← Back
One family attached or semi-detached
21-04 144 STREET
QUEENS · BIN 4099426
💬 Discuss this project
1970Year Built
2Stories
A5Building Class
R3-1Zoning
1,831 sfGross Floor Area
1Units
One family attached or semi-detached · 2,156 sf lot · 0.85 FAR built · Flood zone X
Locations of Work
Electrical
Permit Issued — active, not yet Signed-off
RoofUnder Construction1 filing · 8 docs
1 job · most recent 09/11/2026
General Wiring
FiledStatusContractorScope
09/11/2026Permit IssuedSUNRUN SOLAR ELECTL CORPGeneral Wiring
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Inspection (1)Special Inspection (5)
09/10/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
08/27/2026
Permit issued — Solar
Q01448248-I1-SL
08/20/2026
Filed — Alteration
Q01448248-I1
08/20/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
08/20/2026
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
08/19/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
08/19/2026
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
08/19/2026
Special inspection requirement — Final
Walid Abdulla
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/07/2024$1.1M—Private party → Private party$573/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC108/20/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor108/30/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272108/20/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedSUNRUN INSTALLATION SVC08/27/2026
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
09/10/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
08/20/2026Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
08/20/2026Air barrier - visual inspectionWalid Abdullaenergy_progress
08/19/2026Fire-Resistant Penetrations and JointsWalid Abdullaspecial
08/19/2026Energy Code Compliance InspectionsWalid Abdullaprogress
08/19/2026FinalWalid Abdullaprogress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/21/2026Q01448248-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/28/2026Q01448248-I1Open ↗
08/28/2026Q01448248-I1Open ↗
08/28/2026Q01448248-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026Q01448248-I1Open ↗
08/28/2026Q01448248-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/21/2026Q01448248-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/21/2026Q01448248-I1Open ↗