← Back
BuildNYC
Elevator apt, fireproof with stores
214-33 41ST AVENUE
QUEENS · Bayside · BIN 4623899
💬 Discuss this project
2022Year Built
4Stories
D6Building Class
R6BZoning
28,917 sfGross Floor Area
17Units
Rent Stabilized1 Active Violation ▸FDNY Report ↗
Elevator apt, fireproof with stores · Owner of record: Amj Property Holdings · 8,000 sf lot · 3.61 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofAmj Property Holrings57p · 3 filings · 20 docs
BulkheadLand and zoning attorney3p · 2 filings · 20 docs
Floor 4Amj Property Holrings60p · 4 filings · 20 docs
Floor 3Amj Property Holrings61p · 4 filings · 20 docs
Floor 2Amj Property Holrings103p · 4 filings · 20 docs
Floor 1Nu Mar Medical, Spear Physical Therapy155p · 13 filings · 20 docs
CellarNu Mar Medical117p · 7 filings · 20 docs
Site & exteriorAmj Property Holrings27p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Amj Property Holdings503/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Caliendo Architects203/21/2026
Empire City Consultants203/21/2026
Milrose Consultants403/21/2026
Rigid Structural Design303/21/2026
Gerald J. Caliendo R.A2403/21/2026
Building Brothers203/21/2026
Patuxent Engineering203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Adc Builders & DevelopersGeneral Contractor1607/08/2026
Skyline Scaffolding GroupScaffold1203/21/2026
Adc Builders & DevelopersScaffold1007/08/2026
LW Interior RemodelingGeneral Contractor407/08/2026
MJ General MechanicalPlumbing307/08/2026
Unlimited PLG SolutionsFire Protection207/08/2026
K.N.C. ElectricElectrical203/22/2026
Paul SignsSign hanger107/08/2026
Dno Equipment and DevelopmentGeneral Contractor107/08/2026
Orbit SprinklerFire Protection107/08/2026
Top Plumbing and HeatingPlumbing107/08/2026
Advanced Scaffold ServiceScaffold104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA Building & Inspection15192107/16/2026
World Design Architecture9323110/16/2025
Catalpa Special Inspectio2004202/26/2025
MEP Inspections1102102/26/2025
Spivak Architects6957402/26/2025
Building Lifecycle
All (219)Filed (34)Permit Issued (30)Signed Off (17)Violation (14)Inspection (14)Objection (80)Special Inspection (30)
10/08/2026
Signed off — Alteration
INTERIOR ALTERATION TO EXISTING RETAIL SPACE ON EXISTING MIXED USE BUILDING. TO ALTER INTERIOR LAYOUT AS PER PLANS FILED HEREIN. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01295752-S1
09/17/2026
Special inspection requirement — Metering
Younes Abouyaala
09/17/2026
Special inspection requirement — Fenestration air leakage
Younes Abouyaala
09/17/2026
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
09/17/2026
Special inspection requirement — Lighting in dwelling units
Younes Abouyaala
09/17/2026
Special inspection requirement — Fenestration areas
Younes Abouyaala
09/17/2026
Special inspection requirement — Air barrier - visual inspection
Younes Abouyaala
09/17/2026
Special inspection requirement — Exterior lighting power
Younes Abouyaala
09/17/2026
Special inspection requirement — Lighting controls
Younes Abouyaala
09/17/2026
Special inspection requirement — Maintenance information
Younes Abouyaala
09/17/2026
Special inspection requirement — Protection of exposed foundation insulation
Younes Abouyaala
09/17/2026
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
09/17/2026
Special inspection requirement — Air barrier — testing
