← Back
Elevator cooperative
211 THOMPSON STREET
MANHATTAN · BIN 1008680
💬 Discuss this project
1887Year Built
6Stories
D4Building Class
R7-2Zoning
55,800 sfGross Floor Area
97Units
LL97 CoveredRent Stabilized0 Open ViolationsFISP: SAFE
Elevator cooperative · Owner of record: 211 THOMPSON OWNER CORP · 10,000 sf lot · 5.58 FAR built · Flood zone X
Locations of Work
Architecture
Roof1p · 1 filing · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PRAT ENTERPRISES407/08/2026
211 THOMPSON OWNERS3304/09/2026
OWNER OF 207 THOMPSON STR203/22/2026
211 THOMPSON OWNER COR103/22/2026
THE OWNER OF103/22/2026
CARLETON MANAGEMENT C103/22/2026
AKAM ASSOCIATES2303/21/2026
INTERSYSTEMS603/21/2026
211 THOMPSON ST OWNERS703/21/2026
MULTIMEDIA203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Rigid Structural Design, LLC1003/21/2026
FRAMEWORK CONSULTANTS403/21/2026
CONVERSANO ASSOCIATES, INC.203/21/2026
BOSCHEN DESIGN, ARCHITECTURE803/21/2026
PRAT ENTERPRISES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
INTERSYSTEMS INSTAL S&SGeneral Contractor607/08/2026
PRAT ENTERPRISES CORPGeneral Contractor607/08/2026
212 BUILDERS INCGeneral Contractor407/08/2026
YOUNG CHOEElectrical203/21/2026
JADCOM CONSTRUCTION CORPGeneral Contractor203/21/2026
INTERSYSTEM CONSTRUCTIONGeneral Contractor104/09/2026
ANSHELEWITZ, ALVINElectrical103/21/2026
ZONE PLUMBING & HEATING CPlumbing107/08/2026
DARIO KNESICHElectrical103/21/2026
KENNEDY, DANIELElectrical103/21/2026
ROBERT COVELLOElectrical103/21/2026
VAN VASSELLElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
LPE ENGINEERING PC3102208/14/2025
OUTSOURCE SPECIAL INSPECT2827208/14/2025
ENTHINK ENGINEERS LLC6247208/21/2023
PRUDIGM ENGINEERING LLCU4304206/29/2023
BOSCHEN DESIGN, ARCHITECT2477209/09/2021
Building Lifecycle
All (162)Filed (16)Permit Issued (14)Signed Off (6)Facade (FISP) (12)Violation (60)Inspection (7)Objection (17)Special Inspection (30)
05/12/2026
Cycle 10 facade report submitted
05/12/2026
Cycle 10 facade inspection completed
05/12/2026
Cycle 10 facade report signed — SAFE
04/17/2026
Cycle 9 facade report signed — SAFE
04/01/2026
Signed off — Alteration
EXTERIOR FACADE REPAIRS AND RESTORATION PER PLANS FILED. THERE IS NO CHANGE IN OCCUPANCY USE OR EGRESS
M01108015-I1
03/27/2026
Permit issued — General Construction
M01108015-I1-ST
03/11/2026
Cycle 9 facade report submitted
03/11/2026
Cycle 9 facade inspection completed
01/20/2026
Permit issued — Sidewalk Shed
M01009438-I1-SH
01/14/2026
Signed off — Alteration
INSTALLATION AND USE OF SUSPENDED SCAFFOLD FOR FACADE RESTORATION/ INSPECTION AS PER PLANS SUBMITTED
M01279664-I1
12/26/2025
Violation issued (HPD, closed)
C
11/25/2025
Cycle 9 facade report submitted
11/25/2025
Cycle 9 facade report signed — UNSAFE
11/18/2025
Cycle 9 facade inspection completed
11/17/2025
Permit issued — Supported Scaffold
M01141348-I1-SF
11/04/2025
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01141348-P1
10/29/2025
Permit issued — Protection and Mechanical Methods
M01308222-I1-PMM
10/28/2025
Filed — Alteration
Installation of a temporary overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01308222-I1
10/22/2025
Permit issued — General Construction
M01108015-I1-GC
10/03/2025
Permit issued — Suspended Scaffold
M01279664-I1-SC
08/29/2025
Filed — Alteration
INSTALLATION AND USE OF SUSPENDED SCAFFOLD FOR FACADE RESTORATION/ INSPECTION AS PER PLANS SUBMITTED
M01279664-I1
08/25/2025
Special inspection requirement — Post-installed Anchors
