← Back
Elevator cooperative
33-34 CRESCENT STREET
QUEENS · BIN 4430867
💬 Discuss this project
1950Year Built
15Stories
D4Building Class
R5Zoning
563,800 sfGross Floor Area
727Units
LL97 CoveredRent Stabilized2 Open Violations ▸FISP: SAFEFDNY Report ↗
Elevator cooperative · Owner of record: QUEENSVIEW INC · 449,820 sf lot · 1.25 FAR built · Flood zone X
Locations of Work
Architecture
Permit Issued — active, not yet Signed-off
RoofUnder Construction2p · 2 filings · 9 docs
BulkheadUnder Construction3p · 2 filings · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DAYTON TOWERS504/09/2026
QUEENSVIEWS INC2803/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AE DESIGN SOLUTION403/21/2026
DOMANI CONSULTING1203/21/2026
THERESA VOLTAGGIO103/21/2026
MERRITT ENGINEERING CONSULTANT DPC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
EXO INDUSTRIES CORPGeneral Contractor707/08/2026
NEE ELECTRICAL, LLCElectrical103/22/2026
MNR GROUP INCGeneral Contractor104/09/2026
OMUNDSEN CONSTRUCTION CORGeneral Contractor107/08/2026
PHOENIX SUTTON STR INCGeneral Contractor107/08/2026
BACKFLOW PREVENTION OF NYPlumbing107/08/2026
K & R ELECTRIC CO., INC.Electrical103/22/2026
SEAN COAKLEY P & H INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BUILDING CONSULTING ENGIN1034105/30/2025
COWLEY ENGINEERING186105/30/2025
CUSTODIO CONSULTING, LLC1835605/22/2024
MERRITT ENGINEERING CONSU460105/16/2022
Building Lifecycle
All (98)Filed (15)Permit Issued (9)Signed Off (7)Facade (FISP) (13)Violation (37)Inspection (3)Objection (2)Special Inspection (12)
04/10/2026
Signed off — Alteration
Installation of material hoist. Amend #1, added scaffold drops with inspection and outrigger detail
Q01239599-I1
12/01/2025
Objection resolved — Addressed
11/25/2025
Objection raised — Other
11/18/2025
Filed — Alteration
Installation of material hoist. Amend #1, added scaffold drops with inspection and outrigger detail
Q01239599-P1
10/03/2025
Permit issued — General Construction
Q01228833-I1-GC
06/17/2025
Permit issued — Suspended Scaffold
Q01239599-I1-SC
06/11/2025
Filed — Alteration
Installation of material hoist. Amend #1, added scaffold drops with inspection and outrigger detail
Q01239599-I1
05/30/2025
Filed — Alteration
Bulkhead cladding as per plans filed herewith. No change to use, egress, or occupancy.
Q01228833-I1
05/20/2025
Special inspection requirement — Final
Eric Cowley
05/20/2025
Special inspection requirement — Masonry
Eric Cowley
05/20/2025
Special inspection requirement — Post-installed Anchors
Eric Cowley
05/20/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Eric Cowley
05/20/2025
Special inspection requirement — Tenant Protection Plan Compliance
TONY ONYEAGORO
05/20/2025
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
Eric Cowley
11/12/2024
Signed off — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
Q00781672-I1
11/12/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
Q00781720-I1
05/22/2024
Filed — Alteration
INTERIOR DEMOLITION AND CONSTRUCTION WORK ON THE FIRST FLOOR TO INCLUDE THE INSTALLATION CONCRETE PLATFORM IN CONJUNCTION WITH WATER PUMP REPLACEMENT WORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00657716-P3
05/22/2024
Signed off — Alteration
INTERIOR DEMOLITION AND CONSTRUCTION WORK ON THE FIRST FLOOR TO INCLUDE THE INSTALLATION CONCRETE PLATFORM IN CONJUNCTION WITH WATER PUMP REPLACEMENT WORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00657716-I1
05/16/2024
Signed off — Alteration
WATER PUMP REPLACEMENT WORK ON THE FIRST FLOOR. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00657749-I1
02/12/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
10/06/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
10/03/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
09/12/2023
Filed — Alteration
WATER PUMP REPLACEMENT WORK ON THE FIRST FLOOR. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00657749-P2
09/12/2023
Permit issued — Plumbing
Q00657749-I1-PL
06/01/2023
Cycle 9 facade report submitted
05/26/2023
Signed off — Alteration
Q00736875-I1
05/26/2023
Cycle 9 facade report signed — SAFE
05/24/2023
Cycle 9 facade inspection completed
02/22/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/18/2023
Violation issued (HPD, closed)
A
01/18/2023
Violation issued (HPD, closed)
A
01/18/2023
Violation issued (HPD, closed)
A
10/20/2022
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
Q00781672-P1
10/20/2022
Filed — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
Q00781720-P1
09/27/2022
Permit issued — General Construction
Q00736875-I1-GC
