| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/26/2022 | $1.6M | — | Private party → Private party | $625/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| JIAN ENGINEERING PLLC | 4 | 05/30/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| JRK CREATIVE | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GENESIS NYC CONSTRUCTION | General Contractor | 1 | 07/08/2026 |
| CROSSFIELD PLBG.&HTG | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JIAN ENGINEERING PLLC | 7397 | 4 | 05/30/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | CROSSFIELD PLBG.&HTG | 11/29/2022 |
| DOB NOW | General Construction | Signed-off | GENESIS NYC CONSTRUCTION | 11/22/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/11/2023 | Complete | J Y ELECTRIC INC | 3 meters, 3 new_meters |
| 12/01/2022 | Complete | J Y ELECTRIC INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/25/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/27/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 03/02/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/02/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/28/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/31/2023 | Lighting in dwelling units | JIAN DENG | energy_progress |
| 05/31/2023 | Energy Code Compliance Inspections | JIAN DENG | progress |
| 05/31/2023 | Fire-Resistant Penetrations and Joints | JIAN DENG | special |
| 05/31/2023 | Concrete - Cast-In-Place | JIAN DENG | special |
| 05/27/2023 | HVAC-R and service water heating system controls | JIAN DENG | energy_progress |
| 05/27/2023 | Fire-Resistant Penetrations and Joints | JIAN DENG | special |
| 05/27/2023 | Energy Code Compliance Inspections | JIAN DENG | progress |
| 05/27/2023 | HVAC-R and service water piping design and insulation | JIAN DENG | energy_progress |
| 05/27/2023 | HVAC-R and service water heating equipment | JIAN DENG | energy_progress |
| 03/02/2023 | HVAC-R and service water heating system controls | JIAN DENG | energy_progress |
| 03/02/2023 | HVAC-R and service water heating equipment | JIAN DENG | energy_progress |
| 03/02/2023 | HVAC-R and service water piping design and insulation | JIAN DENG | energy_progress |
| 03/02/2023 | Energy Code Compliance Inspections | JIAN DENG | progress |
| 03/02/2023 | Fire-Resistant Penetrations and Joints | JIAN DENG | special |