| Firm | Filings | Most Recent |
|---|---|---|
| P GEORGOPOULOS ARCHITECT PC | 8 | 08/13/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EMILJANO CONSTRUCTION INC | General Contractor | 1 | 08/07/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | EMILJANO CONSTRUCTION INC | 08/06/2026 |
| DOB NOW | Full Demolition | Signed-off | BORI CONSTRUCTION CORP | 06/16/2026 |
| DOB NOW | Construction Fence | Permit Issued | EMILJANO CONSTRUCTION INC | 04/23/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/13/2026 | — | — | Air Conditioning Systems, Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/13/2026 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/13/2026 | — | — | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/06/2026 | Permit Issued | EMILJANO CONSTRUCTION INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/01/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/05/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 01/26/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 01/26/2026 | Concrete - Cast-In-Place | — | special |
| 01/26/2026 | Subgrade Inspections | — | special |
| 01/26/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 01/26/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 01/26/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 01/26/2026 | Subgrade Inspections | — | special |
| 12/08/2025 | Sprinkler Systems | — | special |
| 12/08/2025 | Final | — | progress |
| 12/08/2025 | Footing and Foundation | — | progress |
| 12/08/2025 | Alternative Materials - OTCR Buildings Bulletin Number | — | special |
| 12/08/2025 | Metering | — | energy_progress |
| 12/08/2025 | Air barrier — testing | — | energy_progress |
| 11/17/2025 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 11/17/2025 | Interior lighting power | — | energy_progress |
| 11/17/2025 | Air barrier - visual inspection | — | energy_progress |
| 11/17/2025 | Lighting controls | — | energy_progress |
| 11/17/2025 | Maintenance information | — | energy_progress |
| 11/17/2025 | Fenestration areas | — | energy_progress |
| 11/17/2025 | Lighting in dwelling units | — | energy_progress |
| 11/17/2025 | Exterior lighting power | — | energy_progress |
| 11/17/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 11/17/2025 | Protection of exposed foundation insulation | — | energy_progress |
| 11/17/2025 | Insulation placement and R values | — | energy_progress |