Younes Abouyaala
09/17/2026
Special inspection requirement — Insulation placement and R values
Younes Abouyaala
09/17/2026
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
Younes Abouyaala
09/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
09/17/2026
Special inspection requirement — Interior lighting power
Younes Abouyaala
08/11/2026
Objection resolved — Resolved
08/03/2026
Objection raised — Scope
07/16/2026
Filed — New Building
Mechanical work on conjunction with NB job #Q00489289-I1
Q00489289-P6
05/21/2026
Permit issued — General Construction
Q01295752-I1-GC
05/13/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/12/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/11/2026
Violation issued (HPD, open)
A
05/07/2026
Permit issued — Plumbing
Q01295752-S1-PL
02/17/2026
Objection resolved — Addressed
02/12/2026
Objection raised — Cost
01/23/2026
Filed — Alteration
INTERIOR ALTERATION TO EXISTING RETAIL SPACE ON EXISTING MIXED USE BUILDING. TO ALTER INTERIOR LAYOUT AS PER PLANS FILED HEREIN. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01295752-S1
12/03/2025
Objection resolved — Addressed
11/06/2025
Signed off — Alteration
Q01294880-I1
11/03/2025
Objection resolved — Addressed
11/03/2025
Objection resolved — Addressed
10/29/2025
Objection raised — Cost
10/29/2025
Objection raised — Other
10/29/2025
Objection raised — Scope
10/28/2025
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
Younes Abouyaala
10/28/2025
Special inspection requirement — Air barrier — testing
Younes Abouyaala
10/28/2025
Special inspection requirement — Metering
Younes Abouyaala
10/28/2025
Special inspection requirement — Protection of exposed foundation insulation
Younes Abouyaala
10/28/2025
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
Younes Abouyaala
10/28/2025
Special inspection requirement — Fenestration air leakage
Younes Abouyaala
10/28/2025
Special inspection requirement — Exterior lighting power
Younes Abouyaala
10/28/2025
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
10/28/2025
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
10/28/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Younes Abouyaala
10/28/2025
Special inspection requirement — Sprayed fire-resistant materials
Younes Abouyaala
10/28/2025
Special inspection requirement — Fenestration areas
Younes Abouyaala
10/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
10/28/2025
Special inspection requirement — Insulation placement and R values
Younes Abouyaala
10/22/2025
Permit issued — Structural
Q01294880-I1-ST
10/16/2025
Filed — Alteration
Q01294880-I1
10/07/2025
Permit issued — Protection and Mechanical Methods
Q01296764-I1-PMM
10/04/2025
Filed — Alteration
Q01296764-I1
10/01/2025
Filed — Alteration
INTERIOR ALTERATION TO EXISTING RETAIL SPACE ON EXISTING MIXED USE BUILDING. TO ALTER INTERIOR LAYOUT AS PER PLANS FILED HEREIN. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01295752-I1
08/19/2025
Signed off — Alteration
Q01204488-I1
07/15/2025
Signed off — Alteration
Modifications to existing Mechanical systems as per plans filed herewith. No change to use , egress or occupancy.
Q01144078-I1
07/08/2025
Signed off — Alteration
Q01144119-I1
07/08/2025
Signed off — Alteration
Plumbing Modifications as per plans filed herewith. No change to use, egress or occupancy.
