← Back
Two family frame
214-50 35 AVENUE
QUEENS · Douglaston-Little Neck · BIN 4617560
💬 Discuss this project
2005Year Built
2Stories
B2Building Class
R3XZoning
2,340 sfGross Floor Area
2Units
11 Open Violations 9 unresolved · 2 paperwork only ▸
Two family frame · 4,800 sf lot · 0.49 FAR built · Flood zone X
Locations of Work
StructuralPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
Roof1p · 1 filing · 4 docs
Floor 2Under Construction10p · 2 filings · 8 docs
Floor 1Under Construction10p · 2 filings · 8 docs
CellarUnder Construction13p · 3 filings · 16 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
T D ASSOCIATES103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JLS DESIGNS309/19/2025
ALL CITY ENGINEERING, P.C.108/12/2025
MEHDI GHAZI, P.E., P.C.104/03/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JLS DESIGNS303/21/2026
ALPHA HOME DESIGN LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GOLDEN TIME CONTRACTING IGeneral Contractor303/21/2026
RRP PLUMBING CORPFire Protection107/08/2026
RRP PLUMBING CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MEHDI GHAZI, P.E. P.C.7129308/12/2025
Building Lifecycle
All (29)Filed (5)Permit Issued (3)Violation (1)Inspection (2)Special Inspection (18)
03/16/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
03/16/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/17/2025
Permit issued — Sprinklers
Q00678244-I1-EW-SP
11/13/2025
Permit issued — Plumbing
Q01203856-I1-PL
10/08/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
MEHDI GHAZI
10/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MEHDI GHAZI
10/08/2025
Special inspection requirement — HVAC-R and service water heating equipment
MEHDI GHAZI
10/08/2025
Special inspection requirement — Maintenance information
MEHDI GHAZI
10/08/2025
Special inspection requirement — HVAC-R and service water heating system controls
MEHDI GHAZI
10/08/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
MEHDI GHAZI
09/19/2025
Filed — Alteration
Plumbing work for a new 2 family residence
Q01203856-P1
08/20/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/20/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
08/20/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
08/20/2025
Special inspection requirement — Maintenance information
08/20/2025
Special inspection requirement — HVAC-R and service water heating system controls
08/20/2025
Special inspection requirement — HVAC-R and service water heating equipment
08/12/2025
Filed — Alteration
Q00678244-I1
04/16/2025
Filed — Alteration
Plumbing work for a new 2 family residence
Q01203856-I1
10/24/2024
Filed — New Building
Q01116466-I1
05/03/2024
Permit issued — Foundation
Q01027642-I1-FO-EA
04/03/2024
Filed — Alteration
Q01027642-I1
03/29/2024
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Rajasekhar Sakhamuri
03/29/2024
Special inspection requirement — Energy Code Compliance Inspections
MEHDI GHAZI
03/28/2024
Special inspection requirement — Concrete - Cast-In-Place
MEHDI GHAZI
03/28/2024
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
MEHDI GHAZI
03/28/2024
Special inspection requirement — Final
MEHDI GHAZI
03/28/2024
Special inspection requirement — Footing and Foundation
MEHDI GHAZI
03/29/2007
Violation issued (ECB, closed)
Site Safety
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedRALPH W. LANDOLFI JR.11/17/2025
DOB NOWPlumbingPermit IssuedRRP PLUMBING CORP11/13/2025
DOB NOWFoundationPermit IssuedGOLDEN TIME CONTRACTING I05/03/2024
BIS—ISSUEDGOLDEN TIME CONTRACTING I12/06/2024
1 project · most recent 09/19/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
09/19/2025Permit IssuedRRP PLUMBING CORPGas, Storm, Water/Sanitary
2 projects · most recent 12/19/2025
General Wiring
FiledStatusContractorScope
12/19/2025CancelledKJK ELECTRIC INCGeneral Wiring
12/19/2025Permit IssuedKJK ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
03/16/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/16/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
