← Back
BuildNYC
Training school
Democracy Prep Harlem Charter High School
212 WEST 120TH STREET · BIN 1058447
💬 Discuss this project
1930Year Built
4Stories
W4Building Class
R7AZoning
76,794 sfGross Floor Area
1Units
LL97 Covered11 Active Violations 1 unresolved · 10 paperwork only ▸
Training school · Owner of record: NYC Department of Education · 30,275 sf lot · 2.54 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofDemocracy Prep Harlem Charter High School11p · 1 filing · 17 docs
Floor 4Democracy Prep Harlem Charter High School23p · 2 filings · 18 docs
Floor 3Democracy Prep Harlem Charter High School15p · 2 filings · 18 docs
Floor 2
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC School Construction Authority9804/09/2026
Democracy Prep Harlem Middle School903/22/2026
NYC Department of Housing Preservation and Development403/21/2026
NYC Department of Education303/22/2026
Volmar Services203/21/2026
City103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Eme Consulting Engineering Group503/16/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM Zoning603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Truline Construction ServiceGeneral Contractor1503/21/2026
Avalon ElectricElectrical803/21/2026
Dia General Contruction IGeneral Contractor603/21/2026
Charan Electrical Enterp'sElectrical103/21/2026
DH Eagle Plumbing & HeatingPlumbing107/08/2026
Gemini Electric CoElectrical103/22/2026
Raptor MechanicalPlumbing107/08/2026
Nieves WilliamElectrical103/21/2026
Stanco System Electrical ContElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AK Engineering678303/16/2023
JPC Logistics Dba JPCL EN351207/14/2022
Building Lifecycle
All (109)Filed (5)Permit Issued (9)Signed Off (1)Violation (60)Inspection (2)Objection (2)Special Inspection (30)
08/03/2026
Violation issued (ECB, closed)
Construction
08/03/2026
Violation issued (ECB, closed)
Construction
08/03/2026
Violation issued (ECB, open)
Construction
08/03/2026
Violation issued (ECB, open)
Construction
08/03/2026
Violation issued (ECB, open)
Construction
08/03/2026
Violation issued (ECB, open)
Construction
08/03/2026
Violation issued (ECB, open)
Construction
09/02/2025
Violation issued (ECB, open)
Construction
09/02/2025
Violation issued (ECB, open)
Construction
09/02/2025
Violation issued (ECB, open)
Construction
02/07/2025
Permit issued — Plumbing
M00772634-S1-PL
02/07/2025
Permit issued — General Construction
M00772634-I1-GC-CX
09/19/2024
Violation issued (ECB, closed)
Construction
09/19/2024
Violation issued (ECB, open)
Construction
09/19/2024
Violation issued (ECB, open)
Construction
09/11/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/31/2023
Permit issued — Plumbing
M00772634-S1-PL
08/29/2023
Signed off — Alteration
FILING FOR GENERAL CONSTRUCTION WORK & INSTALLATION OF A NEW HVAC SYSTEM AS PER PLANS FILED. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00749562-I1
08/25/2023
Permit issued — General Construction
M00772634-I1-GC-CX
08/24/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/02/2023
Permit issued — General Construction
M00749562-I1-GC
03/22/2023
Special inspection requirement — Mechanical Systems
Ari Kamo
03/22/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ari Kamo
03/22/2023
Special inspection requirement — Post-installed Anchors
Ari Kamo
03/22/2023
Special inspection requirement — Final
Ari Kamo
03/22/2023
Special inspection requirement — HVAC-R and service water heating system controls
Ari Kamo
03/22/2023
Special inspection requirement — Lighting controls
Ari Kamo
03/22/2023
Special inspection requirement — Interior lighting power
Ari Kamo
03/22/2023
Special inspection requirement — HVAC-R and service water heating equipment
Ari Kamo
03/22/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Ari Kamo
03/22/2023
Special inspection requirement — Maintenance information
Ari Kamo
03/16/2023
Filed — Alteration
FILING FOR GENERAL CONSTRUCTION WORK & INSTALLATION OF A NEW HVAC SYSTEM AS PER PLANS FILED. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00749562-P2