Q01144108-I1
06/16/2025
Violation issued (HPD, closed)
A
05/30/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
Latest 60 of 219 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offAdc Builders & Developers05/21/2026
DOB NOWPlumbingSigned-offMJ General Mechanical05/07/2026
DOB NOWStructuralSigned-offAdc Builders & Developers10/22/2025
DOB NOWProtection and Mechanical MethodsPermit IssuedAdvanced Scaffold Service10/07/2025
DOB NOWSignSigned-offPaul Signs05/16/2025
DOB NOWSprinklersSigned-offOrbit Sprinkler04/09/2025
DOB NOWMechanical SystemsSigned-offLW Interior Remodeling03/19/2025
DOB NOWPlumbingSigned-offTop Plumbing and Heating03/11/2025
DOB NOWGeneral ConstructionSigned-offLW Interior Remodeling03/06/2025
DOB NOWCurb CutSigned-offDno Equipment and Development08/30/2024
DOB NOWMechanical SystemsSigned-offAdc Builders & Developers06/14/2024
DOB NOWGeneral ConstructionPermit IssuedAdc Builders & Developers04/16/2024
DOB NOWConstruction FenceSigned-offAdc Builders & Developers04/09/2024
DOB NOWSprinklersSigned-offUnlimited PLG Solutions04/02/2024
DOB NOWPlumbingSigned-offMJ General Mechanical10/18/2023
DOB NOWSidewalk ShedSigned-offSkyline Scaffolding Group05/12/2023
DOB NOWProtection and Mechanical MethodsSigned-offSkyline Scaffolding Group05/12/2023
DOB NOWProtection and Mechanical MethodsSigned-offSkyline Scaffolding Group03/21/2023
DOB NOWSprinklersSigned-offUnlimited PLG Solutions03/15/2023
DOB NOWStructuralSigned-offAdc Builders & Developers03/09/2023
DOB NOWConstruction FenceSigned-offAdc Builders & Developers03/08/2023
DOB NOWGeneral ConstructionPermit IssuedAdc Builders & Developers03/06/2023
DOB NOWSidewalk ShedSigned-offSkyline Scaffolding Group12/30/2022
DOB NOWGeneral ConstructionPermit IssuedAdc Builders & Developers11/03/2022
DOB NOWPlumbingSigned-offMJ General Mechanical10/14/2022
DOB NOWConstruction FenceSigned-offAdc Builders & Developers09/27/2022
DOB NOWStructuralSigned-offAdc Builders & Developers07/11/2022
DOB NOWEarth WorkSigned-offAdc Builders & Developers12/17/2021
DOB NOWSupport of ExcavationSigned-offAdc Builders & Developers12/16/2021
DOB NOWConstruction FenceSigned-offAdc Builders & Developers10/01/2021
1 project · most recent 07/16/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
07/16/2026Signed-offAdc Builders & DevelopersHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric M#PKFY-P12NLMU-E 297 CFM · Vrf Indoor ×19
M#MXZ-SM36NAMHZ-U1 36,000 BTU · Condensing Unit ×15
M#PKFY-P18NLMU-E 438 CFM · Vrf Indoor ×15
M#PKFY-P08NFMU-E 237 CFM · Vrf Indoor ×3
M#PEFY-P72NMHSU-E 2,540 CFM · Vrf Indoor ×2
M#PUHY-EP72TNU-A 72,000 BTU · Vrf Outdoor ×2
M#MXZ-SM48NAMHZ-U1 48,000 BTU · Vrf Outdoor ×1
M#PKA-A12LA 457 CFM · Fan Coil Indoor ×1
M#PUY-A12NKA7 12,000 BTU · Condensing Unit ×1
Ventilation
Fantech ERV-10-20H-VG 750 CFM · Erv ×1
LGH-F600RVX-E 600 CFM · Erv ×1
1 project · most recent 01/23/2026
Water/Sanitary
FiledStatusContractorScope
01/23/2026Signed-offCenta Plumbing & HeatingWater/Sanitary
7 projects · most recent 05/23/2025
General Wiring
FiledStatusContractorScope
05/23/2025CompleteLimitless Electric Resources—
04/01/2025CompleteP & Z ElectricGeneral Wiring
12/16/2024CompleteK.N.C. Electric19 meters, 1 new_meters
10/21/2024CompleteK.N.C. ElectricGeneral Wiring
09/05/2024CompleteK.N.C. ElectricGeneral Wiring
11/04/2022CompleteTuxedo Electrical Contracting—
08/22/2022CompleteTop Shelf Electric—
▾Field Inspections (DOB CAP) — 14
DateTypeResultReport
05/13/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/12/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/30/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/27/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/01/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/02/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/18/2024Pass-Final Curb Cut Non-Directive 14PassView ↗
