| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/22/2020 | $950K | — | — → — | $304/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| JLS DESIGNS | 8 | 05/13/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| JLS DESIGNS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DCI ENTERPRISES LLC | General Contractor | 4 | 03/21/2026 |
| D'AMICO CONSTRUCTION INC | General Contractor | 3 | 07/08/2026 |
| LINKED MECHANICAL LLC | General Contractor | 2 | 03/21/2026 |
| ADRIANO PLMBG & HTG CORP | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| METRIC CONSULTING AND INS | 1803 | 4 | 05/13/2025 |
| JLS DESIGNS | 1377 | 2 | 04/11/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | LINKED MECHANICAL | 04/04/2025 |
| DOB NOW | Plumbing | Signed-off | ADRIANO PLMBG & HTG CORP | 10/17/2024 |
| DOB NOW | Construction Fence | Signed-off | DCI ENTERPRISES | 04/03/2024 |
| DOB NOW | Plumbing | Signed-off | ADRIANO PLMBG & HTG CORP | 08/10/2023 |
| DOB NOW | Construction Fence | Signed-off | DCI ENTERPRISES | 07/26/2023 |
| DOB NOW | Construction Fence | Signed-off | D'AMICO CONSTRUCTION INC | 01/23/2023 |
| DOB NOW | Construction Fence | Signed-off | D'AMICO CONSTRUCTION INC | 08/30/2022 |
| BIS | — | ISSUED | DCI ENTERPRISES LLC | 04/21/2025 |
| BIS | — | ISSUED | DCI ENTERPRISES LLC | 04/05/2024 |
| BIS | — | ISSUED | DCI ENTERPRISES LLC | 04/05/2024 |
| BIS | — | ISSUED | DCI ENTERPRISES LLC | 08/04/2023 |
| BIS | — | ISSUED | DCI ENTERPRISES LLC | 07/31/2023 |
| BIS | — | ISSUED | D'AMICO CONSTRUCTION INC | 09/27/2022 |
| BIS | — | ISSUED | D'AMICO CONSTRUCTION INC | 09/23/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/12/2023 | Complete | TOPP WIRE ELECTRIC, INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/28/2025 | On-Site Private Sewage Disposal Systems Installation | JOSEPH SULTANA, JR | special |
| 04/28/2025 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 04/10/2025 | HVAC-R and service water heating system controls | SAMI HAJJAR P.E | energy_progress |
| 04/10/2025 | Fireplaces | SAMI HAJJAR P.E | energy_progress |
| 04/10/2025 | HVAC-R and service water piping design and insulation | SAMI HAJJAR P.E | energy_progress |
| 04/10/2025 | HVAC-R and service water heating equipment | SAMI HAJJAR P.E | energy_progress |
| 04/10/2025 | Ventilation and air distribution system | SAMI HAJJAR P.E | energy_progress |
| 04/10/2025 | Maintenance information | SAMI HAJJAR P.E | energy_progress |
| 04/10/2025 | Mechanical Systems | SAMI HAJJAR P.E | special |
| 04/10/2025 | Final | SAMI HAJJAR P.E | progress |
| 03/31/2025 | On-Site Private Sewage Disposal Systems Installation | JOSEPH SULTANA, JR | special |
| 03/31/2025 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 03/31/2021 | Mechanical Systems | — | special |
| 03/31/2021 | Final | — | progress |
| 03/31/2021 | HVAC-R and service water heating equipment | — | energy_progress |
| 03/31/2021 | HVAC-R and service water heating system controls | — | energy_progress |
| 03/31/2021 | Maintenance information | — | energy_progress |
| 03/31/2021 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 03/31/2021 | Ventilation and air distribution system | — | energy_progress |
| 03/31/2021 | Fireplaces | — | energy_progress |