| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/08/2026 | Permit Issued | REIDY CONTRACTING GROUP | Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/08/2026 | Permit Issued | FRANKIE PLBG & HTG L.L.C | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/02/2025 | Complete | LAREDO ELECTRIC, INC. | — |
| 08/31/2023 | Complete | NEAD ELECTRIC INC. | General Wiring |
| 11/21/2022 | Complete | FOREST ELECTRIC CORP. | General Wiring |
| 06/22/2020 | Complete | NASH ELECTRIC SERVICES IN | — |
| 08/21/2019 | Complete | LOWY & DONNATH INC. | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| AUDUBON REALTY PROPERTIES LLC | 28 | 03/22/2026 |
| AUDUBON REALTY JACK ROSEN | 2 | 03/22/2026 |
| AUDOBON REALTY PROPERTIES LLC | 10 | 03/22/2026 |
| AUDUBON REALTY | 33 | 03/22/2026 |
| AUBUBON RLTY CO | 1 | 03/22/2026 |
| AUDUBON AVENUE REALTY PROPERTIES | 14 | 03/21/2026 |
| ABA | 1 | 03/21/2026 |
| AUDOBON REALTY | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| LILKER ASSOCIATES CONSULTING ENGINE | 2 | 06/08/2026 |
| RSC ARCHITECTS | 2 | 05/28/2026 |
| MCHENERY TESTING LAB | 1 | 07/16/2024 |
| HASCHEK AND BATHGATE ENG. DPC | 2 | 02/02/2023 |
| NADASKAY KOPELSON ARCHITECTS | 1 | 01/30/2023 |
| KZ ENGINEERING, P.C | 2 | 06/30/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| MUNICIPAL EXPEDITING | 8 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| VANGUARD CONSTRUCTION AND | General Contractor | 8 | 07/08/2026 |
| SIRINA FIRE PROT | Plumbing | 4 | 03/22/2026 |
| CARDOZA PLUMBING CORP | Plumbing | 4 | 07/08/2026 |
| CS BRIDGE CORP | General Contractor | 3 | 07/08/2026 |
| REIDY CONTRACTING GROUP | General Contractor | 1 | 09/07/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 1 | 07/08/2026 |
| GREGORY PAPANTONIOU | Electrical | 1 | 03/21/2026 |
| FRANKIE PLBG & HTG L.L.C | Plumbing | 1 | 09/15/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ALAN MARGOLIN & ASSOC | 423 | 3 | 05/29/2026 |
| MCHENERY TESTING LAB | 9181 | 1 | 07/16/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | FRANKIE PLBG & HTG L.L.C | 09/14/2026 |
| DOB NOW | General Construction | Permit Issued | REIDY CONTRACTING GROUP | 09/03/2026 |
| DOB NOW | Mechanical Systems | Signed-off | VANGUARD CONSTRUCTION AND | 06/14/2023 |
| DOB NOW | General Construction | Signed-off | VANGUARD CONSTRUCTION AND | 06/14/2023 |
| DOB NOW | Plumbing | Signed-off | SIRINA FIRE PROT CORP | 05/03/2023 |
| DOB NOW | Sprinklers | Signed-off | CARDOZA PLUMBING CORP | 05/03/2023 |
| DOB NOW | Mechanical Systems | Signed-off | VANGUARD CONSTRUCTION AND | 05/01/2023 |
| DOB NOW | General Construction | Signed-off | VANGUARD CONSTRUCTION AND | 04/20/2023 |
| DOB NOW | General Construction | Signed-off | VANGUARD CONSTRUCTION AND | 12/09/2022 |
| DOB NOW | Supported Scaffold | Signed-off | CS BRIDGE CORP | 07/01/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | CS BRIDGE CORP | 06/26/2020 |
| BIS | OT | ISSUED | FOUR BOROUGH CONSTRUCTION CORP | 07/08/2020 |
| BIS | MH | ISSUED | CASA PRESTIGE RENOVATIONS | 07/17/2019 |
| BIS | PL | ISSUED | M&T PLBG AND HTG CO., INC | 04/20/2018 |
| BIS | PL | ISSUED | BEDROCK PLBG. & HTG., INC | 08/25/2016 |
