Two stories - detached, small or mid-size
212-79 WHITEHALL TERRACE
QUEENS · Queens Village · BIN 4228925
💬 Discuss this project
1930Year Built
2.5Stories
A1Building Class
R2Zoning
2,210 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 4,000 sf lot · 0.55 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofRepair existing brick and retaining wall1p · 1 filing · 10 docs
Floor 2Interior renovation and addition to single family house1 filing · 9 docs
Floor 1Interior renovation and addition to single family house1 filing · 9 docs
CellarInterior renovation and addition to single family house1 filing · 9 docs
Site & exteriorRepair existing brick and retaining wall1 filing · 10 docs
Filed — no permit issuedTemporary construction fence for renovation2p · 1 filing · 2 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
M.S. Savani Architect306/04/2026
Doyun Kim; RA106/24/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Javith Camino103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYC Building SolutionsGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Doyun Kim; RA7415106/24/2021
Building Lifecycle
11/20/2026
Objection raised — Other
10/31/2026
Objection raised — Energy
08/25/2026
Objection resolved — Addressed
08/24/2026
Objection raised — Zoning
08/24/2026
Objection raised — Scope
45 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offNYC Building Solutions09/08/2021
1 project · most recent 06/01/2026
Heating and Air Conditioning Systems
FiledStatusContractorScope
06/01/2026——Heating and Air Conditioning Systems
1 project · most recent 06/01/2026
Gas Water/Sanitary
FiledStatusContractorScope
06/01/2026——Gas, Water/Sanitary
1 project · most recent 06/01/2026
Wood
FiledStatusContractorScope
06/01/2026——Wood
▾Special Inspection Requirements (DOB NOW) — 35
DateRequirementInspectorRole
05/19/2026HVAC-R and service water heating equipment—energy_progress
05/19/2026HVAC-R and service water piping design and insulation—energy_progress
05/19/2026Fenestration air leakage—energy_progress
05/19/2026Permanent certificate—energy_progress
05/19/2026HVAC-R and service water heating equipment—energy_progress
05/19/2026Insulation placement and R values—energy_progress
05/19/2026Protection of exposed foundation insulation—energy_progress
05/19/2026Energy Code Compliance Inspections—progress
05/19/2026HVAC-R and service water heating system controls—energy_progress
05/19/2026Maintenance information—energy_progress
05/19/2026HVAC-R and service water piping design and insulation—energy_progress
05/19/2026Concrete - Cast-In-Place—special
05/19/2026Excavations - Sheeting, Shoring, and Bracing—special
05/19/2026Subgrade Inspections—special
05/19/2026Wall Panels, Curtain Walls, and Veneers—special
05/19/2026Energy Code Compliance Inspections—progress
05/19/2026Fire-Resistance Rated Construction—progress
05/19/2026Structural Wood Frame—progress
05/19/2026Air barrier - visual inspection—energy_progress
05/19/2026Interior lighting power—energy_progress
05/19/2026HVAC-R and service water heating system controls—energy_progress
05/19/2026Fenestration and door U-factor and product ratings—energy_progress
05/19/2026Fenestration areas—energy_progress
05/19/2026Maintenance information—energy_progress
05/19/2026Duct leakage testing, insulation and design—energy_progress
Latest 25 of 35.