Roberta Levine
08/25/2025
Special inspection requirement — Final
Roberta Levine
08/25/2025
Special inspection requirement — Masonry
Roberta Levine
08/25/2025
Special inspection requirement — Structural Steel - Welding
JONAR MADRIAGA
08/25/2025
Special inspection requirement — Tenant Protection Plan Compliance
Roberta Levine
08/25/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Roberta Levine
08/14/2025
Filed — Alteration
EXTERIOR FACADE REPAIRS AND RESTORATION PER PLANS FILED. THERE IS NO CHANGE IN OCCUPANCY USE OR EGRESS
M01108015-P1
07/28/2025
Special inspection requirement — Post-installed Anchors
Roberta Levine
07/25/2025
Special inspection requirement — Structural Steel - Welding
JONAR MADRIAGA
07/21/2025
Special inspection requirement — Final
Roberta Levine
07/21/2025
Special inspection requirement — Tenant Protection Plan Compliance
Roberta Levine
07/21/2025
Special inspection requirement — Masonry
Roberta Levine
07/21/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Roberta Levine
03/10/2025
Permit issued — Sidewalk Shed
M01009438-I1-SH
11/15/2024
Permit issued — Supported Scaffold
M01141348-I1-SF
11/14/2024
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01141348-I1
11/14/2024
Filed — Alteration
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01009438-P1
11/12/2024
Permit issued — General Construction
M01108015-I1-GC
10/07/2024
Filed — Alteration
EXTERIOR FACADE REPAIRS AND RESTORATION PER PLANS FILED. THERE IS NO CHANGE IN OCCUPANCY USE OR EGRESS
M01108015-I1
05/16/2024
Objection raised — Scope
05/08/2024
Objection resolved — Addressed
04/30/2024
Objection raised — Scope
04/30/2024
Objection raised — Energy
04/30/2024
Objection raised — Admin
04/30/2024
Objection raised — Admin
04/30/2024
Objection raised — Admin
04/30/2024
Objection raised — Other
04/30/2024
Objection raised — Scope
04/30/2024
Objection raised — Scope
04/30/2024
Objection raised — Accessibility
04/19/2024
Filed — Alteration
INTERIOR RENOVATION OF UNIT 4J AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01017207-I1
04/19/2024
Filed — Alteration
Interior plumbing work in unit 4J. No change in use, egress or occupancy.
M01017456-I1
04/15/2024
Signed off — Alteration
INTERIOR RENOVATION OF UNIT 5N OF AN EXISTING MUTI-FAMILY BUILDING.NO CHANGE OF USE,EGRESS OR OCCUPANCY.
M00890944-I1
03/26/2024
Cycle 9 facade report submitted
03/26/2024
Cycle 9 facade report signed — UNSAFE
03/26/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/13/2024
Cycle 9 facade inspection completed
03/08/2024
Special inspection requirement — Final
03/07/2024
Permit issued — Sidewalk Shed
M01009438-I1-SH
Latest 60 of 162 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offPRAT ENTERPRISES CORP03/27/2026
DOB NOWSidewalk ShedPermit IssuedINTERSYSTEM CONSTRUCTION01/20/2026
DOB NOWSupported ScaffoldPermit IssuedINTERSYSTEMS INSTAL S&S11/17/2025
DOB NOWProtection and Mechanical MethodsPermit IssuedPRAT ENTERPRISES CORP10/29/2025
DOB NOWGeneral ConstructionSigned-offPRAT ENTERPRISES CORP10/22/2025
DOB NOWSuspended ScaffoldSigned-offPRAT ENTERPRISES CORP10/03/2025
DOB NOWSidewalk ShedPermit IssuedINTERSYSTEMS INSTAL S&S03/10/2025
DOB NOWSupported ScaffoldPermit IssuedINTERSYSTEMS INSTAL S&S11/15/2024
DOB NOWGeneral ConstructionSigned-offPRAT ENTERPRISES CORP11/12/2024
DOB NOWSidewalk ShedPermit IssuedINTERSYSTEMS INSTAL S&S03/07/2024
DOB NOWGeneral ConstructionSigned-offJADCOM CONSTRUCTION07/12/2023
