| Owner | Filings | Most Recent |
|---|---|---|
| ABS PARTNERS REAL ESTATE, LLC | 29 | 09/13/2026 |
| ZWANGER PESIRI | 4 | 07/08/2026 |
| LEVY PROPERTIES | 7 | 07/08/2026 |
| CASELLA CONSTRUCTION C | 2 | 03/22/2026 |
| MIXED FOURSOME LLC A NEW YORK | 4 | 03/21/2026 |
| NORTHERN BOULEVARD ASSOCIATES | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| HNY CONSULTING ENGINEERS LLC | 2 | 04/02/2026 |
| SARGENTI ARCHITECTS | 1 | 04/02/2026 |
| HNY CONSULTING ENGINEERS, LCC | 1 | 04/02/2026 |
| VINCENT J. LIOTTA P.E. | 1 | 09/18/2024 |
| HC ARCHITECT, PC | 2 | 05/04/2023 |
| FLUSHING ENGINEERING SERVICE PC | 6 | 04/26/2023 |
| WCW ENGINEERS INC | 1 | 10/16/2019 |
| RICHARD WAINER ARCHITECT, PLLC | 2 | 07/24/2019 |
| NORMAN C. LOK, PE | 1 | 01/12/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| D R BROWN | 4 | 03/21/2026 |
| LOUIS STRIAR | 2 | 03/21/2026 |
| RPO | 2 | 03/21/2026 |
| JP EXPEDITE | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DIMENSIONAL INC | General Contractor | 3 | 07/08/2026 |
| ZCREW CONSTRUCTION CORP | General Contractor | 2 | 07/08/2026 |
| SIGNSTAR NYC | Scaffold | 2 | 07/08/2026 |
| ULTIMATE SIGNS DESIGNS | Scaffold | 2 | 07/08/2026 |
| TT MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| CITY SIGNS | Scaffold | 1 | 07/08/2026 |
| SIGNS CAD | Scaffold | 1 | 07/08/2026 |
| STALWART PLUMBING CORP | Plumbing | 1 | 08/07/2026 |
| AFGO MECHANICAL SVCS INC | General Contractor | 1 | 07/08/2026 |
| MES CONSTRUCTION CORP | Plumbing | 1 | 07/08/2026 |
| AMERICAN STANDARD PLUMBING & | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SHAHRISH SHUVO ENGINEERIN | 8524 | 2 | 04/02/2026 |
| VINCENT J. LIOTTA P. E. | 1974 | 1 | 09/18/2024 |
| FLUSHING ENGINEERING SERV | 4373 | 6 | 04/26/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | STALWART PLUMBING CORP | 08/06/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | DIMENSIONAL INC | 05/21/2026 |
| DOB NOW | General Construction | Permit Issued | DIMENSIONAL INC | 05/21/2026 |
| DOB NOW | General Construction | Permit Issued | DIMENSIONAL INC | 05/21/2026 |
| DOB NOW | Mechanical Systems | Signed-off | AFGO MECHANICAL SVCS | 09/26/2024 |
| DOB NOW | Sign | Signed-off | ELMER DAWSON | 05/05/2023 |
| DOB NOW | Sprinklers | Signed-off | AMERICAN STANDARD PLUMBIN | 02/03/2023 |
| DOB NOW | Mechanical Systems | Signed-off | ZCREW CONSTRUCTION CORP | 01/20/2023 |
| DOB NOW | General Construction | Signed-off | ZCREW CONSTRUCTION CORP | 01/20/2023 |
| DOB NOW | Plumbing | Signed-off | MES CONSTRUCTION CORP | 01/17/2023 |
| DOB NOW | Sign | Signed-off | SIGNS CAD CORP | 01/12/2021 |
| DOB NOW | Plumbing | Signed-off | RENTOM GROUP CORP | 10/24/2019 |
| DOB NOW | Sign | Signed-off | ULTIMATE SIGNS&DESIGNS CO | 07/25/2019 |
| DOB NOW | Sign | Signed-off | ULTIMATE SIGNS&DESIGNS CO | 07/24/2019 |
| DOB NOW | Sign | Signed-off | SIGNSTAR NYC | 10/23/2018 |
| DOB NOW | Sign | Signed-off | SIGNSTAR NYC | 02/21/2018 |
| BIS | — | ISSUED | JAMES J.LEONARD ARCHITECT | 08/14/2020 |
| BIS | OT | ISSUED | OCS BUILDERS GROUP LLC | 08/23/2019 |
| BIS | PL | ISSUED | MCMANUS MECH MAINT P&H INC | 07/12/2019 |
| BIS | PL | ISSUED | WASOFF PLBG & UTILITY CO | 04/05/2019 |
| BIS | PL | ISSUED | WASOFF PLBG & UTILITY CO | 03/07/2019 |
| BIS | MH | ISSUED | THE TURBOCHYLL COMPANY IN | 02/05/2019 |
| BIS | SP | ISSUED | MEJ PLUMBING LLC | 09/28/2018 |
| BIS | PL | ISSUED | WASOFF PLBG & UTILITY CO | 02/26/2018 |
| BIS | SP | ISSUED | MEJ PLUMBING LLC | 09/06/2017 |
| BIS | OT | ISSUED | RENAISSANCE 1 CORP | 08/31/2017 |
| BIS | OT | ISSUED | RENAISSANCE 1 CORP | 08/31/2017 |
