| Owner | Filings | Most Recent |
|---|---|---|
| NYC SCHOOL CONSTRUCTION | 21 | 07/25/2026 |
| NYC SCHOOL CONSTRUCTION AUTHORITY | 82 | 07/10/2026 |
| NYC DEPARTMENT OF EDUCATION | 1 | 03/22/2026 |
| DEPARTMENT OF EDUCATION | 9 | 03/22/2026 |
| DOE 040 | 3 | 03/22/2026 |
| DOE Q 485 040 | 2 | 03/22/2026 |
| DOE GROVER CLEVELAND 040 | 9 | 03/22/2026 |
| BOARD OF EDUCATION 040 | 1 | 03/22/2026 |
| NYC BOARD OF EDUCATION040 | 1 | 03/22/2026 |
| NEW YORK CITY SCHOOL CONSTRUCTION AUTHORITY | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| EDWIN DEGUZMAN | 1 | 03/27/2026 |
| HRM ENGINEERING SERVICES, PC | 7 | 10/20/2025 |
| SALAM & GIACALONE ARCHITECTS PC | 4 | 10/17/2025 |
| AK CONSULTING SERVICES, INC | 1 | 06/19/2025 |
| VELOCITY ARCHITECTURAL SERVICES PLL | 10 | 03/14/2024 |
| EME CONSULTING ENGINEERING GROUP | 1 | 10/27/2023 |
| MARIO MENDOZA BLANCO | 6 | 08/25/2023 |
| GIUSEPPE TULUMELLO, AIA | 2 | 07/27/2023 |
| STV INCORPORATED | 4 | 02/22/2023 |
| DVL CONSULTING ENGINEERS, INC | 1 | 02/09/2023 |
| AME SERVICES INC | 3 | 01/15/2023 |
| DRG ARCHITECTS | 1 | 11/29/2022 |
| NSR CONSULTING ENGINEERING LLC | 2 | 09/12/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| CASO ASSOCIATES | 4 | 03/21/2026 |
| PRECISION 3SIXTY NYC, INC | 38 | 03/21/2026 |
| RA | 8 | 03/21/2026 |
| AME SERVICES | 6 | 03/21/2026 |
| AK CONSULTING SERVICES | 2 | 03/21/2026 |
| STV | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SAFECON BUILDERS CORP | General Contractor | 11 | 07/08/2026 |
| ON TOP RENOVATION INC | General Contractor | 10 | 07/08/2026 |
| VARSITY PLBG AND HTG INC | Plumbing | 7 | 07/19/2026 |
| CHAPMAN & EVANS INC | General Contractor | 5 | 07/08/2026 |
| EMPIRE CONTROL ABATEMENT | General Contractor | 5 | 07/08/2026 |
| NIKHI CONTRACTING CORP | General Contractor | 5 | 07/08/2026 |
| FORSYTHE P&H CORP | Plumbing | 5 | 07/10/2026 |
| A.T.J. ELECTRICAL CO INC | General Contractor | 3 | 07/25/2026 |
| I.M.P. PLBG. & HTG. CORP | Plumbing | 3 | 07/08/2026 |
| AIR-TEK MECHANICAL INC | General Contractor | 3 | 03/21/2026 |
| EVERLAST SCAFFOLDING INC | General Contractor | 2 | 07/08/2026 |
| CHARAN ELEC'L ENTERP'S IN | Electrical | 2 | 03/22/2026 |
| HEXAGON CONST & ELECL GRP | Electrical | 1 | 03/22/2026 |
| MNBC ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| CEDOMIR MARA | Electrical | 1 | 03/21/2026 |
| ELECTRIC FIXX INC | Electrical | 1 | 03/22/2026 |
| PRINCE ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| UNIVERSAL TESTING AND INS | 400 | 36 | 03/27/2026 |
| JPC LOGISTICS DBA JPCL EN | 351 | 1 | 10/27/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | A.T.J. ELECTRICAL CO INC | 07/23/2026 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG AND HTG INC | 07/17/2026 |
| DOB NOW | Plumbing | Permit Issued | FORSYTHE P&H CORP | 07/08/2026 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG AND HTG INC | 05/06/2026 |
| DOB NOW | General Construction | Permit Issued | NIKHI CONTRACTING CORP | 04/01/2026 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG AND HTG INC | 03/04/2026 |
| DOB NOW | General Construction | Permit Issued | A.T.J. ELECTRICAL CO INC | 02/26/2026 |
| DOB NOW | Support of Excavation | Permit Issued | SAFECON BUILDERS CORP | 01/21/2026 |
| DOB NOW | General Construction | Permit Issued | SAFECON BUILDERS CORP | 10/06/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | AIR-TEK MECHANICAL INC | 08/14/2025 |