DOB NOWStructuralSigned-off212 BUILDERS INC08/30/2022
DOB NOWPlumbingSigned-offZONE PLUMBING & HEATING C12/29/2021
DOB NOWGeneral ConstructionSigned-off212 BUILDERS INC10/05/2021
BISOTISSUEDKTC DESIGN GROUP INC04/03/2018
BISEQISSUEDWONDER WORKS CONSTR CORP03/13/2018
BIS—ISSUEDWONDER WORKS CONSTR CORP03/13/2018
BISPLISSUEDDEMAR PLUMBING CORP01/30/2018
BISOTISSUEDDEMAR PLUMBING CORP01/30/2018
BISOTISSUEDBUILD AD CONTRACTING, LTD09/22/2017
BISPLISSUEDDPH PLUMBING & HTG CORP06/13/2017
BISOTISSUEDALTAIRANCE LLC05/30/2017
BISPLISSUEDVSP MECHANICAL INC03/27/2017
BISEQISSUEDWONDER WORKS CONSTR CORP01/25/2017
BIS—ISSUEDWONDER WORKS CONSTR CORP01/25/2017
BISEQISSUEDREPUBLIC SCAFFOLD&HOIST C10/11/2016
BISPLISSUEDDYCKMAN PLBG AND HTG INC05/28/2014
BISOTISSUEDWONDER WORKS CONSTR CORP04/25/2014
BISOTISSUEDHD HVAC OF NY INC04/07/2014
BISOTISSUEDSELCA CONSTRUCTION INC10/23/2013
BISEQISSUEDINTERSYSTEMS CORPORATION07/09/2012
BISEQISSUEDINTERSYSTEMS CORPORATION07/06/2012
BISEQISSUEDPRATT CONSTRUCTION INC07/06/2012
BISMHISSUEDF.M.A.CONSTRUCTION INC10/14/2011
BISPLISSUEDDPH PLUMBING & HTG CORP04/19/2011
BISOTISSUEDNOOSA CONTRACTOR INC04/18/2011
BISOTISSUEDPOWER CONSULTING SVCS CO03/04/2010
BISOTISSUEDMIRI CONTRACTING INC11/21/2001
BISPLISSUEDAVON PLBG & HTG INC11/21/2001
BISPLISSUEDAVON PLBG & HTG INC12/06/2000
+ 9 more permits on file
1 project · most recent 04/19/2024
Water/Sanitary
FiledStatusContractorScope
04/19/2024——Water/Sanitary
6 projects · most recent 11/26/2024
General Wiring HVAC Wiring
FiledStatusContractorScope
11/26/2024Permit IssuedAMERICAN ENG ELECL SVCS IHVAC Wiring
03/11/2024CompleteAURORA ELECL CONTG INC—
03/08/2024CompleteW 8 ELECTRIC CORP—
04/09/2023Permit IssuedFALCO ELEC'L SERVICES INCGeneral Wiring
01/11/2022Permit IssuedCLAIRMONT ELEC'L CONTR'GGeneral Wiring
09/19/2018CompleteSANT-TEC ELECTRIC INCGeneral Wiring
2 projects · most recent 11/04/2025
Scaffold Sidewalk Shed
FiledStatusContractorScope
11/04/2025Permit IssuedINTERSYSTEMS INSTAL S&SScaffold
11/14/2024Permit IssuedINTERSYSTEM CONSTRUCTIONSidewalk Shed
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
09/02/2022Pass-Final General Construction Non-Directive 14PassView ↗
08/22/2022Fail-Final General Construction Non-Directive 14FailView ↗
08/16/2022Fail-Final General Construction Non-Directive 14FailView ↗
06/06/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/06/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/17/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
02/17/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 44
DateRequirementInspectorRole
08/25/2025Post-installed AnchorsRoberta Levinespecial
08/25/2025FinalRoberta Levineprogress
08/25/2025MasonryRoberta Levinespecial
08/25/2025Structural Steel - WeldingJONAR MADRIAGAspecial
08/25/2025Tenant Protection Plan ComplianceRoberta Levinespecial
08/25/2025Structural Stability – Alterations of existing buildingsRoberta Levinespecial
07/28/2025Post-installed AnchorsRoberta Levinespecial
07/25/2025Structural Steel - WeldingJONAR MADRIAGAspecial
07/21/2025FinalRoberta Levineprogress
07/21/2025Tenant Protection Plan ComplianceRoberta Levinespecial
07/21/2025MasonryRoberta Levinespecial
07/21/2025Structural Stability – Alterations of existing buildingsRoberta Levinespecial
03/08/2024Final—progress
08/23/2023FinalSunil Saigalprogress
08/23/2023Structural Wood FrameSunil Saigalprogress
08/23/2023Structural Stability – Alterations of existing buildingsSunil Saigalspecial
