← Back
Two stories - detached, small or mid-size
212-21 113 AVENUE
QUEENS · Queens Village · BIN 4240156
💬 Discuss this project
1925Year Built
2.5Stories
A1Building Class
R3-2Zoning
1,706 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 3,000 sf lot · 0.57 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalGeneral
Roof3p · 1 filing · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
OWNER OF 212-21 113 AVE103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC108/06/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNCO CAPITAL203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNCO CAPITAL LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244108/06/2025
Building Lifecycle
All (10)Filed (1)Permit Issued (1)Violation (3)Special Inspection (5)
08/13/2025
Permit issued — Solar
Q01262774-I1-SL
08/06/2025
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON ROOF. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q01262774-I1
07/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
07/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
07/28/2025
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
07/28/2025
Special inspection requirement — Final
NARESH MAHANGU
07/28/2025
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
03/27/2001
Violation issued (ECB, closed)
HPD
03/26/2001
Violation issued (DOB, closed)
VW*-VIOLATION - WORK W/O PERMIT DISMISSED
03/26/2001
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedSUNCO CAPITAL LLC08/13/2025
2 projects · most recent 10/08/2025
FiledStatusContractorScope
10/08/2025Permit IssuedTRIANGLE ELECTRIC INC.1 meters
07/31/2025Permit IssuedBERGER QUALITY ELEC'L CON—
1 project · most recent 08/06/2025
FiledStatusContractorScope
08/06/2025Permit IssuedSUNCO CAPITAL LLC20 panels, 8.6 kw, 836 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
07/28/2025Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
07/28/2025Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
07/28/2025Energy Code Compliance InspectionsNARESH MAHANGUprogress
07/28/2025FinalNARESH MAHANGUprogress
07/28/2025Air barrier - visual inspectionNARESH MAHANGUenergy_progress
▾Documents — 6 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026Q01262774-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
09/16/2026Q01262774-I1Open ↗
09/16/2026Q01262774-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01262774-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/16/2026Q01262774-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01262774-I1Open ↗