Locations of Work
Architecture
Basement1p · 1 filing · 13 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/08/2016$430K—— → —$208/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
FREDA DESIGN ARCHITECT, PLLC509/11/2021
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CLEMENTE ALCANTARA MENDEZGeneral Contractor407/08/2026
PLBG P & H INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
FREDA DESIGN ARCHITECT PL837409/11/2021
Building Lifecycle
All (26)Filed (5)Permit Issued (3)Signed Off (3)Inspection (4)Special Inspection (11)
12/06/2021
Signed off — Alteration
test all existing fixtures and piping for integrity to turn water and gas back on, replace oil fire boiler with new gas fired boiler, install new gas HWH, relocate laundry tub & install necessary plumbing fixtures and piping for new bathroom in basement
X00495540-I1
09/27/2021
Signed off — Alteration
erect temporary construction fence along Lydig Avenue for pedestrian protection.
X00495530-I1
09/27/2021
Signed off — Alteration
PROPOSE TO REPAIR FIRE DAMAGED AREAS IN THE BASE, 1ST & 2ND FL OF 1 FAMILY 3 STORY AND INSTALL NEW WINDOWS, INSULATION AT PERIMETER WALLS AND UNDER ROOF. REPLACE HEATING UNDER separate APP & OTHER PLUMBING AS REQ., NO CHANGE IN USE OR MEANS OF EGRESS.
X00495535-I1
09/23/2021
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/22/2021
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/15/2021
Special inspection requirement — Insulation placement and R values
Antonio Freda
09/15/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Antonio Freda
09/15/2021
Special inspection requirement — Energy Code Compliance Inspections
Antonio Freda
09/15/2021
Special inspection requirement — Fenestration air leakage
Antonio Freda
09/15/2021
Special inspection requirement — Air barrier - visual inspection
Antonio Freda
09/15/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
Antonio Freda
09/11/2021
Filed — Alteration
PROPOSE TO REPAIR FIRE DAMAGED AREAS IN THE BASE, 1ST & 2ND FL OF 1 FAMILY 3 STORY AND INSTALL NEW WINDOWS, INSULATION AT PERIMETER WALLS AND UNDER ROOF. REPLACE HEATING UNDER separate APP & OTHER PLUMBING AS REQ., NO CHANGE IN USE OR MEANS OF EGRESS.
X00495535-P1
07/09/2021
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/09/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/29/2021
Filed — Alteration
test all existing fixtures and piping for integrity to turn water and gas back on, replace oil fire boiler with new gas fired boiler, install new gas HWH, relocate laundry tub & install necessary plumbing fixtures and piping for new bathroom in basement
X00495540-P1
06/28/2021
Special inspection requirement — Energy Code Compliance Inspections
Antonio Freda
06/28/2021
Special inspection requirement — HVAC-R and service water heating equipment
Antonio Freda
06/28/2021
Special inspection requirement — HVAC-R and service water heating system controls
Antonio Freda
06/28/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
Antonio Freda
06/28/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Antonio Freda
05/24/2021
Permit issued — Plumbing
X00495540-I1-PL
05/07/2021
Permit issued — Construction Fence
X00495530-I1-FN
05/05/2021
Permit issued — General Construction
X00495535-I1-GC
04/07/2021
Filed — Alteration
test all existing fixtures and piping for integrity to turn water and gas back on, replace oil fire boiler with new gas fired boiler, install new gas HWH, relocate laundry tub & install necessary plumbing fixtures and piping for new bathroom in basement
X00495540-I1
04/07/2021
Filed — Alteration
erect temporary construction fence along Lydig Avenue for pedestrian protection.
X00495530-I1
04/07/2021
Filed — Alteration
PROPOSE TO REPAIR FIRE DAMAGED AREAS IN THE BASE, 1ST & 2ND FL OF 1 FAMILY 3 STORY AND INSTALL NEW WINDOWS, INSULATION AT PERIMETER WALLS AND UNDER ROOF. REPLACE HEATING UNDER separate APP & OTHER PLUMBING AS REQ., NO CHANGE IN USE OR MEANS OF EGRESS.
X00495535-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offPLBG P & H INC05/24/2021
DOB NOWConstruction FenceSigned-offCLEMENTE ALCANTARA MENDEZ05/07/2021
DOB NOWGeneral ConstructionSigned-offCLEMENTE ALCANTARA MENDEZ05/05/2021
1 project · most recent 05/23/2021
General Wiring
FiledStatusContractorScope
05/23/2021CompleteJOE ELECTRICAL INCGeneral Wiring
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
09/23/2021Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/22/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/09/2021Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/09/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 11
DateRequirementInspectorRole
09/15/2021Insulation placement and R valuesAntonio Fredaenergy_progress
09/15/2021Fire-Resistant Penetrations and JointsAntonio Fredaspecial
09/15/2021Energy Code Compliance InspectionsAntonio Fredaprogress
09/15/2021Fenestration air leakageAntonio Fredaenergy_progress
09/15/2021Air barrier - visual inspectionAntonio Fredaenergy_progress
09/15/2021Fenestration and door U-factor and product ratingsAntonio Fredaenergy_progress
06/28/2021Energy Code Compliance InspectionsAntonio Fredaprogress
06/28/2021HVAC-R and service water heating equipmentAntonio Fredaenergy_progress
06/28/2021HVAC-R and service water heating system controlsAntonio Fredaenergy_progress
06/28/2021HVAC-R and service water piping design and insulationAntonio Fredaenergy_progress
06/28/2021Fire-Resistant Penetrations and JointsAntonio Fredaspecial
▾Documents — 27 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/25/2026X00495535-P1Request digital key ↗
08/25/2026X00495535-I1Request digital key ↗
08/25/2026X00495530-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature9
08/27/2026X00495540-P1Open ↗
08/27/2026X00495540-P1Open ↗
08/27/2026X00495540-P1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/25/2026X00495535-I1Open ↗
08/25/2026X00495535-P1Open ↗
08/25/2026X00495530-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/27/2026X00495540-P1Open ↗
08/25/2026X00495535-I1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/25/2026X00495535-I1Open ↗
08/25/2026X00495535-P1Open ↗
08/25/2026X00495540-P1Open ↗
Showing 3 of 4 on file for this type
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026X00495535-I1Open ↗
08/13/2026X00495540-I1Open ↗