047-I1
02/11/2026
Signed off — Alteration
M01150077-I1
11/17/2025
Signed off — Alteration
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259515-I1
11/13/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SUPPORTED SCAFFOLD FOR BETAMAX HOIST AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259554-I1
11/13/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SUPPORTED SCAFFOLD FOR BETAMAX HOIST AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259554-S1
11/13/2025
Signed off — Alteration
INSTALLATION OF A TEMPORARY CONSTRUCTION FENCE ENCLOSURE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. FENCE ENCLOSURE INSTALLED IN ACCORDANCE WITH 2022 NYC DOB CODE, CHAPTER 33.
M01276832-I1
09/22/2025
Permit issued — General Construction
M01259451-I1-GC
09/22/2025
Permit issued — General Construction
M01259455-I1-GC
09/15/2025
Filed — Alteration
TEAR OFF ROOF REPLACEMENT PROJECT, REPLACE WITH SIPLAST ROOFING SYSTEM AS SHOWN ON DRAWINGS. INSTALLATION OF OPTIM-R INSULATION PANEL WITH R VALUE=33. INSTALLATION OF BALLAST PAVERS ABOVE NEW ROOFING SYSTEM. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01259455-I1
09/15/2025
Filed — Alteration
TEAR OFF ROOF REPLACEMENT PROJECT, REPLACE WITH SIPLAST ROOFING SYSTEM AS SHOWN ON DRAWINGS. INSTALLATION OF OPTIM-R INSULATION PANEL WITH R VALUE=33. INSTALLATION OF BALLAST PAVERS ABOVE NEW ROOFING SYSTEM. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01259451-I1
08/27/2025
Filed — Alteration
INSTALLATION OF A TEMPORARY CONSTRUCTION FENCE ENCLOSURE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. FENCE ENCLOSURE INSTALLED IN ACCORDANCE WITH 2022 NYC DOB CODE, CHAPTER 33.
M01276832-I1
08/27/2025
Permit issued — Construction Fence
M01276832-I1-FN
08/07/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
07/31/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SUPPORTED SCAFFOLD FOR BETAMAX HOIST AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259554-I1
07/31/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SUPPORTED SCAFFOLD FOR BETAMAX HOIST AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259554-S1
07/31/2025
Permit issued — Supported Scaffold
M01259554-I1-SF
07/31/2025
Permit issued — Protection and Mechanical Methods
M01259554-S1-PMM
07/29/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/29/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/28/2025
Filed — Alteration
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
M01259515-I1
07/28/2025
Permit issued — Sidewalk Shed
M01259515-I1-SH
07/22/2025
Special inspection requirement — Fenestration air leakage
Christopher Krepcio
07/22/2025
Special inspection requirement — Final
Christopher Krepcio
07/22/2025
Special inspection requirement — Energy Code Compliance Inspections
Christopher Krepcio
07/22/2025
Special inspection requirement — Air barrier - visual inspection
Christopher Krepcio
07/22/2025
Special inspection requirement — Fenestration air leakage
Christopher Krepcio
07/22/2025
Special inspection requirement — Final
Christopher Krepcio
07/22/2025
Special inspection requirement — Energy Code Compliance Inspections
Christopher Krepcio
07/22/2025
Special inspection requirement — Air barrier - visual inspection
Christopher Krepcio
05/14/2025
Cycle 9 facade report signed — SAFE
03/19/2025
Permit issued — Sprinklers
M01163047-I1-EW-SP
02/20/2025
Cycle 9 facade report submitted
02/19/2025
Cycle 9 facade inspection completed
02/10/2025
Signed off — Alteration
M00886530-I1
02/04/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01123662-I1
01/22/2025
Objection raised — Scope
01/22/2025
Objection resolved — Addressed
01/22/2025
Objection raised — Scope
01/22/2025
Objection resolved — Addressed
01/16/2025
Permit issued — Supported Scaffold
M01150077-I1-SF
01/15/2025
Signed off — Alteration
M00820989-I1
01/09/2025
Filed — Alteration
Additions/Modifications to existing sprinkler system. No change to use, egress, or occupancy.
M01163047-I1
01/06/2025
Special inspection requirement — Sprinkler Systems
EUGENE BIFULCO
01/03/2025
Permit issued — Suspended Scaffold
M01107962-I1-SC
12/04/2024
Filed — Alteration
M01150077-I1
11/26/2024
Filed — Alteration
INSTALLATION OF A TEMPORARY SCAFFOLD AS PER PLANS IN CONJUNCTION WITH GENERAL CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH 2022 NYC BUILDING CODE, CHAPTER 33.