| BIS | MH | ISSUED | WITH PRIDE AIR CONDITIONING | 08/29/2017 |
| BIS | PL | ISSUED | WASOFF PLBG & UTILITY CO | 08/24/2017 |
| BIS | OT | ISSUED | RENAISSANCE 1 CORP | 08/14/2017 |
| BIS | OT | ISSUED | RENAISSANCE 1 CORP | 02/16/2017 |
| BIS | OT | ISSUED | RENAISSANCE 1 CORP | 02/14/2017 |
| BIS | — | ISSUED | NORTH SHORE NEON SIGN CO | 10/01/2015 |
| BIS | OT | ISSUED | PACIFIC WEST CONSTRUCTION | 07/19/2013 |
| BIS | OT | ISSUED | PACIFIC WEST CONSTRUCTION | 09/18/2012 |
| BIS | SP | ISSUED | ALLSTATE SPRINKLER LLC | 04/19/2012 |
| BIS | PL | ISSUED | SKYLINE P & H INC | 12/16/2011 |
| BIS | OT | ISSUED | CLOUTIER BUILDING CORP | 12/15/2011 |
| BIS | MH | ISSUED | CLOUTIER BUILDING CORP | 12/15/2011 |
| BIS | — | ISSUED | NATIONAL MAINTENANCE, INC | 11/09/2011 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/02/2026 | Signed-off | STALWART PLUMBING CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2023 | Complete | GUIDING LIGHT ELECTRIC IN | — |
| 04/19/2023 | Complete | VOLTRON ELECTRIC LLC | General Wiring |
| 07/29/2021 | Complete | CSI ELEC'L & MECHANICAL I | General Wiring |
| 06/13/2021 | Complete | ACCURATE ELEC'L CORP. | General Wiring |
| 01/22/2021 | Complete | SIGNS CAD CORP | — |
| 07/26/2019 | Complete | ULTIMATE SIGNS & ELEC COR | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/19/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/19/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/28/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 05/02/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/02/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/02/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/28/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 04/10/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/06/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/31/2026 | Lighting controls | Shahrish Shuvo | energy_progress |
| 03/31/2026 | Interior lighting power | Shahrish Shuvo | energy_progress |
| 03/18/2026 | Final | Shahrish Shuvo | progress |
| 03/18/2026 | Fire-Resistance Rated Construction | Shahrish Shuvo | progress |
| 03/18/2026 | Final | Shahrish Shuvo | progress |
| 03/18/2026 | Fire-Resistant Penetrations and Joints | Shahrish Shuvo | special |
| 08/02/2023 | Mechanical Systems | Vincent Liotta | special |
| 08/02/2023 | Final | Vincent Liotta | progress |
| 08/02/2023 | HVAC-R and service water heating system controls | Vincent Liotta | energy_progress |
| 08/02/2023 | HVAC-R and service water heating equipment | Vincent Liotta | energy_progress |
| 08/02/2023 | Maintenance information | Vincent Liotta | energy_progress |
| 08/02/2023 | HVAC-R and service water piping design and insulation | Vincent Liotta | energy_progress |
| 04/26/2023 | Interior lighting power | KY FU | energy_progress |
| 04/26/2023 | Fire-Resistance Rated Construction | KY FU | progress |
| 04/26/2023 | Energy Code Compliance Inspections | KY FU | progress |
| 04/26/2023 | Fire-Resistant Penetrations and Joints | KY FU | special |
| 04/26/2023 | Lighting controls | KY FU | energy_progress |
| 01/09/2023 | HVAC-R and service water piping design and insulation | KY FU | energy_progress |
| 01/09/2023 | Fire-Resistant Penetrations and Joints | KY FU | special |
| 01/09/2023 | Energy Code Compliance Inspections | KY FU | progress |
| 01/09/2023 | HVAC-R and service water heating equipment | KY FU | energy_progress |
| 11/25/2020 | Final | Hackjong Choi | progress |
| 07/24/2019 | Final | Richard Wainer | progress |
| 07/24/2019 | Final | Richard Wainer | progress |