| BIS | MH | ISSUED | IDEAL INTERIORS GROUP LLC | 08/15/2016 |
| BIS | OT | ISSUED | IDEAL INTERIORS GROUP LLC | 07/29/2016 |
| BIS | PL | ISSUED | M&T PLBG AND HTG CO., INC | 06/03/2016 |
| BIS | SP | ISSUED | NYC FIRE SPRINKLER CORP | 09/17/2015 |
| BIS | PL | ISSUED | M&T PLBG AND HTG CO., INC | 10/23/2014 |
| BIS | MH | ISSUED | IDEAL INTERIORS GROUP LLC | 07/21/2014 |
| BIS | OT | ISSUED | IDEAL INTERIORS GROUP LLC | 07/21/2014 |
| BIS | EQ | ISSUED | S.N.A. CONSTRUCTION CORP | 10/28/2013 |
| BIS | OT | ISSUED | S.N.A. CONSTRUCTION CORP | 10/11/2013 |
| BIS | OT | ISSUED | ARCHER WATERPROOFING INC | 07/11/2011 |
| BIS | FS | ISSUED | JACK PICCINI, INC | 12/08/2009 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 08/26/2009 |
| BIS | OT | ISSUED | ARCHER WATERPROOFING INC | 03/16/2009 |
| BIS | EQ | ISSUED | S&E BRIDGE & SCAFFOLD LLC. | 04/29/2008 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 04/23/2008 |
| BIS | MH | ISSUED | HELLMAN CONSTRUCTION CO | 04/17/2008 |
| BIS | OT | ISSUED | HELLMAN CONSTRUCTION CO | 04/17/2008 |
| BIS | OT | ISSUED | HELLMAN CONSTRUCTION CO | 04/17/2008 |
| BIS | OT | ISSUED | ARCHER WATERPROOFING INC | 02/06/2008 |
| BIS | PL | ISSUED | ALJER PLBG & HTG CORP | 01/14/2008 |
| BIS | PL | ISSUED | ALJER PLBG & HTG CORP | 01/14/2008 |
| BIS | OT | ISSUED | HELLMAN CONSTRUCTION CO | 01/07/2008 |
| BIS | MH | ISSUED | HELLMAN CONSTRUCTION CO | 01/07/2008 |
| BIS | OT | ISSUED | HELLMAN CONSTRUCTION CO | 01/07/2008 |
| BIS | OT | ISSUED | OXFORD CONSTRUCTION | 11/13/2007 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/25/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/13/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/13/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/13/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/29/2026 | Energy Code Compliance Inspections | Young Suh | progress |
| 05/29/2026 | HVAC-R and service water piping design and insulation | Young Suh | energy_progress |
| 05/28/2026 | Final | Young Suh | progress |
| 05/28/2026 | Interior lighting power | Young Suh | energy_progress |
| 05/28/2026 | Energy Code Compliance Inspections | Young Suh | progress |
| 05/28/2026 | Lighting controls | Young Suh | energy_progress |
| 08/21/2024 | Final | Young Suh | progress |
| 08/21/2024 | Mechanical Systems | Young Suh | special |
| 07/12/2024 | Masonry | TREVOR O. FLOWERS | special |
| 07/12/2024 | Final | TREVOR O. FLOWERS | progress |
| 01/26/2023 | Shutoff dampers | Young Suh | energy_progress |
| 01/26/2023 | Maintenance information | Young Suh | energy_progress |
| 01/26/2023 | HVAC-R and service water piping design and insulation | Young Suh | energy_progress |
| 01/26/2023 | HVAC-R and service water heating equipment | Young Suh | energy_progress |
| 01/26/2023 | HVAC-R and service water heating system controls | Young Suh | energy_progress |
| 01/26/2023 | Energy Code Compliance Inspections | Young Suh | progress |
| 11/09/2022 | Mechanical Systems | Young Suh | special |
| 11/09/2022 | Sprinkler Systems | Young Suh | special |
| 11/09/2022 | Final | Young Suh | progress |
| 06/19/2020 | Final | Karol Zdancewicz | progress |
| 06/19/2020 | Final | Karol Zdancewicz | progress |