| Owner | Filings | Most Recent |
|---|---|---|
| YORK ASSOCIATES | 10 | 03/21/2026 |
| OLIMA CONSTRUCTION | 4 | 07/08/2026 |
| ORNSTEIN 215-217 E.86 LLC | 1 | 03/22/2026 |
| KOBEYAKI | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| IW ARCHITECTURE, PLLC | 1 | 08/04/2026 |
| NEW YORK ENGINEERS LLC | 2 | 07/13/2026 |
| GREGORY RALPH, ARCHITECT | 1 | 06/30/2026 |
| DARIUS TORABY ARCHITECTS, P.C. | 3 | 03/26/2026 |
| ALWAYS FAST SERVICES CORP | 1 | 09/03/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 08/25/2025 |
| F.P.VILLANO CONSULTING ENGINEER LLC | 1 | 12/01/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| LOUIS STRIAR | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| OLIMA CONSTRUCTION CORP | General Contractor | 3 | 08/13/2026 |
| MICHELLE KUO CORP | General Contractor | 2 | 07/30/2026 |
| PHOENIX SUTTON STR INC | General Contractor | 2 | 04/09/2026 |
| SERGIO GIANNACHI | Electrical | 1 | 03/21/2026 |
| TROADIO MENENDEZ | Electrical | 1 | 03/21/2026 |
| TRI STATE PLBG & HTG INC | Plumbing | 1 | 08/30/2026 |
| L S SIGN | Scaffold | 1 | 07/08/2026 |
| LELIS, ARILSON | Electrical | 1 | 03/21/2026 |
| VALLESIGNS AWNINGS | Scaffold | 1 | 08/08/2026 |
| NEU, RICHARD | Electrical | 1 | 03/21/2026 |
| RICHARD NEU | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GRA DESIGN STUDIO | 9854 | 3 | 07/13/2026 |
| MJ ENGINEERING & DESIGN | 5546 | 3 | 07/13/2026 |
| DARIUS TORABY ARCHITECTS, | 116 | 3 | 03/26/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | TRI STATE PLBG & HTG INC | 08/27/2026 |
| DOB NOW | General Construction | Permit Issued | OLIMA CONSTRUCTION CORP | 08/12/2026 |
| DOB NOW | Sign | Permit Issued | VALLESIGNS & AWNINGS INC | 08/07/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | MICHELLE KUO CORP | 07/29/2026 |
| DOB NOW | General Construction | Permit Issued | MICHELLE KUO CORP | 07/24/2026 |
| DOB NOW | Structural | Signed-off | OLIMA CONSTRUCTION CORP | 09/24/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | PHOENIX SUTTON STR INC | 09/04/2025 |
| DOB NOW | Supported Scaffold | Signed-off | PHOENIX SUTTON STR INC | 09/04/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | OLIMA CONSTRUCTION CORP | 08/26/2025 |
| DOB NOW | Sign | Signed-off | WEINFELD, ELLIOT | 12/03/2020 |
| BIS | PL | ISSUED | HERTLER NADILE P & H, INC | 08/17/2015 |
| BIS | SP | ISSUED | A + SPRINKLER CORP | 08/21/2014 |
| BIS | FP | ISSUED | ACTIVE FIRE EXTING CO INC | 08/05/2014 |
| BIS | PL | ISSUED | HERTLER NADILE P & H, INC | 05/19/2014 |
| BIS | PL | ISSUED | HERTLER NADILE P & H, INC | 05/19/2014 |
| BIS | OT | ISSUED | ROBIN SYSTEMS INC | 05/12/2014 |
| BIS | OT | ISSUED | ROBIN SYSTEMS INC | 03/25/2014 |
| BIS | OT | ISSUED | KING'S ASSOCIATES INC | 03/15/2002 |
| BIS | EQ | ISSUED | ROCKLEDGE SCAFFOLD CORP | 07/13/2001 |
| BIS | — | ISSUED | BARTER SIGN | 04/06/1999 |
| BIS | FP | RE-ISSUED | NEW YORK BUSINESS FIRE SYSTEM | 04/28/1998 |
| BIS | FP | ISSUED | MASTER FIRE SYSTEMS, INC | 03/20/1996 |
| BIS | PL | ISSUED | MAGOR PLUMBING HEATING | 03/20/1996 |
