| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/08/2016 | $455K | — | PROFESSIONAL DEVELOPERS, LLC → Private party | $267/sf building |
| 10/26/2015 | $185K | — | ALL NATIONS REALTY, INC. → PROFESSIONAL DEVELOPERS, LLC | $108/sf building |
| 07/23/2015 | $185K | — | Private party → ALL NATIONS REALTY, INC. | $108/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| KENNY LEE ARCHITECT | 5 | 06/30/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| KORMAN DESIGN & BUILD | 6 | 03/21/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2026 | — | — | Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2026 | — | — | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2026 | — | — | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2026 | — | — | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/22/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 06/26/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 05/04/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 03/27/2026 | Metering | — | energy_progress |
| 03/27/2026 | Protection of exposed foundation insulation | — | energy_progress |
| 03/27/2026 | Maintenance information | — | energy_progress |
| 03/27/2026 | Mechanical Systems | — | special |
| 03/27/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 03/27/2026 | Final | — | progress |
| 03/27/2026 | Energy Code Compliance Inspections | — | progress |
| 03/27/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 03/27/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 03/27/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 12/29/2025 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 11/18/2025 | Electric vehicle service equipment requirements | — | energy_progress |
| 11/18/2025 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 11/18/2025 | Permanent certificate | — | energy_progress |
| 11/18/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 11/18/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 11/18/2025 | Insulation placement and R values | — | energy_progress |
| 11/18/2025 | Fenestration air leakage | — | energy_progress |
| 11/18/2025 | Fenestration areas | — | energy_progress |
| 11/18/2025 | Concrete - Cast-In-Place | — | special |
| 11/18/2025 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | — | special |
| 11/18/2025 | Energy Code Compliance Inspections | — | progress |