03/15/2023
Permit issued — General Construction
M00749562-I1-GC
03/09/2023
Permit issued — General Construction
M00749562-I1-MS
03/07/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ari Kamo
03/07/2023
Special inspection requirement — Mechanical Systems
Ari Kamo
03/07/2023
Special inspection requirement — Post-installed Anchors
Ari Kamo
03/07/2023
Special inspection requirement — Final
Ari Kamo
03/07/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Ari Kamo
03/07/2023
Special inspection requirement — HVAC-R and service water heating system controls
Ari Kamo
03/07/2023
Special inspection requirement — HVAC-R and service water heating equipment
Ari Kamo
03/07/2023
Special inspection requirement — Maintenance information
Ari Kamo
03/07/2023
Special inspection requirement — Lighting controls
Ari Kamo
03/07/2023
Special inspection requirement — Interior lighting power
Ari Kamo
08/16/2022
Permit issued — General Construction
M00749562-I1-GC
08/16/2022
Permit issued — Mechanical Systems
M00749562-I1-MS
08/15/2022
Filed — Alteration
FILING FOR GENERAL CONSTRUCTION WORK & INSTALLATION OF A NEW HVAC SYSTEM AS PER PLANS FILED. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00749562-P1
08/15/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ari Kamo
08/15/2022
Special inspection requirement — Mechanical Systems
Ari Kamo
08/15/2022
Special inspection requirement — Post-installed Anchors
Ari Kamo
08/15/2022
Special inspection requirement — Final
Ari Kamo
08/15/2022
Special inspection requirement — Interior lighting power
Ari Kamo
08/15/2022
Special inspection requirement — HVAC-R and service water heating equipment
Ari Kamo
08/15/2022
Special inspection requirement — Lighting controls
Ari Kamo
08/15/2022
Special inspection requirement — Maintenance information
Ari Kamo
08/15/2022
Special inspection requirement — HVAC-R and service water heating system controls
Ari Kamo
Latest 60 of 109 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedL.spina Plumbing & Heating02/07/2025
DOB NOWGeneral ConstructionPermit IssuedDia General Contruction I02/07/2025
DOB NOWPlumbingPermit IssuedRaptor Mechanical08/31/2023
DOB NOWGeneral ConstructionPermit IssuedDia General Contruction I08/25/2023
DOB NOWGeneral ConstructionSigned-offTruline Construction Service05/02/2023
DOB NOWGeneral ConstructionSigned-offTruline Construction Service03/15/2023
DOB NOWGeneral ConstructionSigned-offTruline Construction Service03/09/2023
DOB NOWGeneral ConstructionSigned-offTruline Construction Service08/16/2022
DOB NOWMechanical SystemsSigned-offTruline Construction Service08/16/2022
BISMHISSUEDKW Tech01/23/2025
BISOTISSUEDSkyline Industries03/13/2024
BISMHISSUEDKW Tech01/24/2024
BISOTISSUEDKG Construction Services01/04/2024
BISOTISSUEDSkyline Industries04/07/2023
BISOTISSUEDKG Construction Services02/23/2023
BISOTISSUEDKG Construction Services02/23/2023
BISOTISSUEDKG Construction Services02/23/2023
BISMHISSUEDKW Tech02/01/2023
BISPLISSUEDForsythe P&H10/07/2022
BISMHISSUEDR.A.M.S. Mechanical10/07/2022
BISOTISSUEDSkyline Industries04/06/2022
BISOTISSUEDKG Construction Services02/23/2022
BISOTISSUEDKG Construction Services02/23/2022
BISOTISSUEDKG Construction Services02/23/2022
BISMHISSUEDKW Tech02/03/2022
BISEQISSUEDKG Construction Services12/20/2021
BISMHISSUEDR.A.M.S. Mechanical10/05/2021
BISOTISSUEDKG Construction Services02/26/2021
BISOTISSUEDSkyline Industries02/24/2021
BISOTISSUEDKG Construction Services02/23/2021
BISOTISSUEDKG Construction Services02/23/2021
BISPLISSUEDForsythe P&H02/03/2021
BISEQISSUEDRoma Scaffolding01/11/2021
BISOTISSUEDKG Construction Services12/11/2020
BISEQISSUEDKG Construction Services12/02/2020
BISEQISSUEDRoma Scaffolding12/02/2020
BISEQISSUEDKG Construction Services12/02/2020
BISMHISSUEDR.A.M.S. Mechanical03/24/2020
BISOTISSUEDKG Construction Services02/24/2020
BISOTISSUEDKG Construction Services02/24/2020
+ 19 more permits on file
12 projects · most recent 06/19/2026
