2,993 sfGross Floor Area
1Units
0 Open Violations
Predominantly retail with other uses · Owner of record: 21-02 USA, LLC · 2,997 sf lot · 1 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalFire ProtectionGeneral
Roof3p · 2 filings · 16 docs
Floor 177p · 2 filings · 20 docs
Mezzanine75p · 2 filings · 20 docs
Cellar73p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
21-02 USA1809/13/2026
CTI CONSTRUCTION603/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
FANG ARCHITECT1107/22/2026
AGT ARCHITECTURE P.C.208/04/2025
ALAN YANG ARCHITECTURE DPC107/16/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
FANG ARCHITECT203/21/2026
LEADING GREEN ENERGY CONSTRUCTION103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CTI CONSTRUCTION INCGeneral Contractor1604/09/2026
TRI STATE PLBG & HTG INCPlumbing407/08/2026
LEADING GREEN ENERGY CONGeneral Contractor303/21/2026
RRP PLUMBINGPlumbing103/22/2026
KWONG MING ELECTRIC INC 003828General Contractor103/22/2026
RRP PLUMBING CORPFire Protection107/08/2026
AI FANG WUElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A & T DESIGN GROUP LLC10881107/22/2026
TRIANGLE INSPECTION & TES7495208/04/2025
ALAN YANG ARCHITECTURE9490107/16/2025
Building Lifecycle
All (90)Filed (14)Permit Issued (16)Signed Off (6)Violation (6)Inspection (12)Objection (6)Special Inspection (30)
07/22/2026
Filed — New Building
PROPOSED A NEW ATTACHED 1-STORY COMMERCIAL BUILDING
Q00561468-P5
07/22/2026
Special inspection requirement — Insulation placement and R values
ROBERT LIN
07/22/2026
Special inspection requirement — Lighting controls
ROBERT LIN
07/22/2026
Special inspection requirement — Mechanical Systems
ROBERT LIN
07/22/2026
Special inspection requirement — HVAC-R and service water heating equipment
ROBERT LIN
07/22/2026
Special inspection requirement — Exterior lighting power
ROBERT LIN
07/22/2026
Special inspection requirement — Shutoff dampers
ROBERT LIN
07/22/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ROBERT LIN
07/22/2026
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
ROBERT LIN
07/22/2026
Special inspection requirement — Final
ROBERT LIN
07/22/2026
Special inspection requirement — Interior lighting power
ROBERT LIN
07/22/2026
Special inspection requirement — Protection of exposed foundation insulation
ROBERT LIN
07/22/2026
Special inspection requirement — Metering
ROBERT LIN
07/22/2026
Special inspection requirement — Air barrier — testing
ROBERT LIN
07/22/2026
Special inspection requirement — HVAC-R and service water heating system controls
ROBERT LIN
07/22/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
ROBERT LIN
07/22/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
ROBERT LIN
07/22/2026
Special inspection requirement — Heating Systems
ROBERT LIN
07/22/2026
Special inspection requirement — Masonry
ROBERT LIN
07/22/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
ROBERT LIN
07/22/2026
Special inspection requirement — Energy Code Compliance Inspections
ROBERT LIN
07/22/2026
Special inspection requirement — Fire-Resistance Rated Construction
ROBERT LIN
07/22/2026
Special inspection requirement — Footing and Foundation
ROBERT LIN
07/22/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
ROBERT LIN
07/22/2026
Special inspection requirement — Maintenance information
ROBERT LIN
07/22/2026
Special inspection requirement — Fenestration air leakage
ROBERT LIN
07/22/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
ROBERT LIN
07/22/2026
Special inspection requirement — Fenestration areas
ROBERT LIN
07/22/2026
Special inspection requirement — Air barrier - visual inspection
ROBERT LIN
07/22/2026
Special inspection requirement — Concrete - Cast-In-Place
ROBERT LIN
05/13/2026
Filed — New Building
PROPOSED A NEW ATTACHED 1-STORY COMMERCIAL BUILDING
Q00561468-P4
04/16/2026
Special inspection requirement — Concrete - Cast-In-Place
ROBERT LIN
03/13/2026
Signed off — Alteration
FILED STRUCTURAL WORK FOR A NEW 1-STORY COMMERCIAL BUILDING
Q00684102-I1
01/29/2026
Signed off — Alteration
Q01252981-I1
01/12/2026
Signed off — Alteration
HEREWITH FILED PLUMBING WORK FOR A NEW 1-STORY COMMERCIAL BUILDING.
Q00926084-I1
01/09/2026
Signed off — Alteration
HEREWITH FILED PLUMBING WORK FOR A NEW 1-STORY COMMERCIAL BUILDING.