| BIS | PL | ISSUED | MAGOR PLUMBING & HEATING | 03/14/1996 |
| BIS | — | ISSUED | PRIMECO,INC. | 03/06/1996 |
| BIS | PL | ISSUED | MAGOR PLUMBING HEATING | 07/11/1995 |
| BIS | OT | ISSUED | CHUI LAM CONST. | 06/21/1995 |
| BIS | — | ISSUED | J. MINOS INC | 02/10/1993 |
| BIS | — | ISSUED | J.M.MINOS | 01/12/1993 |
| BIS | — | ISSUED | J.M MINOS INC | 07/30/1992 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/13/2026 | Permit Issued | MICHELLE KUO CORP | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Lg ZRNU283M3AA 90,000 BTU · Vrf Indoor ×3 KSSAE091A 9,000 BTU · Split System ×1 ZRNU183M2AA 18,000 BTU · Vrf Indoor ×1 ZRUM096BTE6 96,000 BTU · Vrf Outdoor ×1 Ventilation Captiveaire EA2-D.250-20D 96,230 BTU · Makeup Air ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/13/2026 | Permit Issued | TRI STATE PLBG & HTG INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2026 | Permit Issued | SPECTRUM ON BROADWAY-ELEC | — |
| 09/01/2026 | Permit Issued | JEM ELEC'L CONTR. CORP | General Wiring |
| 09/04/2025 | Complete | RICHARD NEU | — |
| 12/04/2020 | Complete | AUR0RA ELECL CONTG INC | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/30/2026 | Fire-Resistant Penetrations and Joints | Magdy Youssef | special |
| 06/30/2026 | Post-installed Anchors | Magdy Youssef | special |
| 06/30/2026 | Energy Code Compliance Inspections | Magdy Youssef | progress |
| 06/30/2026 | Fire-Resistance Rated Construction | Magdy Youssef | progress |
| 06/30/2026 | Lighting controls | Magdy Youssef | energy_progress |
| 06/30/2026 | Interior lighting power | Magdy Youssef | energy_progress |
| 06/23/2026 | Duct leakage testing, insulation and design | Magdy Youssef | energy_progress |
| 06/23/2026 | HVAC-R and service water piping design and insulation | Magdy Youssef | energy_progress |
| 06/23/2026 | Fire-Resistant Penetrations and Joints | Magdy Youssef | special |
| 06/23/2026 | Ventilation and air distribution system | Magdy Youssef | energy_progress |
| 06/23/2026 | HVAC-R and service water heating equipment | Magdy Youssef | energy_progress |
| 06/23/2026 | Energy Code Compliance Inspections | Magdy Youssef | progress |
| 06/23/2026 | Tenant Protection Plan Compliance | Gregory Ralph | special |
| 06/23/2026 | Maintenance information | Magdy Youssef | energy_progress |
| 06/23/2026 | HVAC-R and service water piping design and insulation | Magdy Youssef | energy_progress |
| 06/23/2026 | Fire-Resistant Penetrations and Joints | Magdy Youssef | special |
| 06/23/2026 | Energy Code Compliance Inspections | Magdy Youssef | progress |
| 06/23/2026 | HVAC-R and service water heating equipment | Magdy Youssef | energy_progress |
| 06/23/2026 | HVAC-R and service water heating system controls | Magdy Youssef | energy_progress |
| 06/01/2026 | Tenant Protection Plan Compliance | Gregory Ralph | special |
| 05/13/2026 | Tenant Protection Plan Compliance | Gregory Ralph | special |
| 05/13/2026 | Final | Gregory Ralph | progress |
| 05/13/2026 | Mechanical Systems | Magdy Youssef | special |
| 01/15/2026 | Final | Gregory Ralph | progress |