| Firm | Filings | Most Recent |
|---|---|---|
| Scaglione Architects | 5 | 12/06/2023 |
| William Montague Engineering | 1 | 10/18/2022 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Island Wide Building | Scaffold | 10 | 07/08/2026 |
| Duo Plumbing & Heating | Plumbing | 3 | 07/08/2026 |
| D and H Electrical Construction | Electrical | 1 | 03/22/2026 |
| Island Wide Building | General Contractor | 1 | 07/08/2026 |
| Duo Plumbing & Heating | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SRA Planning & Expediting | 5677 | 3 | 12/06/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | Duo Plumbing & Heating | 11/20/2023 |
| DOB NOW | Curb Cut | Signed-off | Island Wide Building | 10/02/2023 |
| DOB NOW | Construction Fence | Signed-off | Island Wide Building | 08/09/2023 |
| DOB NOW | Plumbing | Signed-off | Duo Plumbing & Heating | 11/18/2022 |
| DOB NOW | Construction Fence | Signed-off | Island Wide Building | 11/02/2022 |
| DOB NOW | Sprinklers | Signed-off | Duo Plumbing & Heating | 10/28/2022 |
| DOB NOW | Plumbing | Signed-off | Duo Plumbing & Heating | 10/28/2022 |
| DOB NOW | Construction Fence | Signed-off | Island Wide Building | 07/01/2022 |
| DOB NOW | Construction Fence | Signed-off | Island Wide Building | 10/29/2021 |
| DOB NOW | Construction Fence | Signed-off | Island Wide Building | 06/18/2021 |
| DOB NOW | Construction Fence | Signed-off | Island Wide Building | 05/25/2021 |
| DOB NOW | Construction Fence | Signed-off | Island Wide Building | 02/20/2019 |
| BIS | — | ISSUED | Island Wide Building | 10/19/2023 |
| BIS | — | ISSUED | Island Wide Building | 05/11/2023 |
| BIS | — | ISSUED | Island Wide Building | 11/01/2022 |
| BIS | — | ISSUED | Island Wide Building | 05/04/2022 |
| BIS | — | ISSUED | Island Wide Building | 10/29/2021 |
| BIS | — | ISSUED | Island Wide Building | 06/21/2021 |
| BIS | — | ISSUED | Island Wide Building | 02/21/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/22/2023 | Complete | D and H Electrical Construction | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/17/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 08/30/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/30/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/29/2023 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 03/13/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/02/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| 11/29/2022 | Fail-Final PL - Underground | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/07/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | WILLIAM MONTAGUE | special |
| 12/07/2023 | Energy Code Compliance Inspections | WILLIAM MONTAGUE | progress |
| 12/01/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | WILLIAM MONTAGUE | special |
| 12/01/2023 | Energy Code Compliance Inspections | WILLIAM MONTAGUE | progress |
| 08/17/2022 | Fire-Resistant Penetrations and Joints | WILLIAM MONTAGUE | special |
| 07/19/2021 | Sprinkler Systems | WILLIAM MONTAGUE | special |