| DOB NOW | Plumbing | Permit Issued | FORSYTHE P&H CORP | 08/07/2025 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG AND HTG INC | 07/21/2025 |
| DOB NOW | General Construction | Permit Issued | A.T.J. ELECTRICAL CO INC | 07/08/2025 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG AND HTG INC | 04/29/2025 |
| DOB NOW | Construction Fence | Permit Issued | SAFECON BUILDERS CORP | 04/28/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | ON TOP RENOVATION INC | 02/27/2025 |
| DOB NOW | General Construction | Permit Issued | SAFECON BUILDERS CORP | 10/15/2024 |
| DOB NOW | Construction Fence | Permit Issued | SAFECON BUILDERS CORP | 10/15/2024 |
| DOB NOW | Plumbing | Permit Issued | FORSYTHE P&H CORP | 09/06/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | ON TOP RENOVATION INC | 05/03/2024 |
| DOB NOW | General Construction | Permit Issued | ON TOP RENOVATION INC | 04/12/2024 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG AND HTG INC | 04/12/2024 |
| DOB NOW | General Construction | Permit Issued | NIKHI CONTRACTING CORP | 04/12/2024 |
| DOB NOW | Construction Fence | Permit Issued | SAFECON BUILDERS CORP | 02/26/2024 |
| DOB NOW | Plumbing | Signed-off | I.M.P. PLBG. & HTG. CORP | 01/29/2024 |
| DOB NOW | Construction Fence | Permit Issued | SAFECON BUILDERS CORP | 01/11/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | CHAPMAN EVANS | 10/17/2023 |
| DOB NOW | General Construction | Permit Issued | SAFECON BUILDERS CORP | 10/05/2023 |
| DOB NOW | Plumbing | Permit Issued | FORSYTHE P&H CORP | 10/05/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | EVERLAST SCAFFOLDING | 07/20/2023 |
| DOB NOW | Supported Scaffold | Signed-off | EVERLAST SCAFFOLDING | 07/14/2023 |
| DOB NOW | General Construction | Signed-off | EMPIRE CONTROL ABATEMENT | 07/12/2023 |
| DOB NOW | Mechanical Systems | Signed-off | EMPIRE CONTROL ABATEMENT | 07/12/2023 |
| DOB NOW | General Construction | Permit Issued | ON TOP RENOVATION INC | 07/03/2023 |
| DOB NOW | General Construction | Permit Issued | NIKHI CONTRACTING CORP | 04/14/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | CHAPMAN EVANS | 04/13/2023 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG AND HTG INC | 04/13/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | CHAPMAN EVANS | 03/31/2023 |
| DOB NOW | General Construction | Permit Issued | NIKHI CONTRACTING CORP | 03/30/2023 |
| DOB NOW | Construction Fence | Permit Issued | SAFECON BUILDERS CORP | 02/10/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/27/2023 | — | — | Heating and Air Conditioning Systems | Heat / Cool Fujitsu ASUB36TLAV2 38,000 BTU · Fan Coil Indoor ×24 AOU120RLAVL 135,000 BTU · Condensing Unit ×6 AOU72RLAVL 81,000 BTU · Condensing Unit ×1 |
| 08/25/2023 | Permit Issued | NIKHI CONTRACTING CORP | Ventilation Systems | |
| 02/22/2023 | Permit Issued | ON TOP RENOVATION INC | Associated Ducts and Piping | Ducts & Piping Us Draft TRV-2 74 CFM · Exhaust Fan ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/27/2026 | Permit Issued | VARSITY PLBG AND HTG INC | Water/Sanitary |
| 10/20/2025 | Permit Issued | VARSITY PLBG AND HTG INC | Water/Sanitary |
| 08/25/2023 | Permit Issued | FORSYTHE P&H CORP | Gas, Water/Sanitary |
| 02/22/2023 | Permit Issued | VARSITY PLBG AND HTG INC | Gas, Water/Sanitary |
| 02/09/2023 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/21/2026 | Complete | A & S ELECTRIC INC. | — |