08/23/2023Structural Steel - DetailsSunil Saigalspecial
08/23/2023Post-installed AnchorsSunil Saigalspecial
07/12/2023Insulation placement and R valuesNaeem Anwarenergy_progress
07/12/2023Fire-Resistant Penetrations and JointsNaeem Anwarspecial
07/12/2023Tenant Protection Plan ComplianceNaeem Anwarspecial
07/12/2023Energy Code Compliance InspectionsNaeem Anwarprogress
07/12/2023FinalNaeem Anwarprogress
07/12/2023Fire-Resistance Rated ConstructionNaeem Anwarprogress
07/12/2023Interior lighting powerNaeem Anwarenergy_progress
Latest 25 of 44.
▾Documents — 426 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch12
09/03/2026M00556874-P1Request digital key ↗
08/30/2026M00890944-P1Request digital key ↗
08/30/2026M00890944-I1Request digital key ↗
Showing 3 of 12 on file for this type
▸DOB NOWPlans/Sketch - General Construction1
09/03/2026M00447341-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/15/2026M00444297-I1Request digital key ↗
▸Applications & Permits84
▸BISPLAN / WORK APPROVAL APPLICATION52
01/15/2026100315062Open ↗
01/07/2026100315062Open ↗
12/12/2025100315062Open ↗
Showing 3 of 52 on file for this type
▸BISWORK PERMIT APPLICATION24
04/04/2018123305752Open ↗
03/19/2018122557081Open ↗
03/14/2018122557081Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWLPC Approval/Permit7
09/03/2026M00556874-P1Open ↗
08/15/2026M00556874-I1Open ↗
08/13/2026M00447341-I1Open ↗
Showing 3 of 7 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
02/09/2018122557081Open ↗
▸Seals & Professional Certifications101
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION32
07/10/2019122557081Open ↗
07/10/2019122557081Open ↗
06/04/2019123305752Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature19
09/27/2026M00556874-I1Open ↗
09/27/2026M00556874-I1Open ↗
09/27/2026M00556874-I1Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature15
09/03/2026M00556874-P1Open ↗
09/03/2026M00556874-I1Open ↗
08/30/2026M00890944-P1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWProgress Inspector Seal & Signature12
09/27/2026M00556874-I1Open ↗
09/27/2026M00556874-I1Open ↗
09/02/2026M00556874-P1Open ↗
Showing 3 of 12 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST11
12/04/2017123266964Open ↗
07/31/2017123305752Open ↗
Showing 2 of 11 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT6
12/04/2017123266964Open ↗
07/31/2017123305752Open ↗
Showing 2 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment31
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE14
05/29/2018123266964Open ↗
05/23/2018123266964Open ↗
05/03/2018123266964Open ↗
Showing 3 of 14 on file for this type
▸BISSELF-CERT PLUMBING NOTICE7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISEQUIPMENT USE PERMITS5
07/25/2019122557081Open ↗
07/25/2019122557081Open ↗
07/25/2019122557081Open ↗
Showing 3 of 5 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA3
08/30/2018122557081Open ↗
08/27/2018122557081Open ↗
04/10/2018122788304Open ↗
▸BISSCHEDULE B - PLUMBING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT1
07/25/2019122557081Open ↗
▸Safety & Tenant Protection8
▸BISTenant Protection Plan and Notes4
12/04/2017123266964Open ↗
07/31/2017123305752Open ↗
03/16/2017123011631Open ↗
Showing 3 of 4 on file for this type
▸BISSRO MD ANTI-HARASSMENT CHECKLIST2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSTREET TREE CHECKLIST1
02/02/2017123011631Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00444297-I1Open ↗
