← Back
Public elementary, junior or senior high
East Side Elementary School, P.S. 267
209 EAST 63 STREET · Upper East Side-Lenox Hill-Roosevelt Island · BIN 1087680
💬 Discuss this project
1910Year Built
6Stories
W1Building Class
R8BZoning
42,000 sfGross Floor Area
1Units
LL97 Covered8 Open Violations 0 unresolved · 8 paperwork only ▸FISP: SWARMP
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF EDUCATION · 10,226 sf lot · 4.11 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCSCA1807/08/2026
NYC DEPARTMENT OF EDUCATION103/22/2026
DEPARTMENT OF EDUCATION903/22/2026
DEPARTMENT OF EDUCATION 0103/22/2026
DOE PS 39 C MEETH 040103/22/2026
DOE P.S. 59803/22/2026
DOE PS 59 040303/22/2026
DOE 040403/22/2026
DOE PS 59 MEETH203/22/2026
DEPT OF EDUCATION PS59 ME203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AME SERVICES INC405/10/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AME SERVICES803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
EVERLAST SCAFFOLDING INCGeneral Contractor1007/08/2026
KOKO CONTRACTING INCGeneral Contractor407/08/2026
ANA DIAZElectrical203/21/2026
ANTHONY COMOElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
20/20 INSPECTIONS INC1471205/10/2021
Building Lifecycle
All (89)Filed (4)Permit Issued (9)Signed Off (3)Facade (FISP) (12)Violation (60)Special Inspection (1)
03/10/2026
Violation issued (ECB, open)
Construction
03/10/2026
Violation issued (ECB, open)
Construction
03/10/2026
Violation issued (ECB, open)
Construction
05/19/2025
Violation issued (ECB, open)
Construction
02/28/2024
Violation issued (ECB, closed)
Construction
02/28/2024
Violation issued (ECB, closed)
Construction
10/10/2023
Signed off — Alteration
FILING FOR INSTALLATION OF TEMPORARY FENCE ON BEHALF OF CONTRACTOR
M00326207-I1
10/05/2023
Signed off — Alteration
FILING FOR PIPE SCAFFOLDING ON BEHALF OF CONTRACTOR - NO CHANGE IN USE, EGRESS, AND OCCUPANCY
M00329350-I1
10/05/2023
Signed off — Alteration
Filing for Installation of Sidewalk Shed on behalf of Contractor - NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M00329375-I1
08/01/2023
Cycle 9 facade report signed — SWARMP
06/20/2023
Cycle 9 facade report submitted
06/01/2023
Cycle 9 facade inspection completed
05/31/2023
Violation issued (ECB, closed)
Construction
03/09/2023
Violation issued (ECB, closed)
Construction
01/20/2023
Cycle 9 facade report submitted
01/20/2023
Cycle 9 facade report signed — UNSAFE
01/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/13/2023
Cycle 9 facade inspection completed
07/26/2022
Cycle 8 facade report signed — SAFE
06/01/2022
Cycle 8 facade report submitted
05/18/2022
Cycle 8 facade inspection completed
02/04/2022
Permit issued — Sidewalk Shed
M00329375-I1-SH
02/04/2022
Permit issued — Supported Scaffold
M00329350-I1-SF
12/23/2021
Permit issued — Construction Fence
M00326207-I1-FN
05/10/2021
Filed — Alteration
FILING FOR PIPE SCAFFOLDING ON BEHALF OF CONTRACTOR - NO CHANGE IN USE, EGRESS, AND OCCUPANCY
M00329350-P1
05/09/2021
Special inspection requirement — Post-installed Anchors
JACOB HAAS
02/24/2021
Violation issued (ECB, closed)
Construction
02/24/2021
Violation issued (ECB, closed)
Construction
02/02/2021
Permit issued — Supported Scaffold
M00329350-I1-SF
02/02/2021
Permit issued — Sidewalk Shed
M00329375-I1-SH
12/23/2020
Permit issued — Construction Fence
M00326207-I1-FN
11/19/2020
Violation issued (ECB, open)
Construction
09/24/2020
Violation issued (ECB, closed)
Construction
08/31/2020
Violation issued (ECB, closed)
Construction
08/31/2020
Violation issued (ECB, closed)
Construction
07/06/2020
Violation issued (ECB, open)