M01145679-I1
11/20/2024
Permit issued — Protection and Mechanical Methods
M01123662-I1-PMM
10/31/2024
Permit issued — Mechanical Systems
M01083056-S1-MS
10/17/2024
Permit issued — General Construction
M01083056-I1-GC
10/08/2024
Filed — Alteration
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01123662-I1
10/02/2024
Permit issued — Sidewalk Shed
M00886530-I1-SH
09/12/2024
Violation issued (ECB, closed)
Unknown
09/11/2024
Permit issued — Suspended Scaffold
M01107962-I1-SC
09/10/2024
Filed — Alteration
M01107962-I1
09/04/2024
Filed — Alteration
Instillation of new chillers, dry coolers, and air conditioning units as per plans herewith. No change to use, egress, or occupancy.
M01083056-S1
09/04/2024
Filed — Alteration
Instillation of new chillers, dry coolers, and air conditioning units as per plans herewith. No change to use, egress, or occupancy.
M01083056-I1
Latest 60 of 198 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offTishman Interiors09/22/2025
DOB NOWGeneral ConstructionSigned-offTishman Interiors09/22/2025
DOB NOWConstruction FenceSigned-offStarr Industries08/27/2025
DOB NOWSupported ScaffoldSigned-offStarr Industries07/31/2025
DOB NOWProtection and Mechanical MethodsSigned-offStarr Industries07/31/2025
DOB NOWSidewalk ShedSigned-offStarr Industries07/28/2025
DOB NOWSprinklersSigned-offAshlar Mechanical03/19/2025
DOB NOWSupported ScaffoldSigned-offUniversal Build Supp01/16/2025
DOB NOWSuspended ScaffoldPermit IssuedH & H Restoration01/03/2025
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding11/20/2024
DOB NOWMechanical SystemsSigned-offTishman Interiors10/31/2024
DOB NOWGeneral ConstructionSigned-offTishman Interiors10/17/2024
DOB NOWSidewalk ShedSigned-offSpring Scaffolding10/02/2024
DOB NOWSuspended ScaffoldPermit IssuedH & H Restoration09/11/2024
DOB NOWSidewalk ShedSigned-offSpring Scaffolding06/08/2023
DOB NOWGeneral ConstructionSigned-offOn-Trac Construction Associates05/05/2023
DOB NOWGeneral ConstructionSigned-offTishman Interiors10/18/2022
DOB NOWMechanical SystemsSigned-offTishman Interiors08/04/2022
DOB NOWGeneral ConstructionSigned-offTishman Interiors08/04/2022
DOB NOWGeneral ConstructionSigned-offOn-Trac Construction Associates07/15/2022
DOB NOWSupported ScaffoldSigned-offSpring Scaffolding07/01/2022
DOB NOWSidewalk ShedSigned-offSpring Scaffolding06/30/2022
DOB NOWConstruction FenceSigned-offSpring Scaffolding06/27/2022
DOB NOWGeneral ConstructionSigned-offOn-Trac Construction Associates06/08/2022
DOB NOWGeneral ConstructionSigned-offOn-Trac Construction Associates02/25/2022
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding02/18/2022
DOB NOWSupported ScaffoldSigned-offSpring Scaffolding07/01/2021
DOB NOWSidewalk ShedSigned-offSpring Scaffolding07/01/2021
DOB NOWGeneral ConstructionSigned-offOn-Trac Construction Associates05/25/2021
DOB NOWSidewalk ShedSigned-offYork Scaffold Equipment10/10/2019
DOB NOWSidewalk ShedSigned-offYork Scaffold Equipment02/13/2019
DOB NOWSidewalk ShedSigned-offYork Scaffold Equipment04/20/2018
BISSPISSUEDSirina Fire Protection02/18/2020
BISMHISSUEDTishman Construction11/21/2019
BISOTISSUEDTishman Construction09/23/2019
BISOTISSUEDTishman Construction09/23/2019
BISMHISSUEDTishman Construction09/23/2019
BISOTISSUEDOn-Trac Construction Associates04/01/2019
BISSPISSUEDCode Fire Protection01/15/2019
BISSPISSUEDCode Fire Protection01/14/2019
+ 42 more permits on file
1 project · most recent 01/09/2025
FiledStatusContractorScope
01/09/2025Signed-offAshlar Mechanical5 heads
9 projects · most recent 08/01/2025
General Wiring Lighting
FiledStatusContractorScope
08/01/2025CompleteJ.A. Lee Electric ServicesGeneral Wiring
09/26/2024CompleteJames F. Volpe ElectricalGeneral Wiring
06/01/2023CompleteTop Shelf Electric—
02/07/2023CompleteAllan/Brite-Way Electrical CoGeneral Wiring
09/28/2022CompletePinto & Teger ElectricGeneral Wiring
05/27/2021CompleteTop Shelf Electric—