General Wiring Lighting
FiledStatusContractorScope
06/19/2026Permit IssuedMetropolitan Electric of NY IGeneral Wiring
10/16/2025CompleteVial Electric & CompanyLighting
08/16/2024Permit IssuedC.falco Eletl ContGeneral Wiring
01/24/2024CompleteAvalon ElectricGeneral Wiring
11/22/2023CompleteAnco Electl ContctngGeneral Wiring
10/25/2023Permit IssuedGemini Electric CoGeneral Wiring
09/11/2023CompleteAnco Electl Contctng—
03/27/2023CompleteMechanical Electr'l—
12/02/2022CompleteGemini Electric CoGeneral Wiring
10/03/2022Permit IssuedGemini Electric CoGeneral Wiring
12/03/2019CompleteStanco System Electrical Cont—
12/02/2019CompleteMechanical Electr'l—
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
09/11/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/24/2023Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
03/22/2023Mechanical SystemsAri Kamospecial
03/22/2023Fire-Resistant Penetrations and JointsAri Kamospecial
03/22/2023Post-installed AnchorsAri Kamospecial
03/22/2023FinalAri Kamoprogress
03/22/2023HVAC-R and service water heating system controlsAri Kamoenergy_progress
03/22/2023Lighting controlsAri Kamoenergy_progress
03/22/2023Interior lighting powerAri Kamoenergy_progress
03/22/2023HVAC-R and service water heating equipmentAri Kamoenergy_progress
03/22/2023HVAC-R and service water piping design and insulationAri Kamoenergy_progress
03/22/2023Maintenance informationAri Kamoenergy_progress
03/07/2023Fire-Resistant Penetrations and JointsAri Kamospecial
03/07/2023Mechanical SystemsAri Kamospecial
03/07/2023Post-installed AnchorsAri Kamospecial
03/07/2023FinalAri Kamoprogress
03/07/2023HVAC-R and service water piping design and insulationAri Kamoenergy_progress
03/07/2023HVAC-R and service water heating system controlsAri Kamoenergy_progress
03/07/2023HVAC-R and service water heating equipmentAri Kamoenergy_progress
03/07/2023Maintenance informationAri Kamoenergy_progress
03/07/2023Lighting controlsAri Kamoenergy_progress
03/07/2023Interior lighting powerAri Kamoenergy_progress
08/15/2022Fire-Resistant Penetrations and JointsAri Kamospecial
08/15/2022Mechanical SystemsAri Kamospecial
08/15/2022Post-installed AnchorsAri Kamospecial
08/15/2022FinalAri Kamoprogress
08/15/2022Interior lighting powerAri Kamoenergy_progress
Latest 25 of 34.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Democracy Prep Harlem Charter High SchoolEducationFloors 3, 4, Roof
Project M00772634 Alteration · Permit Entire · 07/13/2022
Project M00749562 Alteration · LOC Issued · 06/07/2022
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 39 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
09/02/2026M00749562-P1Request digital key ↗
09/02/2026M00749562-P2Request digital key ↗
09/02/2026M00772634-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications18
▸DOB NOWProgress Inspector Seal & Signature8
08/25/2026M00749562-P1Open ↗
08/25/2026M00749562-P1Open ↗
08/25/2026M00749562-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
08/25/2026M00749562-P1Open ↗
08/25/2026M00749562-I1Open ↗
08/24/2026M00749562-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
09/02/2026M00749562-P1Open ↗
09/02/2026M00749562-I1Open ↗
09/02/2026M00749562-P2Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
09/02/2026M00772634-S1Open ↗
08/14/2026M00749562-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/14/2026M00749562-I1Open ↗
▸Approvals, Objections & Sign-offs11
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter5
09/02/2026M00749562-P1Open ↗
09/02/2026M00749562-P2Open ↗
09/02/2026M00772634-S1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)2
08/13/2026M00772634-S1Open ↗
08/13/2026M00772634-I1Open ↗
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)2
08/13/2026M00772634-I1Open ↗
08/13/2026M00772634-S1Open ↗
▸DOB NOWDEP Variance (V5) letter2
09/02/2026M00772634-I1Open ↗
09/02/2026M00772634-S1Open ↗
▸Other Documents2
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal2
08/13/2026M00772634-I1Open ↗
08/13/2026M00772634-S1Open ↗