| Owner | Filings | Most Recent |
|---|---|---|
| Amj Property Holdings | 5 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Gerald Caliendo Architects | 10 | 07/16/2026 |
| HM Loke Consulting Engineering | 2 | 10/16/2025 |
| Leon Skvirsky PE | 1 | 05/15/2025 |
| Loring Consulting Engineers | 3 | 02/26/2025 |
| Spivak Architects | 1 | 02/24/2025 |
| Sharon Associates | 13 | 03/28/2024 |
| Newtec Engineering | 1 | 10/30/2023 |
| Urban Integrations | 3 | 07/06/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| Caliendo Architects | 2 | 03/21/2026 |
| Empire City Consultants | 2 | 03/21/2026 |
| Milrose Consultants | 4 | 03/21/2026 |
| Rigid Structural Design | 3 | 03/21/2026 |
| Gerald J. Caliendo R.A | 24 | 03/21/2026 |
| Building Brothers | 2 | 03/21/2026 |
| Patuxent Engineering | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Adc Builders & Developers | General Contractor | 16 | 07/08/2026 |
| Skyline Scaffolding Group | Scaffold | 12 | 03/21/2026 |
| Adc Builders & Developers | Scaffold | 10 | 07/08/2026 |
| LW Interior Remodeling | General Contractor | 4 | 07/08/2026 |
| MJ General Mechanical | Plumbing | 3 | 07/08/2026 |
| Unlimited PLG Solutions | Fire Protection | 2 | 07/08/2026 |
| K.N.C. Electric | Electrical | 2 | 03/22/2026 |
| Paul Signs | Sign hanger | 1 | 07/08/2026 |
| Dno Equipment and Development | General Contractor | 1 | 07/08/2026 |
| Orbit Sprinkler | Fire Protection | 1 | 07/08/2026 |
| Top Plumbing and Heating | Plumbing | 1 | 07/08/2026 |
| Advanced Scaffold Service | Scaffold | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA Building & Inspection | 1519 | 21 | 07/16/2026 |
| World Design Architecture | 9323 | 1 | 10/16/2025 |
| Catalpa Special Inspectio | 2004 | 2 | 02/26/2025 |
| MEP Inspections | 1102 | 1 | 02/26/2025 |
| Spivak Architects | 6957 | 4 | 02/26/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | Adc Builders & Developers | 05/21/2026 |
| DOB NOW | Plumbing | Signed-off | MJ General Mechanical | 05/07/2026 |
| DOB NOW | Structural | Signed-off | Adc Builders & Developers | 10/22/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Advanced Scaffold Service | 10/07/2025 |
| DOB NOW | Sign | Signed-off | Paul Signs | 05/16/2025 |
| DOB NOW | Sprinklers | Signed-off | Orbit Sprinkler | 04/09/2025 |
| DOB NOW | Mechanical Systems | Signed-off | LW Interior Remodeling | 03/19/2025 |
| DOB NOW | Plumbing | Signed-off | Top Plumbing and Heating | 03/11/2025 |
| DOB NOW | General Construction | Signed-off | LW Interior Remodeling | 03/06/2025 |
| DOB NOW | Curb Cut | Signed-off | Dno Equipment and Development | 08/30/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Adc Builders & Developers | 06/14/2024 |
| DOB NOW | General Construction | Permit Issued | Adc Builders & Developers | 04/16/2024 |
| DOB NOW | Construction Fence | Signed-off | Adc Builders & Developers | 04/09/2024 |
| DOB NOW | Sprinklers | Signed-off | Unlimited PLG Solutions | 04/02/2024 |
| DOB NOW | Plumbing | Signed-off | MJ General Mechanical | 10/18/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Skyline Scaffolding Group | 05/12/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Skyline Scaffolding Group | 05/12/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Skyline Scaffolding Group | 03/21/2023 |
| DOB NOW | Sprinklers | Signed-off | Unlimited PLG Solutions | 03/15/2023 |
| DOB NOW | Structural | Signed-off | Adc Builders & Developers | 03/09/2023 |
| DOB NOW | Construction Fence | Signed-off | Adc Builders & Developers | 03/08/2023 |
| DOB NOW | General Construction | Permit Issued | Adc Builders & Developers | 03/06/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Skyline Scaffolding Group | 12/30/2022 |
| DOB NOW | General Construction | Permit Issued | Adc Builders & Developers | 11/03/2022 |
| DOB NOW | Plumbing | Signed-off | MJ General Mechanical | 10/14/2022 |
| DOB NOW | Construction Fence | Signed-off | Adc Builders & Developers | 09/27/2022 |
| DOB NOW | Structural | Signed-off | Adc Builders & Developers | 07/11/2022 |
| DOB NOW | Earth Work | Signed-off | Adc Builders & Developers | 12/17/2021 |
| DOB NOW | Support of Excavation | Signed-off | Adc Builders & Developers | 12/16/2021 |
