| Owner | Filings | Most Recent |
|---|---|---|
| KATARIA | 16 | 09/12/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ASHOKE CHAKRABORTY RA | 5 | 07/16/2026 |
| EDWARD C. HICKS RA | 1 | 01/13/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CYCLURA PLBG & HTG INC | Plumbing | 7 | 07/08/2026 |
| L J & A CONSTRUCTION CORP | General Contractor | 2 | 07/08/2026 |
| JAGDEEP DEOL | Electrical | 1 | 03/21/2026 |
| JAGDEEP S. DEOL | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| KOJO SIMPSON ARCHITECT | 1664 | 1 | 01/10/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | CYCLURA PLBG & HTG INC | 12/22/2025 |
| DOB NOW | General Construction | Signed-off | L J & A CONSTRUCTION CORP | 10/06/2025 |
| DOB NOW | Plumbing | Permit Issued | CYCLURA PLBG & HTG INC | 05/13/2024 |
| DOB NOW | General Construction | Signed-off | L J & A CONSTRUCTION CORP | 05/02/2024 |
| BIS | OT | ISSUED | A. INTERNATIONAL LTD | 11/13/2003 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2026 | Permit Issued | CYCLURA PLBG & HTG INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/24/2024 | Permit Issued | JD ELECTRICAL ENTERPRISES | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/17/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/10/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/08/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 05/08/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/07/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 04/30/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/30/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/16/2026 | HVAC-R and service water piping design and insulation | ASHOKE CHAKRABORTY | energy_progress |
| 07/16/2026 | Energy Code Compliance Inspections | ASHOKE CHAKRABORTY | progress |
| 05/21/2026 | Energy Code Compliance Inspections | ASHOKE CHAKRABORTY | progress |
| 05/21/2026 | HVAC-R and service water piping design and insulation | ASHOKE CHAKRABORTY | energy_progress |
| 12/18/2025 | HVAC-R and service water piping design and insulation | ASHOKE CHAKRABORTY | energy_progress |
| 12/18/2025 | Energy Code Compliance Inspections | ASHOKE CHAKRABORTY | progress |
| 01/10/2024 | Masonry | KOJO SIMPSON | special |
| 01/10/2024 | Structural Stability – Alterations of existing buildings | KOJO SIMPSON | special |
| 01/10/2024 | Fenestration and door U-factor and product ratings | EDWARD HICKS | energy_progress |
| 01/10/2024 | Fenestration areas | EDWARD HICKS | energy_progress |
| 01/10/2024 | Subgrade Inspections | KOJO SIMPSON | special |
| 01/10/2024 | Interior lighting power | EDWARD HICKS | energy_progress |
| 01/10/2024 | Air barrier - visual inspection | EDWARD HICKS | energy_progress |
| 01/10/2024 | Fenestration air leakage | EDWARD HICKS | energy_progress |
| 01/10/2024 | Insulation placement and R values | EDWARD HICKS | energy_progress |
| 01/10/2024 | Concrete - Cast-In-Place | KOJO SIMPSON | special |
| 11/24/2023 | Fire-Resistant Penetrations and Joints | KOJO SIMPSON | special |
| 11/24/2023 | Energy Code Compliance Inspections | EDWARD HICKS | progress |
| 11/24/2023 | Fire-Resistance Rated Construction | EDWARD HICKS | progress |
| 11/24/2023 | Final | EDWARD HICKS | progress |
| 01/13/2023 | Final | — | progress |
| 01/13/2023 | Footing and Foundation | — | progress |
| 01/13/2023 | Energy Code Compliance Inspections | — | progress |
| 01/13/2023 | Fire-Resistance Rated Construction | — | progress |
| 01/13/2023 | Exterior lighting power | — | energy_progress |