02/25/2021CompletePinto & Teger ElectricGeneral Wiring, Lighting
02/04/2019Permit IssuedStanco System Electrical Cont—
04/12/2018CompleteStanco System Electrical Cont—
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
08/07/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/29/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/29/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
07/22/2025Fenestration air leakageChristopher Krepcioenergy_progress
07/22/2025FinalChristopher Krepcioprogress
07/22/2025Energy Code Compliance InspectionsChristopher Krepcioprogress
07/22/2025Air barrier - visual inspectionChristopher Krepcioenergy_progress
07/22/2025Fenestration air leakageChristopher Krepcioenergy_progress
07/22/2025FinalChristopher Krepcioprogress
07/22/2025Energy Code Compliance InspectionsChristopher Krepcioprogress
07/22/2025Air barrier - visual inspectionChristopher Krepcioenergy_progress
01/06/2025Sprinkler SystemsEUGENE BIFULCOspecial
08/19/2024Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
08/15/2024FinalEUGENE BIFULCOprogress
01/30/2023Air barrier - visual inspectionChristopher Krepcioenergy_progress
01/30/2023Fenestration air leakageChristopher Krepcioenergy_progress
01/30/2023Structural Stability – Alterations of existing buildingsChristopher Krepciospecial
01/30/2023FinalChristopher Krepcioprogress
01/30/2023Energy Code Compliance InspectionsChristopher Krepcioprogress
01/30/2023MasonryChristopher Krepciospecial
05/05/2022HVAC-R and service water piping design and insulationEUGENE BIFULCOenergy_progress
05/05/2022Maintenance informationEUGENE BIFULCOenergy_progress
05/05/2022Shutoff dampersEUGENE BIFULCOenergy_progress
05/05/2022Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
05/05/2022HVAC-R and service water heating system controlsEUGENE BIFULCOenergy_progress
05/05/2022HVAC-R and service water heating equipmentEUGENE BIFULCOenergy_progress
05/05/2022Duct leakage testing, insulation and designEUGENE BIFULCOenergy_progress
03/28/2022Fenestration air leakageChristopher Krepcioenergy_progress
Latest 25 of 34.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
VerizonOfficeEntire building
Project M01259451 Alteration · LOC Issued · 09/15/2025
Project M01259455 Alteration · LOC Issued · 09/15/2025
Project M01083056 Alteration · LOC Issued · 09/04/2024
Project M00820989 Alteration · LOC Issued · 04/10/2023
Project M00645845 Alteration · LOC Issued · 05/03/2022
Project M00474171 Alteration · LOC Issued · 03/01/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 555 on file (BIS + DOB NOW)
▸Plans & Drawings28
▸DOB NOWPlans/Sketch25
09/06/2026M00033729-I1Request digital key ↗
09/03/2026M00529281-I1Request digital key ↗
09/03/2026M00529281-P1Request digital key ↗
Showing 3 of 25 on file for this type
▸DOB NOWPlans/Sketch - General Construction2
09/04/2026M00474171-P1Request digital key ↗
08/15/2026M00474171-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00126936-I1Request digital key ↗
▸Applications & Permits120
▸BISPLAN / WORK APPROVAL APPLICATION70
05/04/2020123257411Open ↗
03/25/2020123239575Open ↗
03/19/2020123239584Open ↗
Showing 3 of 70 on file for this type
▸BISWORK PERMIT APPLICATION50
02/19/2020123239584Open ↗
11/22/2019123239600Open ↗
09/24/2019123239593Open ↗
Showing 3 of 50 on file for this type
▸Seals & Professional Certifications114
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION58
02/24/2020123128864Open ↗
02/14/2020123239575Open ↗
02/14/2020123239575Open ↗
Showing 3 of 58 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature27
09/06/2026M00033729-I1Open ↗
09/02/2026M00550084-I1Open ↗
09/02/2026M00645845-I1Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWProgress Inspector Seal & Signature15
09/01/2026M01259455-I1Open ↗
09/01/2026M01259455-I1Open ↗
08/31/2026M00550084-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/31/2026M01083056-I1Open ↗
08/30/2026M00820989-I1Open ↗