Q00926084-S1
01/08/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/01/2025
Signed off — New Building
PROPOSED A NEW ATTACHED 1-STORY COMMERCIAL BUILDING
Q00561468-S1
11/28/2025
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
11/14/2025
Signed off — Alteration
INSTALL TEMP. CONSTRUCTION FENCE. FILED IN CONJUNCTION WITH NB #Q00561474, #Q00561470, #Q00561468, #Q00561457.
Q00908899-I1
11/14/2025
Permit issued — Curb Cut
Q00561468-S1-CC
10/07/2025
Filed — New Building
PROPOSED A NEW ATTACHED 1-STORY COMMERCIAL BUILDING
Q00561468-P3
08/28/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
08/23/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/18/2025
Permit issued — Construction Fence
Q00908899-I1-FN
08/14/2025
Permit issued — Plumbing
Q00926084-I1-PL
08/04/2025
Filed — Alteration
HEREWITH FILED PLUMBING WORK FOR A NEW 1-STORY COMMERCIAL BUILDING.
Q00926084-P1
07/24/2025
Permit issued — Solar
Q01252981-I1-SL
07/16/2025
Filed — Alteration
Q01252981-I1
06/17/2025
Violation issued (ECB, closed)
Construction
05/16/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
05/13/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
05/06/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
05/06/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
04/10/2025
Objection resolved — Addressed
03/27/2025
Objection resolved — Addressed
03/27/2025
Objection resolved — Addressed
03/05/2025
Violation issued (ECB, closed)
Unknown
02/11/2025
Permit issued — Foundation
Q00561468-I1-GC-CX
12/02/2024
Inspection — Pass-Final House Connection
Pass
View inspection ↗
Latest 60 of 90 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offCTI CONSTRUCTION INC11/14/2025
DOB NOWConstruction FenceSigned-offCTI CONSTRUCTION INC08/18/2025
DOB NOWPlumbingSigned-offDW PLUMBING INC08/14/2025
DOB NOWSolarSigned-offLEADING GREEN ENERGY CON07/24/2025
DOB NOWFoundationPermit IssuedCTI CONSTRUCTION INC02/11/2025
DOB NOWStructuralSigned-offCTI CONSTRUCTION INC11/25/2024
DOB NOWSprinklersSigned-offRALPH W. LANDOLFI JR.09/27/2024
DOB NOWGeneral ConstructionPermit IssuedCTI CONSTRUCTION INC09/27/2024
DOB NOWConstruction FenceSigned-offCTI CONSTRUCTION INC09/12/2024
DOB NOWPlumbingSigned-offDW PLUMBING INC08/06/2024
DOB NOWPlumbingSigned-offDW PLUMBING INC03/28/2024
DOB NOWFoundationPermit IssuedCTI CONSTRUCTION INC02/16/2024
DOB NOWStructuralSigned-offCTI CONSTRUCTION INC11/28/2023
DOB NOWFoundationPermit IssuedCTI CONSTRUCTION INC11/27/2023
DOB NOWConstruction FenceSigned-offCTI CONSTRUCTION INC09/25/2023
DOB NOWMechanical SystemsPermit IssuedCTI CONSTRUCTION INC05/23/2022
1 project · most recent 07/22/2026
Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
07/22/2026Signed-offCTI CONSTRUCTION INCAir Conditioning Systems, Heating Systems
Cooling
Fujitsu MODEL: ASUG12LMAS 16,000 BTU · Split System ×4
Heating
Modine HD 125AS0111FDAN 125,000 BTU · Unit Heater ×6
MODEL: HD 125AS0111FDAN, SERIAL # 43010017090225-2285 125,000 BTU · Unit Heater ×1
MODEL: HD 125AS0111FDAN, SERIAL # 43010017090225-2286 125,000 BTU · Unit Heater ×1
2 projects · most recent 10/28/2025
General Wiring
FiledStatusContractorScope
10/28/2025CompleteKWONG MING ELECTRIC INC—
06/04/2025CompleteA.C. MORGAN ELECTRICGeneral Wiring
1 project · most recent 07/22/2026
FiledStatusContractorScope
07/22/2026Signed-offCTI CONSTRUCTION INC6 scope_items
1 project · most recent 07/22/2026
Earthwork
FiledStatusContractorScope
07/22/2026Signed-offCTI CONSTRUCTION INCEarthwork
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
01/08/2026Pass-Final CND-Occupancy InspectionPassView ↗
11/28/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
08/28/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/23/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/16/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
05/13/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/06/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/06/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/02/2024Pass-Final House ConnectionPassView ↗
10/09/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
09/10/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
