| Owner | Filings | Most Recent |
|---|---|---|
| TYH 2094 RYER LLC | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/30/2024 | $700K | — | Private party → TYH 2094 RYER LLC | $245/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NIC 88 CORP | 4 | 09/26/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| BASIC GROUPS | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CUBE BUILDERS GROUP NY | General Contractor | 2 | 07/08/2026 |
| PIPESTYLISTS, INC | Plumbing | 2 | 07/08/2026 |
| BDS ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NIC 88 CORP | 8371 | 2 | 09/26/2025 |
| NIC DESIGN INC | 9758 | 2 | 02/18/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | T & T PLUMBING INC | 06/27/2025 |
| DOB NOW | General Construction | Signed-off | CUBE BUILDERS GROUP NY | 03/20/2025 |
| DOB NOW | Mechanical Systems | Signed-off | CUBE BUILDERS GROUP NY | 02/20/2025 |
| DOB NOW | Plumbing | Signed-off | T & T PLUMBING INC | 02/20/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/23/2026 | Permit Issued | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 10/08/2025 | Permit Issued | BDS ELECTRIC CORP. | General Wiring, Lighting |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/26/2025 | Insulation placement and R values | Eric Sun | energy_progress |
| 09/26/2025 | Fenestration and door U-factor and product ratings | Eric Sun | energy_progress |
| 09/26/2025 | Interior lighting power | Eric Sun | energy_progress |
| 09/26/2025 | Maintenance information | Eric Sun | energy_progress |
| 09/26/2025 | HVAC-R and service water piping design and insulation | Eric Sun | energy_progress |
| 09/26/2025 | Duct leakage testing, insulation and design | Eric Sun | energy_progress |
| 09/26/2025 | Fire-Resistant Penetrations and Joints | Eric Sun | special |
| 09/26/2025 | Mechanical Systems | Eric Sun | special |
| 09/26/2025 | Energy Code Compliance Inspections | Eric Sun | progress |
| 09/26/2025 | Final | Eric Sun | progress |
| 09/26/2025 | Fire-Resistance Rated Construction | Eric Sun | progress |
| 09/26/2025 | Air barrier - visual inspection | Eric Sun | energy_progress |
| 09/26/2025 | HVAC-R and service water heating system controls | Eric Sun | energy_progress |
| 09/26/2025 | Fenestration areas | Eric Sun | energy_progress |
| 09/26/2025 | HVAC-R and service water heating equipment | Eric Sun | energy_progress |
| 09/26/2025 | Fenestration air leakage | Eric Sun | energy_progress |
| 08/13/2025 | Energy Code Compliance Inspections | Eric Sun | progress |
| 08/13/2025 | HVAC-R and service water heating equipment | Eric Sun | energy_progress |
| 08/13/2025 | HVAC-R and service water piping design and insulation | Eric Sun | energy_progress |
| 08/13/2025 | HVAC-R and service water heating system controls | Eric Sun | energy_progress |
| 08/13/2025 | Fire-Resistant Penetrations and Joints | Eric Sun | special |