← Back
Two family converted from one family
212-18 113 AVENUE
QUEENS · Queens Village · BIN 4240102
💬 Discuss this project
1935Year Built
2.5Stories
B3Building Class
R3-2Zoning
1,712 sfGross Floor Area
2Units
82 Open Violations ▸FDNY Report ↗
Two family converted from one family · 3,000 sf lot · 0.57 FAR built · Flood zone X
Locations of Work
Architecture
Roof2p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC104/21/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KAMTECH RESTORATION CORP203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KAMTECH RESTORATION CORPGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854104/21/2025
Building Lifecycle
All (68)Filed (1)Permit Issued (1)Signed Off (1)Violation (60)Special Inspection (5)
06/25/2025
Signed off — Alteration
ROOFTOP SOLAR INSTALLATION. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Q01213738-I1
04/22/2025
Permit issued — Solar
Q01213738-I1-SL
04/21/2025
Filed — Alteration
ROOFTOP SOLAR INSTALLATION. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Q01213738-I1
04/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
04/21/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
04/21/2025
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
04/21/2025
Special inspection requirement — Final
TOM PETERSEN
04/21/2025
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
12/30/2024
Violation issued (HPD, open)
B
12/30/2024
Violation issued (HPD, open)
C
12/30/2024
Violation issued (HPD, open)
C
12/30/2024
Violation issued (HPD, open)
C
12/30/2024
Violation issued (HPD, open)
C
12/25/2024
Violation issued (HPD, open)
B
12/25/2024
Violation issued (HPD, open)
C
12/25/2024
Violation issued (HPD, open)
B
12/25/2024
Violation issued (HPD, open)
C
12/25/2024
Violation issued (HPD, open)
B
12/25/2024
Violation issued (HPD, open)
C
12/25/2024
Violation issued (HPD, open)
B
12/25/2024
Violation issued (HPD, open)
C
12/23/2024
Violation issued (HPD, open)
C
12/22/2024
Violation issued (HPD, open)
C
12/15/2024
Violation issued (HPD, open)
B
12/15/2024
Violation issued (HPD, open)
C
12/15/2024
Violation issued (HPD, open)
C
12/15/2024
Violation issued (HPD, open)
C
12/15/2024
Violation issued (HPD, open)
C
12/15/2024
Violation issued (HPD, open)
C
12/15/2024
Violation issued (HPD, open)
C
12/15/2024
Violation issued (HPD, open)
B
12/15/2024
Violation issued (HPD, open)
C
12/15/2024
Violation issued (HPD, open)
B
12/07/2024
Violation issued (HPD, open)
C
12/07/2024
Violation issued (HPD, open)
B
12/07/2024
Violation issued (HPD, open)
B
12/07/2024
Violation issued (HPD, open)
B
12/07/2024
Violation issued (HPD, open)
C
12/07/2024
Violation issued (HPD, open)
A
12/07/2024
Violation issued (HPD, open)
A
12/07/2024
Violation issued (HPD, open)
C
12/06/2024
Violation issued (HPD, open)
B
12/03/2024
Violation issued (HPD, open)
B
12/03/2024
Violation issued (HPD, open)
B
12/03/2024
Violation issued (HPD, open)
B
12/03/2024
Violation issued (HPD, open)
B
10/07/2024
Violation issued (HPD, open)
I
10/05/2024
Violation issued (HPD, open)
C
10/05/2024
Violation issued (HPD, open)
C
10/05/2024
Violation issued (HPD, closed)
A
10/05/2024
Violation issued (HPD, open)
B
10/05/2024
Violation issued (HPD, open)
B
10/05/2024
Violation issued (HPD, open)
B
10/05/2024
Violation issued (HPD, open)
C
10/05/2024
Violation issued (HPD, open)
B
10/05/2024
Violation issued (HPD, open)
B
10/05/2024
Violation issued (HPD, open)
B
10/04/2024
Violation issued (HPD, open)
B
10/04/2024
Violation issued (HPD, open)
C
10/04/2024
Violation issued (HPD, open)
C
Latest 60 of 68 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offKAMTECH RESTORATION CORP04/22/2025
1 project · most recent 04/21/2025
FiledStatusContractorScope
04/21/2025CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
04/21/2025Fire-Resistant Penetrations and JointsTOM PETERSENspecial
04/21/2025Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
04/21/2025Energy Code Compliance InspectionsTOM PETERSENprogress
04/21/2025FinalTOM PETERSENprogress
04/21/2025Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026Q01213738-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/27/2026Q01213738-I1Open ↗
08/27/2026Q01213738-I1Open ↗
08/27/2026Q01213738-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/27/2026Q01213738-I1Open ↗
08/27/2026Q01213738-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/20/2026Q01213738-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/20/2026Q01213738-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01213738-I1Open ↗