| Owner | Filings | Most Recent |
|---|---|---|
| KADAR ELITE CONSTRUCTION | 2 | 03/22/2026 |
| INDV | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| STEEL CORE ENGINEERING PLLC | 9 | 11/24/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 07/21/2021 |
| SHENKER ARCHITECT, PC | 1 | 10/29/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| Shenker Architects | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KADAR ELITE CONSTRUCTION | General Contractor | 12 | 07/08/2026 |
| G.B. & SON, INC | Plumbing | 3 | 03/22/2026 |
| POWERS BRIDGING & SCAFFOLDING | General Contractor | 2 | 03/21/2026 |
| PFL MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| MARSHALL SCHLESINGER | Electrical | 1 | 03/21/2026 |
| GRUSHINSKY PIPNG & HTG IN | Fire Protection | 1 | 07/08/2026 |
| MIKHAIL UMANSKIY | Electrical | 1 | 03/21/2026 |
| TOTAL FIRE PROTECTION | Electrical | 1 | 03/21/2026 |
| YEVGENY KOLTUNOV | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 9 | 11/24/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | PFL MECHANICAL CORP | 10/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | KADAR ELITE CONSTRUCTION | 08/08/2025 |
| DOB NOW | Construction Fence | Permit Issued | KADAR ELITE CONSTRUCTION | 06/03/2024 |
| DOB NOW | Construction Fence | Permit Issued | KADAR ELITE CONSTRUCTION | 05/31/2023 |
| DOB NOW | Plumbing | Permit Issued | PFL MECHANICAL CORP | 09/09/2022 |
| DOB NOW | Construction Fence | Permit Issued | KADAR ELITE CONSTRUCTION | 05/23/2022 |
| DOB NOW | Structural | Signed-off | KADAR ELITE CONSTRUCTION | 03/07/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | POWERS BRIDGING & SCAFFOL | 07/27/2021 |
| DOB NOW | Sprinklers | Signed-off | GRUSHINSKY PIPNG & HTG IN | 07/15/2021 |
| DOB NOW | Mechanical Systems | Signed-off | KADAR ELITE CONSTRUCTION | 05/26/2021 |
| DOB NOW | Construction Fence | Permit Issued | KADAR ELITE CONSTRUCTION | 05/25/2021 |
| DOB NOW | Mechanical Systems | Signed-off | KADAR ELITE CONSTRUCTION | 04/02/2021 |
| BIS | — | ISSUED | KADAR ELITE CONSTRUCTION | 10/28/2025 |
| BIS | — | ISSUED | KADAR ELITE CONSTRUCTION | 06/03/2025 |
| BIS | — | ISSUED | KADAR ELITE CONSTRUCTION | 10/28/2024 |
| BIS | — | ISSUED | KADAR ELITE CONSTRUCTION | 05/31/2024 |
| BIS | — | ISSUED | KADAR ELITE CONSTRUCTION | 10/27/2023 |
| BIS | — | ISSUED | KADAR ELITE CONSTRUCTION | 05/31/2023 |
| BIS | — | ISSUED | KADAR ELITE CONSTRUCTION | 10/25/2022 |
| BIS | — | ISSUED | KADAR ELITE CONSTRUCTION | 05/26/2022 |
| BIS | — | ISSUED | KADAR ELITE CONSTRUCTION | 10/19/2021 |
| BIS | — | ISSUED | KADAR ELITE CONSTRUCTION | 03/18/2021 |
| BIS | — | ISSUED | KADAR ELITE CONSTRUCTION | 03/18/2021 |
| BIS | OT | ISSUED | ANES INC | 10/25/2012 |
| BIS | OT | ISSUED | G AND R CONSULTANT INC. | 04/26/2002 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/24/2025 | Permit Issued | PFL MECHANICAL CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/21/2021 | Complete | OPTIMAL ELECTRIC, INC | — |
| 05/06/2021 | Permit Issued | CMY ELECTRICAL CORP | General Wiring |
| 11/26/2019 | Permit Issued | A.L. ELECTRICAL CORP. | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/24/2025 | HVAC insulation and sealing | Younes Abouyaala | energy_progress |
| 12/24/2025 | Maintenance information | Younes Abouyaala | energy_progress |
| 12/24/2025 | HVAC and service water heating equipment | Younes Abouyaala | energy_progress |
| 12/24/2025 | HVAC and service water heating system controls | Younes Abouyaala | energy_progress |
| 12/24/2025 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 12/24/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Younes Abouyaala | special |
| 12/24/2025 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 08/11/2025 | HVAC and service water heating equipment | Younes Abouyaala | energy_progress |
| 08/11/2025 | Permanent certificate | Younes Abouyaala | energy_progress |
| 08/11/2025 | Maintenance information | Younes Abouyaala | energy_progress |
| 08/11/2025 | Shutoff dampers | Younes Abouyaala | energy_progress |
| 08/11/2025 | Electrical motors | Younes Abouyaala | energy_progress |
| 08/11/2025 | Heating Systems | Younes Abouyaala | special |
| 08/11/2025 | Mechanical Systems | Younes Abouyaala | special |
| 08/11/2025 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Younes Abouyaala | special |
| 08/11/2025 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 08/11/2025 | Final | NAVEEN KUMAR | progress |
| 08/11/2025 | HVAC insulation and sealing | Younes Abouyaala | energy_progress |
| 08/11/2025 | HVAC and service water heating system controls | Younes Abouyaala | energy_progress |
| 07/19/2025 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 07/19/2025 | Maintenance information | Younes Abouyaala | energy_progress |
| 07/19/2025 | HVAC and service water heating equipment | Younes Abouyaala | energy_progress |
| 07/19/2025 | HVAC insulation and sealing | Younes Abouyaala | energy_progress |
| 07/19/2025 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 07/19/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Younes Abouyaala | special |