| 05/21/2026 | Complete | A & S ELECTRIC INC. | — |
| 05/19/2026 | Complete | A & S ELECTRIC INC. | — |
| 05/08/2026 | Complete | A & S ELECTRIC INC. | — |
| 09/10/2025 | Permit Issued | A.T.J. ELECTRICAL CO.INC. | General Wiring |
| 08/14/2025 | Permit Issued | LVI NYC ELECTRICAL INC | Lighting |
| 07/09/2025 | Complete | A.T.J. ELECTRICAL CO.INC. | General Wiring |
| 05/08/2025 | Permit Issued | MNBC ELECTRICAL CORP | General Wiring |
| 09/05/2024 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 05/15/2024 | Complete | ANCO ELECTL CONTCTNG INC | — |
| 04/28/2024 | Permit Issued | AUJLA ELECTRIC CORP | HVAC Wiring |
| 10/16/2023 | Complete | ANTONIO CERIELLO ELEC INC | — |
| 07/19/2023 | Complete | DORION NORTON ELECL CONT | — |
| 04/13/2023 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 03/22/2023 | Complete | HEXAGON CONST & ELECL GRP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/15/2023 | Permit Issued | SAFECON BUILDERS CORP | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/14/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/15/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/28/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/20/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/19/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/19/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/18/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 01/24/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/18/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/22/2025 | Post-installed Anchors | NELSON LOPEZ | special |
| 10/22/2025 | Fire-Resistant Penetrations and Joints | NELSON LOPEZ | special |
| 10/22/2025 | Fire-Resistant Penetrations and Joints | NELSON LOPEZ | special |
| 04/22/2025 | Excavations - Sheeting, Shoring, and Bracing | NELSON LOPEZ | special |
| 04/10/2025 | Post-installed Anchors | NELSON LOPEZ | special |
| 04/10/2025 | Fire-Resistant Penetrations and Joints | NELSON LOPEZ | special |
| 04/10/2025 | Final | NELSON LOPEZ | progress |
| 04/10/2025 | Mechanical Systems | NELSON LOPEZ | special |
| 04/10/2025 | Fire-Resistant Penetrations and Joints | NELSON LOPEZ | special |
| 04/08/2025 | Final | NELSON LOPEZ | progress |
| 04/08/2025 | Mechanical Systems | NELSON LOPEZ | special |
| 01/31/2025 | Mechanical Systems | — | special |
| 01/31/2025 | Final | — | progress |
| 03/19/2024 | Fire-Resistant Penetrations and Joints | NELSON LOPEZ | special |
| 02/26/2024 | Final | NELSON LOPEZ | progress |
| 02/26/2024 | Mechanical Systems | NELSON LOPEZ | special |
| 02/19/2024 | Fire-Resistant Penetrations and Joints | NELSON LOPEZ | special |
| 02/19/2024 | Final | NELSON LOPEZ | progress |
| 02/19/2024 | Mechanical Systems | NELSON LOPEZ | special |
| 10/25/2023 | Final | Asma Hashmi | progress |
| 10/25/2023 | Mechanical Systems | Asma Hashmi | special |
| 10/25/2023 | Post-installed Anchors | Asma Hashmi | special |
| 10/25/2023 | Fire-Resistant Penetrations and Joints | Asma Hashmi | special |
| 09/13/2023 | Fire-Resistant Penetrations and Joints | NELSON LOPEZ | special |
| 08/29/2023 | Final | NELSON LOPEZ | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Grover Cleveland H.S | Education | Cellar, Sub-basement, Basement, Ground, Floors 2, 3, Roof | Project Q01214385 Project Q00810903 Project Q00810902 Project Q00708848 Project Q00633527 |