09/09/2024Pass-Final CND-Occupancy InspectionPassView ↗
08/06/2024Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve TestCertifiedView ↗
08/01/2024Certified Sprinkler (SP) - Booster Pump TestCertifiedView ↗
03/05/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/04/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/26/2023Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
10/19/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
09/17/2026Air barrier — testing Younes Abouyaalaenergy_progress
09/17/2026Protection of exposed foundation insulationYounes Abouyaalaenergy_progress
09/17/2026Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
09/17/2026Insulation placement and R valuesYounes Abouyaalaenergy_progress
09/17/2026Exterior lighting powerYounes Abouyaalaenergy_progress
09/17/2026Fenestration air leakageYounes Abouyaalaenergy_progress
09/17/2026Air barrier - visual inspectionYounes Abouyaalaenergy_progress
09/17/2026Interior lighting powerYounes Abouyaalaenergy_progress
09/17/2026Lighting controlsYounes Abouyaalaenergy_progress
09/17/2026Energy Code Compliance InspectionsYounes Abouyaalaprogress
09/17/2026Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
09/17/2026Fenestration areasYounes Abouyaalaenergy_progress
09/17/2026MeteringYounes Abouyaalaenergy_progress
09/17/2026Wall Panels, Curtain Walls, and VeneersYounes Abouyaalaspecial
09/17/2026Lighting in dwelling unitsYounes Abouyaalaenergy_progress
09/17/2026Maintenance informationYounes Abouyaalaenergy_progress
10/28/2025Lighting in dwelling unitsYounes Abouyaalaenergy_progress
10/28/2025Interior lighting powerYounes Abouyaalaenergy_progress
10/28/2025Maintenance informationYounes Abouyaalaenergy_progress
10/28/2025Air barrier - visual inspectionYounes Abouyaalaenergy_progress
10/28/2025Protection of exposed foundation insulationYounes Abouyaalaenergy_progress
10/28/2025Fenestration and door U-factor and product ratingsYounes Abouyaalaenergy_progress
10/28/2025Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
10/28/2025Energy Code Compliance InspectionsYounes Abouyaalaprogress
10/28/2025Wall Panels, Curtain Walls, and VeneersYounes Abouyaalaspecial
Latest 25 of 150.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Nu Mar MedicalMedical / HealthcareCellar, Floor 1
Project Q01294880 Alteration · LOC Issued · 10/16/2025
Project Q01296764 Alteration · Permit Entire · 10/04/2025
Project Q01295752 Alteration · Permit Entire · 10/01/2025
Spear Physical TherapyMedical / HealthcareFloor 1
Project Q01144078 Alteration · LOC Issued · 02/26/2025
Project Q01144108 Alteration · LOC Issued · 02/26/2025
Project Q01144119 Alteration · LOC Issued · 02/26/2025
Project Q01144048 Alteration · LOC Issued · 02/24/2025
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 214 on file (BIS + DOB NOW)
▸Plans & Drawings34
▸DOB NOWPlans/Sketch34
08/27/2026Q00510212-I1Request digital key ↗
08/27/2026Q00510239-I1Request digital key ↗
08/27/2026Q00512889-P1Request digital key ↗
Showing 3 of 34 on file for this type
▸Applications & Permits3
▸BISBPP-5 - Authorization to the Department of Transportation2
03/14/2024440675930Open ↗
06/25/2021440675930Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
06/25/2021440675930Open ↗
▸Zoning, Tax Lot & Property Records32
▸DOB NOWRestrictive Declaration/Easement 17
08/23/2026Q00489289-P5Open ↗
08/23/2026Q00489289-I1Open ↗
08/23/2026Q00489289-P3Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWZoning Exhibit form (1-5)6
08/23/2026Q00489289-P5Open ↗
08/23/2026Q00489289-I1Open ↗
