Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CONSOLIDATED SCAFFOLDING INC.404/09/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PAUL G. JONES, P.E.101/11/2025
TECTONIC ENGINEERING511/20/2024
SPARC FIRE PROTECTION ENGINEERING112/11/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
RIZZO GROUP503/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TITANIUM CONSTRUCTION SERGeneral Contractor504/09/2026
ROCK SOLID LANDSCAPE ANDGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TECTONIC ENGINEERING CONS106411/20/2024
Building Lifecycle
All (78)Filed (7)Permit Issued (6)Signed Off (1)Objection (39)Special Inspection (25)
08/21/2026
Signed off — Alteration
Curb cut installation as per plans filed herewith. No change in use, egress, or occupancy.
S00967891-I1
01/27/2026
Permit issued — General Construction
S00960710-I1-GC-CX
01/27/2026
Permit issued — Solar
S00967863-I1-SL
01/14/2026
Permit issued — General Construction
S00963779-I1-GC
10/31/2025
Objection resolved — Addressed
08/21/2025
Objection resolved — Addressed
08/21/2025
Objection resolved — Addressed
08/20/2025
Permit issued — Curb Cut
S00967891-I1-CC
02/03/2025
Permit issued — Structural
S01144200-I1-GC-CX
01/13/2025
Permit issued — Construction Fence
S01165563-I1-FN
01/11/2025
Filed — Alteration
S01165563-I1
11/20/2024
Filed — Alteration
S01144200-I1
11/20/2024
Special inspection requirement — Masonry
GEORGE GHEBRYAL
11/20/2024
Special inspection requirement — Post-installed Anchors
GEORGE GHEBRYAL
11/20/2024
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
MARK STIER
11/20/2024
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
GEORGE GHEBRYAL
11/20/2024
Special inspection requirement — Structural Steel - High Strength Bolting
GEORGE GHEBRYAL
11/20/2024
Special inspection requirement — Subgrade Inspections
GEORGE GHEBRYAL
11/20/2024
Special inspection requirement — Concrete - Cast-In-Place
GEORGE GHEBRYAL
11/18/2024
Special inspection requirement — Structural Steel - Details
GEORGE GHEBRYAL
11/18/2024
Special inspection requirement — Final
GEORGE GHEBRYAL
10/21/2024
Objection resolved — Addressed
10/21/2024
Objection resolved — Addressed
10/21/2024
Objection resolved — Addressed
10/21/2024
Objection resolved — Addressed
09/30/2024
Objection resolved — Addressed
09/30/2024
Objection resolved — Addressed
09/30/2024
Objection resolved — Addressed
07/09/2024
Objection resolved — Addressed
07/09/2024
Objection resolved — Addressed
07/09/2024
Objection resolved — Addressed
06/10/2024
Objection resolved — Addressed
03/26/2024
Special inspection requirement — Air barrier - visual inspection
GEORGE GHEBRYAL
03/13/2024
Objection resolved — Addressed
03/13/2024
Objection resolved — Addressed
03/13/2024
Objection resolved — Addressed
03/13/2024
Objection resolved — Addressed
03/11/2024
Objection raised — Scope
03/11/2024
Objection resolved — Addressed
02/27/2024
Filed — Alteration
Curb cut installation as per plans filed herewith. No change in use, egress, or occupancy.
S00967891-I1
02/07/2024
Objection raised — Other
01/26/2024
Filed — Alteration
Solar installation as per plans filed herewith. No change in use, egress, or occupancy.