08/29/2026M00645847-I1Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
03/12/2019123128864Open ↗
Showing 1 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
03/12/2019123128864Open ↗
Showing 1 of 4 on file for this type
▸Trade Schedules & Equipment33
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE11
03/25/2020123239575Open ↗
03/19/2020123239584Open ↗
03/13/2020123239584Open ↗
Showing 3 of 11 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA7
08/14/2020123257439Open ↗
08/14/2020123257420Open ↗
04/03/2020123521894Open ↗
Showing 3 of 7 on file for this type
▸BISEQUIPMENT USE PERMITS6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISSCHEDULE B - PLUMBING5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSELF-CERT PLUMBING NOTICE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSPRINKLER INSP REPORT : FP-851
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos33
▸BISASBESTOS: CERTIFICATION (DEP ACP5)16
08/18/2020123257439Open ↗
04/03/2020123521894Open ↗
03/11/2020123521894Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
09/02/2026M00645845-I1Open ↗
09/01/2026M00777561-I1Open ↗
08/31/2026M00820989-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
08/26/2026M01083056-S1Open ↗
08/26/2026M01083056-I1Open ↗
08/21/2026M01259451-I1Open ↗
Showing 3 of 5 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance36
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS19
02/24/2020123128864Open ↗
03/12/2019123128864Open ↗
08/09/2018123553920Open ↗
Showing 3 of 19 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
05/28/2020123239593Open ↗
05/28/2020123239600Open ↗
05/26/2020123142731Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
05/28/2020123239593Open ↗
05/28/2020123239593Open ↗
05/28/2020123239600Open ↗
Showing 3 of 4 on file for this type
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026M00474171-I1Open ↗
08/15/2026M00645847-I1Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/26/2026M01083056-S1Open ↗
▸Inspections & Test Reports20
▸BISTECHNICAL REPORT: RESPONSIBILITY16
08/18/2020123257420Open ↗
07/14/2020123239575Open ↗
06/24/2020123239584Open ↗
Showing 3 of 16 on file for this type
▸BISHYDRO FLOW TEST LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
01/25/2018123239593Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs47
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST16
08/18/2020123257439Open ↗
08/18/2020123257420Open ↗
07/14/2020123239575Open ↗
Showing 3 of 16 on file for this type
▸BISADMINISTRATIVE OBJECTIONS14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
09/02/2026M00550084-I1Open ↗
09/02/2026M00764665-I1Open ↗
08/31/2026M00886530-I1Open ↗
Showing 3 of 7 on file for this type
▸BISSUPERSEDING LETTER5
02/19/2020123239584Open ↗
07/30/2019123239575Open ↗
07/30/2019123239575Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
05/04/2020123257402Open ↗
02/24/2020123128864Open ↗
Showing 2 of 4 on file for this type
▸BISLANDMARKS APPROVAL1
03/11/2020123521894Open ↗
▸Cost, Insurance & Ownership49
▸BISCOST AFFIDAVIT49
08/18/2020123257439Open ↗
07/14/2020123239575Open ↗
07/08/2020123239584Open ↗
Showing 3 of 49 on file for this type
▸Filing & Intake Forms71
▸BISEFILING COVER SHEET35
03/12/2019123128864Open ↗
07/10/2018123521894Open ↗
06/18/2018123553920Open ↗
Showing 3 of 35 on file for this type
▸BISBOROUGH INTAKE FORM22
05/04/2020123257411Open ↗
04/03/2020123521894Open ↗
03/25/2020123239575Open ↗
Showing 3 of 22 on file for this type
▸BISADDITIONAL INFORMATION14
07/10/2020123239575Open ↗
07/07/2020123239584Open ↗
04/20/2020123239584Open ↗
Showing 3 of 14 on file for this type
▸Other Documents4
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
12/26/2017123239575Open ↗
▸DOB NOWCalculations1
08/13/2026M01107962-I1Open ↗
▸DOB NOWPro Cert Restriction Exception (LL158/17)1
08/13/2026M01145679-I1Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026M01107962-I1Open ↗