04/18/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
07/22/2026Lighting controlsROBERT LINenergy_progress
07/22/2026Concrete - Cast-In-PlaceROBERT LINspecial
07/22/2026Excavations - Sheeting, Shoring, and BracingROBERT LINspecial
07/22/2026Exterior Insulation and Finish Systems (EIFS)ROBERT LINspecial
07/22/2026Fire-Resistant Penetrations and JointsROBERT LINspecial
07/22/2026Heating SystemsROBERT LINspecial
07/22/2026MasonryROBERT LINspecial
07/22/2026Mastic and Intumescent Fire-resistant CoatingsROBERT LINspecial
07/22/2026Mechanical SystemsROBERT LINspecial
07/22/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationROBERT LINspecial
07/22/2026Energy Code Compliance InspectionsROBERT LINprogress
07/22/2026FinalROBERT LINprogress
07/22/2026Fire-Resistance Rated ConstructionROBERT LINprogress
07/22/2026Footing and FoundationROBERT LINprogress
07/22/2026Interior lighting powerROBERT LINenergy_progress
07/22/2026HVAC-R and service water heating equipmentROBERT LINenergy_progress
07/22/2026Insulation placement and R valuesROBERT LINenergy_progress
07/22/2026HVAC-R and service water piping design and insulationROBERT LINenergy_progress
07/22/2026Maintenance informationROBERT LINenergy_progress
07/22/2026Protection of exposed foundation insulationROBERT LINenergy_progress
07/22/2026Fenestration air leakageROBERT LINenergy_progress
07/22/2026Fenestration and door U-factor and product ratingsROBERT LINenergy_progress
07/22/2026MeteringROBERT LINenergy_progress
07/22/2026Exterior lighting powerROBERT LINenergy_progress
07/22/2026Fenestration areasROBERT LINenergy_progress
Latest 25 of 150.
▾Documents — 115 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch14
08/26/2026Q00684102-P1Request digital key ↗
08/26/2026Q00684102-I1Request digital key ↗
08/24/2026Q00908899-I1Request digital key ↗
Showing 3 of 14 on file for this type
▸Zoning, Tax Lot & Property Records11
▸DOB NOWZD1: DOB Zoning Diagram6
08/16/2026Q00561468-P4Open ↗
08/16/2026Q00561468-P5Open ↗
08/13/2026Q00561468-P2Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWZoning Exhibit form (1-5)3
08/16/2026Q00561468-P4Open ↗
08/16/2026Q00561468-P5Open ↗
08/16/2026Q00561468-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/16/2026Q00561468-I1Open ↗
08/13/2026Q00561468-I1Open ↗
▸Seals & Professional Certifications59
▸DOB NOWProgress Inspector Seal & Signature27
08/31/2026Q00561468-P4Open ↗
08/31/2026Q00561468-P4Open ↗
08/31/2026Q00561468-P4Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature18
08/31/2026Q00561468-P4Open ↗
08/31/2026Q00561468-P4Open ↗
08/29/2026Q00926084-P1Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature14
08/26/2026Q00684102-I1Open ↗
08/24/2026Q00908899-I1Open ↗
08/24/2026Q00926084-I1Open ↗
Showing 3 of 14 on file for this type
▸Trade Schedules & Equipment4
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)4
08/13/2026Q00561468-P3Open ↗
08/13/2026Q00561468-P2Open ↗
08/13/2026Q00561468-P1Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection9
▸DOB NOWStreet Tree Checklist6
08/16/2026Q00561468-P2Open ↗
08/16/2026Q00561468-P3Open ↗
08/16/2026Q00561468-P4Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00561468-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/16/2026Q00561468-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/16/2026Q00561468-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/16/2026Q00561468-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01252981-I1Open ↗
▸Cost, Insurance & Ownership2
▸DOB NOWCertification by Insurance Broker or Agency1
08/13/2026Q00561468-I1Open ↗
▸DOB NOWCertificate of Insurance1
08/13/2026Q00561468-I1Open ↗
▸Other Documents14
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone6
08/16/2026Q00561468-P4Open ↗
08/16/2026Q00561468-P5Open ↗
08/13/2026Q00561468-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSite Survey: Initial5
08/16/2026Q00561468-P4Open ↗
08/16/2026Q00561468-P5Open ↗
08/13/2026Q00561468-P3Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWAdditional Insured Authorizations1
08/13/2026Q00561468-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q00561468-I1Open ↗
▸DOB NOWFinal Survey1
08/16/2026Q00561468-I1Open ↗