Elevators
07/06/2020
Violation issued (ECB, open)
Elevators
05/06/2020
Permit issued — Sidewalk Shed
M00329375-I1-SH
05/06/2020
Permit issued — Supported Scaffold
M00329350-I1-SF
04/30/2020
Permit issued — Construction Fence
M00326207-I1-FN
03/20/2020
Filed — Alteration
FILING FOR INSTALLATION OF TEMPORARY FENCE ON BEHALF OF CONTRACTOR
M00326207-I1
03/20/2020
Filed — Alteration
Filing for Installation of Sidewalk Shed on behalf of Contractor - NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M00329375-I1
03/19/2020
Filed — Alteration
FILING FOR PIPE SCAFFOLDING ON BEHALF OF CONTRACTOR - NO CHANGE IN USE, EGRESS, AND OCCUPANCY
M00329350-I1
02/10/2020
Violation issued (ECB, closed)
Construction
09/06/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/25/2019
Cycle 8 facade report submitted
03/25/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/21/2019
Cycle 8 facade report signed — UNSAFE
03/12/2019
Violation issued (ECB, closed)
Construction
03/12/2019
Violation issued (ECB, closed)
Construction
03/11/2019
Cycle 8 facade inspection completed
10/15/2018
Violation issued (ECB, open)
Local Law
08/14/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/13/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
07/31/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/25/2018
Violation issued (ECB, closed)
Construction
01/25/2018
Violation issued (ECB, closed)
Construction
01/25/2018
Violation issued (ECB, closed)
Construction
03/06/2017
Violation issued (ECB, closed)
Construction
03/06/2017
Violation issued (ECB, closed)
Construction
Latest 60 of 89 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedSigned-offEVERLAST SCAFFOLDING02/04/2022
DOB NOWSupported ScaffoldSigned-offEVERLAST SCAFFOLDING02/04/2022
DOB NOWConstruction FenceSigned-offKOKO CONTRACTING INC12/23/2021
DOB NOWSupported ScaffoldSigned-offEVERLAST SCAFFOLDING02/02/2021
DOB NOWSidewalk ShedSigned-offEVERLAST SCAFFOLDING02/02/2021
DOB NOWConstruction FenceSigned-offKOKO CONTRACTING INC12/23/2020
DOB NOWSidewalk ShedSigned-offEVERLAST SCAFFOLDING05/06/2020
DOB NOWSupported ScaffoldSigned-offEVERLAST SCAFFOLDING05/06/2020
DOB NOWConstruction FenceSigned-offKOKO CONTRACTING INC04/30/2020
BISOTISSUEDKOKO CONTRACTING INC05/16/2022
BISEQISSUEDKOKO CONTRACTING INC04/16/2021
BISOTISSUEDKOKO CONTRACTING INC12/08/2020
BISEQISSUEDABAX INC09/21/2020
BISEQISSUEDKOKO CONTRACTING INC04/17/2020
BISEQISSUEDABAX INC08/14/2018
BISEQISSUEDABAX INC08/16/2017
BISPLISSUEDGEORGE BRESLAW & SONS INC04/01/2009
BISFSISSUEDAGEE HEATING SVC CORP02/10/2009
BISMHISSUEDLENDLEASE(US)CONSTRUCTION01/13/2009
BISOTISSUEDAMERICAN ENVIRONMENTAL AS04/02/2008
BISEQISSUEDTRI-STATE DISMANTLING CORP03/10/2008
BISSDISSUEDMANENGEERING BUREAU INC02/26/2008
BISSPISSUEDMANENGEERING BUREAU INC02/26/2008
BISOTISSUEDAMERICAN ENVIRONMENTAL AS01/29/2008
BISEQISSUEDTRI-STATE DISMANTLING CORP12/31/2007
BISPLISSUEDGEORGE BRESLAW & SONS12/04/2007
BISEQISSUEDTRI-STATE DISMANTLING CORP10/25/2007
BIS—ISSUEDLENDLEASE(US)CONSTRUCTION10/16/2007
BISEQISSUEDALL SAFE LLC10/15/2007
BISOTISSUEDTRI-STATE DISMANTLING CORP08/24/2007
BISEQISSUEDYORK SCAFFOLDING & EQUIPTMENT05/03/1991
3 projects · most recent 10/13/2025
General Wiring
FiledStatusContractorScope
10/13/2025CompleteDIAZ ELECTRIC OF NEW YORKGeneral Wiring
12/07/2022CompleteANCO ELECTL CONTCTNG INCGeneral Wiring
04/29/2020CompleteSTANCO SYSTEM ELEC'L CONT—
▾Special Inspection Requirements (DOB NOW) — 1
DateRequirementInspectorRole
05/09/2021Post-installed AnchorsJACOB HAASspecial
▾Documents — 109 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/03/2026M00329350-I1Request digital key ↗
