RoofGenerator installation121p · 4 filings · 20 docs
ArchitectureDMElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Subsequent filing made to cover belly tank integral to Emergency Generator to be installed on roof, per plans filed herewith.
On file for this project
11 documents · 1 drawing sheet
Structural work for Alteration including new steel posts & beams for support of floor joists & repair of existing bulkhead.
On file for this project
118 documents · 6 drawing sheets
PROPOSED FACADE REPAIR AND STRUCTURAL STABILIZATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGREE AND OCCUPANCY.
On file for this project
3 documents
Latest 3 of 4 filings on this floor.
BulkheadStructural work for alteration1p · 1 filing · 20 docs
Structural
Structural work for Alteration including new steel posts & beams for support of floor joists & repair of existing bulkhead.
On file for this project
118 documents · 1 drawing sheet
Floor 5Structural work for alteration106p · 3 filings · 20 docs
ArchitectureDMElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Structural work for Alteration including new steel posts & beams for support of floor joists & repair of existing bulkhead.
On file for this project
118 documents · 5 drawing sheets
PROPOSED FACADE REPAIR AND STRUCTURAL STABILIZATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGREE AND OCCUPANCY.
On file for this project
3 documents
EXTERIOR WORK TO REPLACE ALL WINDOWS AND EXTERIOR DOORS IN BUILDING AS PER PLANS FILED HEREWITH
On file for this project
6 documents
Floor 4Generator installation103p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Subsequent filing made to cover belly tank integral to Emergency Generator to be installed on roof, per plans filed herewith.
On file for this project
11 documents · 1 drawing sheet
Structural work for Alteration including new steel posts & beams for support of floor joists & repair of existing bulkhead.
On file for this project
118 documents · 1 drawing sheet
PROPOSED FACADE REPAIR AND STRUCTURAL STABILIZATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGREE AND OCCUPANCY.
On file for this project
3 documents
Latest 3 of 4 filings on this floor.
Floor 3Structural work for alteration103p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Structural work for Alteration including new steel posts & beams for support of floor joists & repair of existing bulkhead.
On file for this project
118 documents · 2 drawing sheets
PROPOSED FACADE REPAIR AND STRUCTURAL STABILIZATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGREE AND OCCUPANCY.
On file for this project
3 documents
EXTERIOR WORK TO REPLACE ALL WINDOWS AND EXTERIOR DOORS IN BUILDING AS PER PLANS FILED HEREWITH
On file for this project
6 documents
Floor 2Structural work for alteration101p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Structural work for Alteration including new steel posts & beams for support of floor joists & repair of existing bulkhead.
On file for this project
118 documents
PROPOSED FACADE REPAIR AND STRUCTURAL STABILIZATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGREE AND OCCUPANCY.
On file for this project
3 documents
EXTERIOR WORK TO REPLACE ALL WINDOWS AND EXTERIOR DOORS IN BUILDING AS PER PLANS FILED HEREWITH
On file for this project
6 documents
Floor 1Generator installation106p · 5 filings · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sidewalk Shed · Sprinklers · Structural
Subsequent filing made to cover belly tank integral to Emergency Generator to be installed on roof, per plans filed herewith.
On file for this project
11 documents · 1 drawing sheet
Structural work for Alteration including new steel posts & beams for support of floor joists & repair of existing bulkhead.
On file for this project
118 documents
PROPOSED FACADE REPAIR AND STRUCTURAL STABILIZATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGREE AND OCCUPANCY.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
CellarGenerator installation125p · 4 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · Foundation · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Subsequent filing made to cover belly tank integral to Emergency Generator to be installed on roof, per plans filed herewith.
On file for this project
11 documents · 1 drawing sheet
Structural work for Alteration including new steel posts & beams for support of floor joists & repair of existing bulkhead.
On file for this project
118 documents · 10 drawing sheets
PROPOSED FACADE REPAIR AND STRUCTURAL STABILIZATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGREE AND OCCUPANCY.
On file for this project
3 documents
Latest 3 of 4 filings on this floor.
Site & exteriorTemporary construction fence installation20p · 5 filings · 11 docs
ArchitectureElectricalEquipmentStructural
Issued Permit Scope
Construction Fence · General Construction · Sidewalk Shed · Supported Scaffold
PROPOSED FACADE REPAIR AND STRUCTURAL STABILIZATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGREE AND OCCUPANCY.
On file for this project
3 documents · 6 drawing sheets
Installation of construction fence in front of 21 East 115th Street.
On file for this project
2 documents · 1 drawing sheet
INSTALLATION OF 300 PSF SIDEWALK SHED AND PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
2 documents · 9 drawing sheets
Latest 3 of 5 filings on this floor.
Filed — no permit issuedConstruction fence4p · 1 filing · 1 doc
General
No filed description on record for this project.
On file for this project
1 document · 4 drawing sheets