| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/24/2023 | $950K | — | Private party → Private party | $592/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MEI ARCHITECT PLLC | 2 | 12/17/2024 |
| MEHDI GHAZI, P.E., P.C. | 4 | 11/17/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| ALPHA HOME DESIGN LLC | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DAVID CONSTRUCTING NY, IN | General Contractor | 11 | 07/08/2026 |
| JOHN FITZGERALD PLBG &HTG | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MEHDI GHAZI, P.E. P.C. | 7129 | 4 | 12/17/2024 |
| TRIANGLE INSPECTION & TES | 7495 | 1 | 11/17/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | JOHN FITZGERALD PLBG &HTG | 10/08/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | DAVID CONSTRUCTING NY, IN | 05/27/2025 |
| DOB NOW | Earth Work | Permit Issued | DAVID CONSTRUCTING NY, IN | 11/19/2024 |
| DOB NOW | Construction Fence | Permit Issued | DAVID CONSTRUCTING NY, IN | 11/19/2024 |
| DOB NOW | Plumbing | Signed-off | JOHN FITZGERALD PLBG &HTG | 02/16/2024 |
| DOB NOW | Structural | Permit Issued | DAVID CONSTRUCTING NY, IN | 12/04/2023 |
| DOB NOW | General Construction | Permit Issued | DAVID CONSTRUCTING NY, IN | 12/01/2023 |
| DOB NOW | Construction Fence | Permit Issued | DAVID CONSTRUCTING NY, IN | 12/01/2023 |
| DOB NOW | Curb Cut | Permit Issued | DAVID CONSTRUCTING NY, IN | 12/01/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/17/2024 | Permit Issued | DAVID CONSTRUCTING NY, IN | Heating Systems | Heating Williamson GWA-233 233,000 BTU · Boiler ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/17/2024 | Signed-off | JOHN FITZGERALD PLBG &HTG | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/16/2025 | Complete | CL ELECTRICAL CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/17/2024 | Signed-off | JOHN FITZGERALD PLBG &HTG | Steel, Masonry, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/12/2023 | Permit Issued | DAVID CONSTRUCTING NY, IN | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/17/2024 | Signed-off | JOHN FITZGERALD PLBG &HTG | Earthwork |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/09/2024 | Chimneys and vents | MEHDI GHAZI | special |
| 12/09/2024 | Construction Operations Influencing Adjacent Structures | MEHDI GHAZI | special |
| 12/09/2024 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 12/09/2024 | Heating Systems | MEHDI GHAZI | special |
| 12/09/2024 | Mechanical Systems | MEHDI GHAZI | special |
| 12/09/2024 | Structural Stability – Alterations of existing buildings | MEHDI GHAZI | special |
| 12/09/2024 | Energy Code Compliance Inspections | MEHDI GHAZI | progress |
| 12/09/2024 | Final | MEHDI GHAZI | progress |
| 12/09/2024 | Fire-Resistance Rated Construction | MEHDI GHAZI | progress |
| 12/09/2024 | HVAC-R and service water heating system controls | MEHDI GHAZI | energy_progress |
| 12/09/2024 | HVAC-R and service water piping design and insulation | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Insulation placement and R values | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Interior lighting power | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Air barrier — testing | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Maintenance information | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Fenestration air leakage | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Air barrier - visual inspection | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Duct leakage testing, insulation and design | MEHDI GHAZI | energy_progress |
| 12/09/2024 | HVAC-R and service water heating equipment | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Permanent certificate | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Fenestration and door U-factor and product ratings | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Electric vehicle service equipment requirements | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Fenestration areas | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Protection of exposed foundation insulation | MEHDI GHAZI | energy_progress |
| 12/09/2024 | Ventilation and air distribution system | MEHDI GHAZI | energy_progress |