09/06/2022
Permit issued — Plumbing
Q00657749-I1-PL
08/08/2022
Permit issued — General Construction
Q00657716-I1-GC
08/04/2022
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
Q00781672-I1
08/04/2022
Filed — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
Q00781720-I1
08/04/2022
Permit issued — Construction Fence
Q00781720-I1-FN
08/04/2022
Permit issued — Sidewalk Shed
Q00781672-I1-SH
07/11/2022
Filed — Alteration
INTERIOR DEMOLITION AND CONSTRUCTION WORK ON THE FIRST FLOOR TO INCLUDE THE INSTALLATION CONCRETE PLATFORM IN CONJUNCTION WITH WATER PUMP REPLACEMENT WORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00657716-P2
07/11/2022
Filed — Alteration
WATER PUMP REPLACEMENT WORK ON THE FIRST FLOOR. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00657749-P1
05/26/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Anthony Caserma
05/26/2022
Special inspection requirement — Energy Code Compliance Inspections
Anthony Caserma
05/26/2022
Special inspection requirement — Final
Anthony Caserma
05/26/2022
Special inspection requirement — Interior lighting power
Anthony Caserma
05/26/2022
Special inspection requirement — Lighting controls
Anthony Caserma
05/25/2022
Filed — Alteration
INTERIOR DEMOLITION AND CONSTRUCTION WORK ON THE FIRST FLOOR TO INCLUDE THE INSTALLATION CONCRETE PLATFORM IN CONJUNCTION WITH WATER PUMP REPLACEMENT WORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00657716-I1
05/25/2022
Filed — Alteration
WATER PUMP REPLACEMENT WORK ON THE FIRST FLOOR. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00657749-I1
05/16/2022
Filed — Alteration
Q00736875-I1
04/16/2021
Violation issued (HPD, closed)
I
04/16/2021
Violation issued (HPD, closed)
A
08/18/2020
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
Q00204820-I1
01/06/2020
Violation issued (HPD, closed)
A
01/06/2020
Violation issued (HPD, closed)
A
12/17/2019
Violation issued (HPD, closed)
C
11/04/2019
Violation issued (HPD, closed)
I
08/05/2019
Permit issued — Sidewalk Shed
Q00204820-I1-SH
08/03/2019
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
Q00204820-I1
Latest 60 of 98 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedMNR GROUP INC10/03/2025
DOB NOWSuspended ScaffoldSigned-offSSD INTERIOR INC06/17/2025
DOB NOWPlumbingSigned-offBACKFLOW PREVENTION OF NY09/12/2023
DOB NOWGeneral ConstructionSigned-offEXO INDUSTRIES CORP09/27/2022
DOB NOWPlumbingSigned-offSEAN COAKLEY P & H INC09/06/2022
DOB NOWGeneral ConstructionSigned-offOMUNDSEN CONSTRUCTION COR08/08/2022
DOB NOWConstruction FenceSigned-offEXO INDUSTRIES CORP08/04/2022
DOB NOWSidewalk ShedSigned-offEXO INDUSTRIES CORP08/04/2022
DOB NOWSidewalk ShedSigned-offPHOENIX SUTTON STR INC08/05/2019
BISOTISSUEDQUEENSVIEW INC03/09/2021
BISOTISSUEDAVARGA CONTRACTING CORP05/19/2020
BISOTISSUEDAVARGA CONTRACTING CORP01/08/2020
BISPLISSUEDCC CONTROLLED PLBG CO INC11/05/2015
BISPLISSUEDCC CONTROLLED PLBG CO INC09/29/2014
BISOTISSUEDC C CONTROLLED COMBUSTION09/29/2014
BISOTISSUEDNEW YORK PLUMBING-HEATING07/30/2012
BISOTISSUEDEBRO CONSTRUCTION02/10/2008
BISEQISSUEDEBRO RESTORATION CORP02/10/2008
BISEQISSUEDSTEEL INDUSTRIES05/29/2007
BISEQISSUEDSPRING SCAFFOLDING .05/01/2002
6 projects · most recent 01/10/2023
General Wiring
FiledStatusContractorScope
01/10/2023CompleteK & R ELECTRIC CO., INC.General Wiring
08/05/2022CompleteRICHARD NEU—
05/19/2021CompleteS.A.L. ELECTRIC CO INC.General Wiring
10/04/2019CompleteS.A.L. ELECTRIC CO INC.—
07/31/2019Permit IssuedELPO ELECTRICAL CONTG INC—
04/06/2018Permit IssuedNEE ELECTRICAL, LLCGeneral Wiring
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
02/12/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/06/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
10/03/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
05/20/2025FinalEric Cowleyprogress
05/20/2025MasonryEric Cowleyspecial
05/20/2025Post-installed AnchorsEric Cowleyspecial
05/20/2025Structural Stability – Alterations of existing buildingsEric Cowleyspecial
05/20/2025Tenant Protection Plan ComplianceTONY ONYEAGOROspecial
05/20/2025Wall Panels, Curtain Walls, and VeneersEric Cowleyspecial
05/26/2022Fire-Resistant Penetrations and JointsAnthony Casermaspecial
05/26/2022Energy Code Compliance InspectionsAnthony Casermaprogress
05/26/2022FinalAnthony Casermaprogress
05/26/2022Interior lighting powerAnthony Casermaenergy_progress
05/26/2022Lighting controlsAnthony Casermaenergy_progress
08/03/2019FinalBRIAN T. O'CONNORprogress
▾Documents — 140 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch14
08/26/2026Q00736875-I1Request digital key ↗
