| Owner | Filings | Most Recent |
|---|---|---|
| YAIR LEDY CORP | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/18/2023 | $2.8M | — | — → — | $1,246/sf building |
| 02/10/2017 | $2.3M | — | Private party → Private party | $1,021/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ABS ENGINEERING, PLLC | 3 | 07/26/2024 |
| RAUCH ARCHITECTURE D.P.C. | 4 | 03/18/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| RAUCH ARCHITECTURE D P C | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RAUCH DESIGN BUILD INC | General Contractor | 13 | 07/08/2026 |
| IKAROS ELECTRICAL ENT INC | Electrical | 1 | 03/22/2026 |
| BOLSTER.US,INC | General Contractor | 1 | 07/08/2026 |
| IMPACT PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RAUCH ARCHITECTURE D.P.C. | 7888 | 7 | 07/26/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | RAUCH DESIGN BUILD INC | 01/30/2026 |
| DOB NOW | General Construction | Permit Issued | RAUCH DESIGN BUILD INC | 04/22/2025 |
| DOB NOW | Structural | Signed-off | RAUCH DESIGN BUILD INC | 04/22/2025 |
| DOB NOW | General Construction | Signed-off | RAUCH DESIGN BUILD INC | 04/22/2025 |
| DOB NOW | Structural | Signed-off | RAUCH DESIGN BUILD INC | 05/16/2024 |
| DOB NOW | General Construction | Signed-off | RAUCH DESIGN BUILD INC | 05/09/2024 |
| DOB NOW | General Construction | Signed-off | RAUCH ARCHITECTURE D.P.C. | 04/03/2024 |
| DOB NOW | Mechanical Systems | Signed-off | RAUCH ARCHITECTURE D.P.C. | 03/13/2024 |
| DOB NOW | Plumbing | Permit Issued | IMPACT PLUMBING INC | 02/12/2024 |
| DOB NOW | General Construction | Signed-off | BOLSTER.US,INC | 06/28/2023 |
| BIS | OT | ISSUED | HONG KONG STYLE CONSTRUCT | 10/19/2009 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/26/2024 | Signed-off | RAUCH DESIGN BUILD INC | Associated Ducts and Piping, Heating and Air Conditioning Systems | Heat / Cool Lg ARUN048GSS4 MULTI V S HEAT PUMP 4.0 TON OUTDOOR UNIT 48,000 BTU · Vrf Outdoor ×1 ARUN048GSS4 MUTIL V S HEAT PUMP 4.0 TON OUTDOOR UNIT 48,000 BTU · Vrf Outdoor ×1 Ducts & Piping Mitsubishi Electric DUCTS AND PIPING 870 CFM · Ductwork ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/26/2024 | Permit Issued | IMPACT PLUMBING INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/14/2025 | Complete | IKAROS ELECTRICAL ENT INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/26/2024 | Signed-off | RAUCH DESIGN BUILD INC | Steel, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/22/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/21/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/19/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/02/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/12/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 03/26/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 02/27/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 02/13/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 08/22/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 08/22/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/12/2024 | Fire-Resistant Penetrations and Joints | Matthew Rauch | special |
| 03/14/2024 | Fire-Resistant Penetrations and Joints | Matthew Rauch | special |
| 03/14/2024 | Structural Stability – Alterations of existing buildings | Matthew Rauch | special |
| 03/14/2024 | Fire-Resistance Rated Construction | Matthew Rauch | progress |
| 03/14/2024 | Preliminary | Matthew Rauch | progress |
| 03/14/2024 | Final | Matthew Rauch | progress |
| 03/14/2024 | Demolition | Matthew Rauch | special |
| 11/07/2023 | Structural Stability – Alterations of existing buildings | Matthew Rauch | special |
| 11/07/2023 | Fire-Resistant Penetrations and Joints | Matthew Rauch | special |
| 11/06/2023 | Structural Steel - Details | Matthew Rauch | special |
| 11/06/2023 | Preliminary | Matthew Rauch | progress |
| 11/02/2023 | Mechanical Systems | Matthew Rauch | special |
| 11/02/2023 | Final | Matthew Rauch | progress |
| 11/02/2023 | Final | Matthew Rauch | progress |
| 09/07/2023 | Fire-Resistance Rated Construction | Matthew Rauch | progress |
| 08/25/2023 | Structural Stability – Alterations of existing buildings | Matthew Rauch | special |
| 08/25/2023 | Fire-Resistant Penetrations and Joints | Matthew Rauch | special |
| 08/25/2023 | Preliminary | Matthew Rauch | progress |
| 08/25/2023 | Demolition | Matthew Rauch | special |
| 05/30/2023 | Final | Matthew Rauch | progress |
| 05/30/2023 | Demolition | Matthew Rauch | special |