← Back
BuildNYC
Zoned residential, not Manhattan
210 GORDON STREET
STATEN ISLAND · BIN 5014395
💬 Discuss this project
0Year Built
—Stories
V0Building Class
R3AZoning
0 sfGross Floor Area
0Units
Zoned residential, not Manhattan · Owner of record: Hamda Investors · 3,000 sf lot · 0 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Filed — no permit issuedHamda Investors LLC20p · 1 filing · 10 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Hamda Investors403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AZ Professional Engineering104/20/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
92 Design203/21/2026
Building Lifecycle
All (30)Filed (1)Objection (9)Special Inspection (20)
07/12/2026
Objection resolved — Resolved
03/19/2026
Objection resolved — Addressed
02/18/2026
Objection resolved — Addressed
12/08/2025
Objection raised — Zoning
12/08/2025
Objection raised — Zoning
10/28/2025
Objection resolved — Addressed
07/22/2025
Special inspection requirement — Interior lighting power
07/22/2025
Special inspection requirement — Protection of exposed foundation insulation
07/22/2025
Special inspection requirement — Maintenance information
07/22/2025
Special inspection requirement — Metering
05/14/2025
Objection raised — Scope
05/14/2025
Objection raised — Zoning
05/14/2025
Objection raised — Zoning
04/20/2025
Filed — New Building
PROPOSED NEW BUILDING TWO (2) STORY WITH ATTIC, TWO (2) FAMILY DWELLING AS PER PLAN.
S01198332-I1
03/27/2025
Special inspection requirement — Ventilation and air distribution system
03/27/2025
Special inspection requirement — HVAC-R and service water heating equipment
03/27/2025
Special inspection requirement — Air barrier — testing
03/27/2025
Special inspection requirement — Fenestration areas
03/27/2025
Special inspection requirement — Air barrier - visual inspection
03/27/2025
Special inspection requirement — Insulation placement and R values
03/27/2025
Special inspection requirement — Permanent certificate
03/27/2025
Special inspection requirement — Fenestration air leakage
03/27/2025
Special inspection requirement — HVAC-R and service water heating system controls
03/27/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
03/27/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
03/20/2025
Special inspection requirement — Footing and Foundation
03/20/2025
Special inspection requirement — Final
03/20/2025
Special inspection requirement — Masonry
03/20/2025
Special inspection requirement — Wood – Prefabricated I-Joists
03/20/2025
Special inspection requirement — Mechanical Systems
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISEQISSUEDMackroyce Contrating06/25/1993
BISEQISSUEDMackroyce Contracting06/23/1993
BIS—ISSUEDMackroyce Contracting06/23/1993
1 project · most recent 04/20/2025
Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
04/20/2025——Heating Systems
Heating
Navien MANUFACTURER: NAVIEN MODEL: 240/130 H 13,000 BTU · Boiler ×2
1 project · most recent 04/20/2025
Concrete Masonry Wood
FiledStatusContractorScope
04/20/2025——Concrete, Masonry, Wood
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
07/22/2025Interior lighting power—energy_progress
07/22/2025Protection of exposed foundation insulation—energy_progress
07/22/2025Maintenance information—energy_progress
07/22/2025Metering—energy_progress
03/27/2025Ventilation and air distribution system—energy_progress
03/27/2025HVAC-R and service water heating equipment—energy_progress
03/27/2025Air barrier — testing —energy_progress
03/27/2025Fenestration areas—energy_progress
03/27/2025Air barrier - visual inspection—energy_progress
03/27/2025Insulation placement and R values—energy_progress
03/27/2025Permanent certificate—energy_progress
03/27/2025Fenestration air leakage—energy_progress
03/27/2025HVAC-R and service water heating system controls—energy_progress
03/27/2025Fenestration and door U-factor and product ratings—energy_progress
03/27/2025HVAC-R and service water piping design and insulation—energy_progress
03/20/2025Footing and Foundation—progress
03/20/2025Final—progress
03/20/2025Masonry—special
03/20/2025Wood – Prefabricated I-Joists—special
03/20/2025Mechanical Systems—special
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/19/2026S01198332-S1Request digital key ↗
08/19/2026S01198332-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026S01198332-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S01198332-I1Open ↗
▸Seals & Professional Certifications1
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/19/2026S01198332-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026S01198332-I1Open ↗
▸Inspections & Test Reports1
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026S01198332-I1Open ↗
▸Other Documents4
▸DOB NOWFinal Survey1
08/13/2026S01198332-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026S01198332-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/19/2026S01198332-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026S01198332-I1Open ↗