▸Environmental & Asbestos25
▸DOB NOWDEP ACP-5: Asbestos Assessment Report10
09/03/2026M00556874-P1Open ↗
08/30/2026M00890944-I1Open ↗
08/30/2026M00890944-P1Open ↗
Showing 3 of 10 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)8
12/04/2017123266964Open ↗
07/31/2017123305752Open ↗
02/02/2017123011631Open ↗
Showing 3 of 8 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISASBESTOS-EXEMPTION (ASB4)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance19
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS15
06/04/2019123305752Open ↗
09/13/2018123011631Open ↗
07/02/2018122557081Open ↗
Showing 3 of 15 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS2
06/04/2019123305752Open ↗
09/13/2018123011631Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
01/03/2023123266964Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026M00447341-I1Open ↗
▸Inspections & Test Reports8
▸BISTECHNICAL REPORT: RESPONSIBILITY4
12/01/2025100315062Open ↗
11/24/2025100315062Open ↗
11/19/2025100315062Open ↗
Showing 3 of 4 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
01/03/2023123266964Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: SOIL INSPECTION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs53
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST21
04/25/2023120276334Open ↗
01/04/2023123266964Open ↗
07/20/2021122788304Open ↗
Showing 3 of 21 on file for this type
▸BISLANDMARKS APPROVAL9
06/04/2019123305752Open ↗
12/04/2017123266964Open ↗
07/31/2017123305752Open ↗
Showing 3 of 9 on file for this type
▸BISADMINISTRATIVE OBJECTIONS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE5
09/24/2018122557081Open ↗
09/04/2018122557081Open ↗
08/01/2018122557081Open ↗
Showing 3 of 5 on file for this type
▸BISLANDMARKS SIGNOFF4
01/03/2023123266964Open ↗
07/20/2021122788304Open ↗
07/19/2021122557081Open ↗
Showing 3 of 4 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
01/07/2026100315062Open ↗
09/17/2018122557081Open ↗
08/30/2018122557081Open ↗
Showing 3 of 4 on file for this type
▸BISFINAL2
04/25/2023120276334Open ↗
01/03/2023123266964Open ↗
▸DOB NOWLandmark Approval2
08/13/2026M01108015-P1Open ↗
08/13/2026M01108015-I1Open ↗
▸BISSUPERSEDING LETTER1
04/04/2018123305752Open ↗
▸Cost, Insurance & Ownership22
▸BISCOST AFFIDAVIT17
06/04/2019123305752Open ↗
09/13/2018123011631Open ↗
12/04/2017123266964Open ↗
Showing 3 of 17 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW33
04/25/2023120276334Open ↗
01/04/2023123266964Open ↗
11/20/2020122788304Open ↗
▸BISOK TO ISSUE TCO PENDING RESOLUTION OFOPEN FACADE VIOLATION - AFFIDAVIT ATTACHED2
01/23/2026122557081Open ↗
04/18/2025122557081Open ↗
▸Filing & Intake Forms56
▸BISBOROUGH INTAKE FORM26
04/06/2020122557081Open ↗
01/10/2020122557081Open ↗
10/10/2019122557081Open ↗
Showing 3 of 26 on file for this type
▸BISEFILING COVER SHEET16
12/04/2017123266964Open ↗
07/31/2017123305752Open ↗
02/02/2017123011631Open ↗
Showing 3 of 16 on file for this type
▸BISADDITIONAL INFORMATION13
01/04/2023123266964Open ↗
05/30/2019123305752Open ↗
09/06/2018122557081Open ↗
Showing 3 of 13 on file for this type
▸BISeFiling Job Application Cover Sheet1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Other Documents5
▸BISSupporting Document: Fee Exempt1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISFEMA FORM (81-31): ELEVATION CERTIFICATE1
07/02/2018122557081Open ↗
▸BISPLOT DIAGRAM1
02/02/2017123011631Open ↗
▸DOB NOWCalculations1
08/13/2026M01279664-I1Open ↗