08/23/2026Q00489289-P3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWRestrictive Declaration/Easement 36
08/23/2026Q00489289-P5Open ↗
08/23/2026Q00489289-I1Open ↗
08/23/2026Q00489289-P3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWRestrictive Declaration/Easement 26
08/23/2026Q00489289-P5Open ↗
08/23/2026Q00489289-I1Open ↗
08/23/2026Q00489289-P3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWZD1: DOB Zoning Diagram6
08/23/2026Q00489289-P3Open ↗
08/23/2026Q00489289-P5Open ↗
08/23/2026Q00489289-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00489289-I1Open ↗
▸Seals & Professional Certifications93
▸DOB NOWDPL-1: Design Professional Seal & Signature34
08/27/2026Q00510345-I1Open ↗
08/27/2026Q00510212-I1Open ↗
08/27/2026Q00510239-I1Open ↗
Showing 3 of 34 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature31
10/04/2026Q00489289-S2Open ↗
09/25/2026Q01144078-I1Open ↗
09/25/2026Q01144078-I1Open ↗
Showing 3 of 31 on file for this type
▸DOB NOWProgress Inspector Seal & Signature26
10/04/2026Q00489289-S2Open ↗
10/04/2026Q00489289-S2Open ↗
10/04/2026Q00489289-S2Open ↗
Showing 3 of 26 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
06/25/2021440675930Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/25/2021440675930Open ↗
▸Trade Schedules & Equipment6
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)6
08/23/2026Q00489289-I1Open ↗
08/23/2026Q00489289-P3Open ↗
08/23/2026Q00489289-P5Open ↗
Showing 3 of 6 on file for this type
▸Safety & Tenant Protection12
▸DOB NOWStreet Tree Checklist6
08/23/2026Q00489289-I1Open ↗
08/23/2026Q00489289-P3Open ↗
08/23/2026Q00489289-P5Open ↗
Showing 3 of 6 on file for this type
▸BISSTREET TREE CHECKLIST3
05/26/2023440675930Open ↗
05/18/2023440675930Open ↗
06/25/2021440675930Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00489289-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026Q00489289-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026Q00489289-I1Open ↗
▸Energy Compliance4
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026Q00489289-I1Open ↗
08/13/2026Q00510345-I1Open ↗
▸DOB NOWPreliminary Commissioning Report Certification2
08/13/2026Q00489289-I1Open ↗
08/13/2026Q00489289-S2Open ↗
▸Inspections & Test Reports6
▸DOB NOWSOIL REPORT4
08/13/2026Q00512820-P2Open ↗
08/13/2026Q00512820-P5Open ↗
08/13/2026Q00512820-P3Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWTR4 Plot Diagram1
08/13/2026Q00512820-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q00512820-I1Open ↗
▸Cost, Insurance & Ownership2
▸DOB NOWCertificate of Insurance1
08/13/2026Q00489289-I1Open ↗
▸DOB NOWCertification by Insurance Broker or Agency1
08/13/2026Q00489289-I1Open ↗
▸Filing & Intake Forms4
▸BISADDITIONAL INFORMATION2
05/26/2023440675930Open ↗
05/18/2023440675930Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
06/25/2021440675930Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
06/25/2021440675930Open ↗
▸Other Documents18
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone6
08/23/2026Q00489289-P3Open ↗
08/23/2026Q00489289-I1Open ↗
08/23/2026Q00489289-P5Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSite Survey: Initial5
08/23/2026Q00489289-I1Open ↗
08/23/2026Q00489289-P3Open ↗
08/23/2026Q00489289-P5Open ↗
Showing 3 of 5 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION2
06/25/2021440675930Open ↗
06/25/2021440675930Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026Q00510329-I1Open ↗
08/13/2026Q00512820-I1Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
05/18/2023440675930Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q00489289-I1Open ↗
▸DOB NOWAdditional Insured Authorizations1
08/13/2026Q00489289-I1Open ↗