| DOB NOW | Construction Fence | Signed-off | Adc Builders & Developers | 10/01/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/16/2026 | Signed-off | Adc Builders & Developers | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric M#PKFY-P12NLMU-E 297 CFM · Vrf Indoor ×19 M#MXZ-SM36NAMHZ-U1 36,000 BTU · Condensing Unit ×15 M#PKFY-P18NLMU-E 438 CFM · Vrf Indoor ×15 M#PKFY-P08NFMU-E 237 CFM · Vrf Indoor ×3 M#PEFY-P72NMHSU-E 2,540 CFM · Vrf Indoor ×2 M#PUHY-EP72TNU-A 72,000 BTU · Vrf Outdoor ×2 M#MXZ-SM48NAMHZ-U1 48,000 BTU · Vrf Outdoor ×1 M#PKA-A12LA 457 CFM · Fan Coil Indoor ×1 M#PUY-A12NKA7 12,000 BTU · Condensing Unit ×1 Ventilation |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/23/2026 | Signed-off | Centa Plumbing & Heating | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/23/2025 | Complete | Limitless Electric Resources | — |
| 04/01/2025 | Complete | P & Z Electric | General Wiring |
| 12/16/2024 | Complete | K.N.C. Electric | 19 meters, 1 new_meters |
| 10/21/2024 | Complete | K.N.C. Electric | General Wiring |
| 09/05/2024 | Complete | K.N.C. Electric | General Wiring |
| 11/04/2022 | Complete | Tuxedo Electrical Contracting | — |
| 08/22/2022 | Complete | Top Shelf Electric | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/13/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/12/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/30/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/27/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/01/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/02/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/18/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 09/09/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/06/2024 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 08/01/2024 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 03/05/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/04/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/26/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/19/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/17/2026 | Air barrier — testing | Younes Abouyaala | energy_progress |
| 09/17/2026 | Protection of exposed foundation insulation | Younes Abouyaala | energy_progress |
| 09/17/2026 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 09/17/2026 | Insulation placement and R values | Younes Abouyaala | energy_progress |
| 09/17/2026 | Exterior lighting power | Younes Abouyaala | energy_progress |
| 09/17/2026 | Fenestration air leakage | Younes Abouyaala | energy_progress |
| 09/17/2026 | Air barrier - visual inspection | Younes Abouyaala | energy_progress |
| 09/17/2026 | Interior lighting power | Younes Abouyaala | energy_progress |
| 09/17/2026 | Lighting controls | Younes Abouyaala | energy_progress |
| 09/17/2026 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 09/17/2026 | Fire-Resistance Rated Construction | Younes Abouyaala | progress |
| 09/17/2026 | Fenestration areas | Younes Abouyaala | energy_progress |
| 09/17/2026 | Metering | Younes Abouyaala | energy_progress |
| 09/17/2026 | Wall Panels, Curtain Walls, and Veneers | Younes Abouyaala | special |
| 09/17/2026 | Lighting in dwelling units | Younes Abouyaala | energy_progress |
| 09/17/2026 | Maintenance information | Younes Abouyaala | energy_progress |
| 10/28/2025 | Lighting in dwelling units | Younes Abouyaala | energy_progress |
| 10/28/2025 | Interior lighting power | Younes Abouyaala | energy_progress |
| 10/28/2025 | Maintenance information | Younes Abouyaala | energy_progress |
| 10/28/2025 | Air barrier - visual inspection | Younes Abouyaala | energy_progress |
| 10/28/2025 | Protection of exposed foundation insulation | Younes Abouyaala | energy_progress |
| 10/28/2025 | Fenestration and door U-factor and product ratings | Younes Abouyaala | energy_progress |
| 10/28/2025 | Fire-Resistance Rated Construction | Younes Abouyaala | progress |
| 10/28/2025 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 10/28/2025 | Wall Panels, Curtain Walls, and Veneers | Younes Abouyaala | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Nu Mar Medical | Medical / Healthcare | Cellar, Floor 1 | Project Q01294880 Project Q01296764 Project Q01295752 |
| Spear Physical Therapy | Medical / Healthcare | Floor 1 | Project Q01144078 Project Q01144108 Project Q01144119 Project Q01144048 |