08/26/2026Q00781672-P1Request digital key ↗
08/26/2026Q00781672-I1Request digital key ↗
Showing 3 of 14 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
08/28/2026Q00204820-I1Request digital key ↗
▸Applications & Permits17
▸BISWORK PERMIT APPLICATION9
03/09/2021421914860Open ↗
01/08/2020440556621Open ↗
10/09/2014421036925Open ↗
Showing 3 of 9 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION7
07/02/2021421914860Open ↗
09/26/2019421914860Open ↗
08/31/2019440556621Open ↗
Showing 3 of 7 on file for this type
▸BISPLACE OF ASSEMBLY1
11/05/2015421227620Open ↗
▸Seals & Professional Certifications36
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/26/2026Q00736875-I1Open ↗
08/24/2026Q00657749-P1Open ↗
08/24/2026Q00657749-I1Open ↗
Showing 3 of 13 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION7
09/26/2019421914860Open ↗
08/08/2016421036925Open ↗
12/16/2014420599533Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/19/2026Q00204820-I1Open ↗
08/30/2026Q01228833-I1Open ↗
08/26/2026Q00657716-P2Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
09/26/2019421914860Open ↗
10/09/2014421036925Open ↗
08/03/2012420599533Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
09/26/2019421914860Open ↗
08/31/2019440556621Open ↗
10/09/2014421036925Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/30/2026Q01228833-I1Open ↗
08/30/2026Q01228833-I1Open ↗
08/26/2026Q00657716-P2Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
08/31/2019440556621Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
08/03/2012420599533Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
08/31/2019440556621Open ↗
▸Trade Schedules & Equipment7
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT3
10/09/2014421036925Open ↗
08/28/2012420599533Open ↗
08/03/2012420599533Open ↗
▸BISSELF-CERT PLUMBING NOTICE2
11/23/2015421036925Open ↗
11/18/2015421036925Open ↗
▸BISBOILER APPROVAL : 900A1
11/23/2015421036925Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
10/09/2014421036925Open ↗
▸Safety & Tenant Protection3
▸BISTenant Protection Plan and Notes2
09/26/2019421914860Open ↗
08/31/2019440556621Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026Q00204820-I1Open ↗
▸Environmental & Asbestos11
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/26/2026Q00736875-I1Open ↗
08/24/2026Q00657749-I1Open ↗
08/24/2026Q00657749-P2Open ↗
Showing 3 of 8 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
08/03/2012420599533Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
08/31/2019440556621Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
10/09/2014421036925Open ↗
▸Energy Compliance14
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
08/08/2016421036925Open ↗
12/16/2014420599533Open ↗
10/09/2014421036925Open ↗
Showing 3 of 6 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
11/10/2020440556621Open ↗
08/08/2016421036925Open ↗
12/16/2014420599533Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
11/10/2020440556621Open ↗
08/31/2019440556621Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
08/31/2019440556621Open ↗
▸BISNYCECC ANALYSIS1
08/31/2019440556621Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026Q00657716-I1Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: RESPONSIBILITY4
03/05/2021421914860Open ↗
11/10/2020440556621Open ↗
09/05/2019440556621Open ↗
Showing 3 of 4 on file for this type
▸Approvals, Objections & Sign-offs13
▸BISLETTERS - SUPPORTING DOCUMENTATION6
07/02/2021421914860Open ↗
08/08/2016421036925Open ↗
08/08/2016421036925Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
03/11/2021421914860Open ↗
11/10/2020440556621Open ↗
08/16/2016421036925Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
11/05/2015421227620Open ↗
08/03/2012420599533Open ↗
▸BISFINAL1
03/11/2021421914860Open ↗
▸Cost, Insurance & Ownership8
▸BISCOST AFFIDAVIT7
11/10/2020440556621Open ↗
09/26/2019421914860Open ↗
08/31/2019440556621Open ↗
Showing 3 of 7 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
03/11/2021421914860Open ↗
▸Filing & Intake Forms8
▸BISADDITIONAL INFORMATION4
11/05/2015421227620Open ↗
09/21/2015421036925Open ↗
09/21/2015421036925Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING COVER SHEET3
09/26/2019421914860Open ↗
10/09/2014421036925Open ↗
08/03/2012420599533Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
08/31/2019440556621Open ↗
▸Other Documents4
▸DOB NOWManufacturer's Specifications2
08/18/2026Q01239599-I1Open ↗
08/13/2026Q01239599-P1Open ↗
▸DOB NOWCalculations2
08/18/2026Q01239599-I1Open ↗
08/13/2026Q01239599-P1Open ↗