09/03/2026M00329350-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
09/05/2026M00326207-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00329375-I1Request digital key ↗
▸Applications & Permits19
▸BISPLAN / WORK APPROVAL APPLICATION11
03/26/2009110035747Open ↗
08/07/2008110035747Open ↗
08/01/2008110301414Open ↗
Showing 3 of 11 on file for this type
▸BISWORK PERMIT APPLICATION8
02/10/2009110301414Open ↗
01/14/2009110301414Open ↗
09/12/2008110163368Open ↗
Showing 3 of 8 on file for this type
▸Seals & Professional Certifications17
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION9
05/19/2009110301414Open ↗
05/19/2009110301414Open ↗
05/19/2009110301414Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/05/2026M00329375-I1Open ↗
09/03/2026M00329350-I1Open ↗
09/03/2026M00329350-P1Open ↗
Showing 3 of 4 on file for this type
▸BISPC FULL REPORT1
01/29/2008110086807Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
01/29/2008110086807Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
01/29/2008110086807Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026M00329350-P1Open ↗
▸Trade Schedules & Equipment17
▸BISSCHEDULE B - PLUMBING7
04/08/2009110035907Open ↗
03/26/2009110035747Open ↗
08/07/2008110035747Open ↗
Showing 3 of 7 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT3
03/09/2009110301414Open ↗
12/04/2008110301414Open ↗
08/01/2008110301414Open ↗
▸BISSELF-CERT PLUMBING NOTICE3
07/31/2008110035747Open ↗
07/29/2008110035907Open ↗
07/24/2008110035907Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
08/29/2009110035729Open ↗
▸BISSPRINKLER INSP REPORT : FP-851
07/29/2008110035907Open ↗
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
10/28/2008110035747Open ↗
▸BISSTANDPIPE INSP REPORT : FP-841
07/31/2008110035747Open ↗
▸Safety & Tenant Protection4
▸DOB NOWNYCSCA - Approved Site Safety Plans4
09/05/2026M00329375-I1Open ↗
09/03/2026M00329350-I1Open ↗
09/03/2026M00329350-P1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos8
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER4
08/01/2008110301414Open ↗
07/23/2008110298954Open ↗
05/09/2008110163368Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS INSPECTION REPORT4
08/01/2008110301414Open ↗
11/26/2007110035907Open ↗
11/26/2007110035729Open ↗
Showing 3 of 4 on file for this type
▸Approvals, Objections & Sign-offs25
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
08/29/2009110035729Open ↗
06/04/2009110035907Open ↗
06/02/2009110035747Open ↗
Showing 3 of 7 on file for this type
▸BISADMINISTRATIVE OBJECTIONS7
08/01/2008110301414Open ↗
07/23/2008110298954Open ↗
05/09/2008110163368Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter4
09/05/2026M00329375-I1Open ↗
09/03/2026M00329350-I1Open ↗
09/03/2026M00329350-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)4
09/05/2026M00329375-I1Open ↗
09/03/2026M00329350-P1Open ↗
09/03/2026M00329350-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)3
09/05/2026M00329375-I1Open ↗
09/03/2026M00329350-I1Open ↗
08/13/2026M00326207-I1Open ↗
▸Cost, Insurance & Ownership8
▸BISCOST AFFIDAVIT8
08/29/2009110035729Open ↗
06/04/2009110035907Open ↗
06/02/2009110035747Open ↗
Showing 3 of 8 on file for this type
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
12/04/2008110301414Open ↗
▸BISEFILING COVER SHEET1
07/23/2008110298954Open ↗
▸Other Documents5
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal4
09/05/2026M00329375-I1Open ↗
09/03/2026M00329350-I1Open ↗
09/03/2026M00329350-P1Open ↗
Showing 3 of 4 on file for this type
▸BISSEPTIC - SUPPORTING DOCUMENTATION1
02/13/2009110298954Open ↗