S00967863-I1
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Scope
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Zoning
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Scope
01/04/2024
Objection raised — Other
01/04/2024
Objection raised — Other
12/28/2023
Objection raised — Scope
12/28/2023
Objection raised — Other
Latest 60 of 78 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedTITANIUM CONSTRUCTION SER01/27/2026
DOB NOWSolarPermit IssuedTITANIUM CONSTRUCTION SER01/27/2026
DOB NOWGeneral ConstructionSigned-offTITANIUM CONSTRUCTION SER01/14/2026
DOB NOWCurb CutSigned-offROCK SOLID LANDSCAPE AND08/20/2025
DOB NOWStructuralPermit IssuedTITANIUM CONSTRUCTION SER02/03/2025
DOB NOWConstruction FencePermit IssuedTITANIUM CONSTRUCTION SER01/13/2025
1 project · most recent 12/11/2023
FiledStatusContractorScope
12/11/2023———
4 projects · most recent 02/20/2026
General Wiring
FiledStatusContractorScope
02/20/2026CompleteSPARTAN ELECTRICAL OF NY1 meters, 1 new_meters
10/30/2025Permit IssuedSPARTAN ELECTRICAL OF NY—
07/10/2025CompleteNEWGRANGE ELECTRIC, INC—
04/01/2025CancelledSPARTAN ELECTRICAL OF NYGeneral Wiring
2 projects · most recent 12/11/2023
Steel Concrete Masonry
FiledStatusContractorScope
12/11/2023Permit IssuedTITANIUM CONSTRUCTION SERSteel, Concrete, Masonry
12/11/2023Signed-offTITANIUM CONSTRUCTION SER1 scope_items
1 project · most recent 01/26/2024
FiledStatusContractorScope
01/26/2024Permit IssuedTITANIUM CONSTRUCTION SER16 panels, 8.64 kw
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
11/20/2024MasonryGEORGE GHEBRYALspecial
11/20/2024Post-installed AnchorsGEORGE GHEBRYALspecial
11/20/2024Subsurface Investigations (Borings/Test Pits)MARK STIERspecial
11/20/2024Subsurface Conditions – Fill Placement & In-Place DensityGEORGE GHEBRYALspecial
11/20/2024Structural Steel - High Strength BoltingGEORGE GHEBRYALspecial
11/20/2024Subgrade InspectionsGEORGE GHEBRYALspecial
11/20/2024Concrete - Cast-In-PlaceGEORGE GHEBRYALspecial
11/18/2024Structural Steel - DetailsGEORGE GHEBRYALspecial
11/18/2024FinalGEORGE GHEBRYALprogress
03/26/2024Air barrier - visual inspectionGEORGE GHEBRYALenergy_progress
12/01/2023Sprinkler Systems—special
11/27/2023Subsurface Investigations (Borings/Test Pits)MARK STIERspecial
11/27/2023Structural Stability – Alterations of existing buildingsGEORGE GHEBRYALspecial
11/27/2023Energy Code Compliance InspectionsGEORGE GHEBRYALprogress
11/27/2023FinalGEORGE GHEBRYALprogress
11/27/2023Concrete - Cast-In-PlaceGEORGE GHEBRYALspecial
11/27/2023Post-installed AnchorsGEORGE GHEBRYALspecial
11/27/2023Seismic Isolation SystemsEdward Iamicelispecial
11/27/2023Structural Steel - High Strength BoltingGEORGE GHEBRYALspecial
11/27/2023Subgrade InspectionsGEORGE GHEBRYALspecial
11/27/2023Subsurface Conditions – Fill Placement & In-Place DensityGEORGE GHEBRYALspecial
11/27/2023Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
11/16/2023Structural Steel - DetailsGEORGE GHEBRYALspecial
11/16/2023MasonryGEORGE GHEBRYALspecial
11/09/2023FinalANTONIO GUALTIERIprogress
▾Documents — 47 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/21/2026S00967863-I1Request digital key ↗
08/20/2026S01144200-I1Request digital key ↗
08/20/2026S01165563-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION3
06/12/2025540263114Open ↗
06/11/2025540263114Open ↗
09/04/2024540263114Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation2
08/13/2025540263114Open ↗
09/04/2024540263114Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
09/04/2024540263114Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026S00960710-I1Open ↗
▸Seals & Professional Certifications16
▸DOB NOWSpecial Inspector Seal & Signature6
09/23/2026S01144200-I1Open ↗
09/23/2026S01144200-I1Open ↗
08/25/2026S00960710-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/21/2026S00967863-I1Open ↗
08/21/2026S00967891-I1Open ↗
08/20/2026S01144200-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/23/2026S01144200-I1Open ↗
08/25/2026S00960710-I1Open ↗
08/23/2026S00967863-I1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
06/07/2024540263114Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/04/2024540263114Open ↗
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist1
08/13/2026S00960710-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S00960710-I1Open ↗
▸Inspections & Test Reports6
▸DOB NOWTR4 Test Report and Plot Diagram2
08/13/2026S00960710-I1Open ↗
08/13/2026S01144200-I1Open ↗
▸DOB NOWSOIL REPORT2
08/13/2026S00960710-I1Open ↗
08/13/2026S01144200-I1Open ↗
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
09/04/2024540263114Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
06/07/2024540263114Open ↗
▸Approvals, Objections & Sign-offs4
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff2
08/13/2025540263114Open ↗
09/04/2024540263114Open ↗
▸DOB NOWOTCR Conditional Acceptance Letter1
08/13/2026S00963779-I1Open ↗
▸DOB NOWOTCR Letter of Conditional Acceptance1
08/13/2026S00963779-I1Open ↗
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
08/13/2025540263114Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
06/07/2024540263114Open ↗
▸Other Documents6
▸BISBPP - SUPPORTING DOCUMENTATION5
08/13/2025540263114Open ↗
08/13/2025540263114Open ↗
09/04/2024540263114Open ↗
Showing 3 of 5 on file for this type
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
09/04/2024540263114Open ↗