10/08/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationMEHDI GHAZIspecial
10/08/2025Fire-Resistant Penetrations and JointsMEHDI GHAZIspecial
10/08/2025HVAC-R and service water heating equipmentMEHDI GHAZIenergy_progress
10/08/2025Maintenance informationMEHDI GHAZIenergy_progress
10/08/2025HVAC-R and service water heating system controlsMEHDI GHAZIenergy_progress
10/08/2025HVAC-R and service water piping design and insulationMEHDI GHAZIenergy_progress
08/20/2025Fire-Resistant Penetrations and Joints—special
08/20/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
08/20/2025HVAC-R and service water piping design and insulation—energy_progress
08/20/2025Maintenance information—energy_progress
08/20/2025HVAC-R and service water heating system controls—energy_progress
08/20/2025HVAC-R and service water heating equipment—energy_progress
03/29/2024Subsurface Investigations (Borings/Test Pits)Rajasekhar Sakhamurispecial
03/29/2024Energy Code Compliance InspectionsMEHDI GHAZIprogress
03/28/2024Concrete - Cast-In-PlaceMEHDI GHAZIspecial
03/28/2024Excavations - Sheeting, Shoring, and BracingMEHDI GHAZIspecial
03/28/2024FinalMEHDI GHAZIprogress
03/28/2024Footing and FoundationMEHDI GHAZIprogress
▾Documents — 67 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/23/2026Q01027642-I1Request digital key ↗
08/21/2026Q01116466-I1Request digital key ↗
08/19/2026Q00678244-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION4
05/30/2025421615112Open ↗
09/06/2024421615112Open ↗
02/25/2020421615112Open ↗
Showing 3 of 4 on file for this type
▸BISWORK PERMIT APPLICATION1
04/18/2025421615112Open ↗
▸Zoning, Tax Lot & Property Records7
▸BISZONING DIAGRAM2
11/07/2024421615112Open ↗
02/14/2022421615112Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
10/29/2021421615112Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
08/16/2021421615112Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
10/29/2021421615112Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
08/16/2021421615112Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026Q01116466-I1Open ↗
▸Seals & Professional Certifications16
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/21/2026Q01116466-I1Open ↗
08/19/2026Q00678244-I1Open ↗
08/18/2026Q01203856-P1Open ↗
Showing 3 of 5 on file for this type
▸BISProfessional and Owner Certification (POC3)3
08/07/2017421536519Open ↗
08/07/2017421536519Open ↗
08/07/2017421536519Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/26/2026Q01027642-I1Open ↗
08/26/2026Q01027642-I1Open ↗
08/25/2026Q01203856-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
04/18/2025421615112Open ↗
02/25/2020421615112Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/26/2026Q01027642-I1Open ↗
08/25/2026Q01203856-I1Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
08/07/2017421536519Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
02/22/2018421536519Open ↗
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
02/14/2022421615112Open ↗
▸Safety & Tenant Protection4
▸BISSTREET TREE CHECKLIST1
10/29/2021421615112Open ↗
▸BISEXCAVATION - SHEETING, SHORING, AND BRACING1
11/22/2024421615112Open ↗
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
04/24/2025421615112Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q01116466-I1Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
04/18/2025421615112Open ↗
02/25/2020421615112Open ↗
▸BIS* SOLAR READY REQUIREMENTS1
11/22/2024421615112Open ↗
▸Inspections & Test Reports9
▸BISTECHNICAL REPORT: RESPONSIBILITY3
10/29/2021421615112Open ↗
10/29/2021421615112Open ↗
10/29/2021421615112Open ↗
▸BISSOIL REPORT1
10/29/2021421615112Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
04/24/2025421615112Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
10/29/2021421615112Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
04/24/2025421615112Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q01027642-I1Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026Q01027642-I1Open ↗
▸Approvals, Objections & Sign-offs3
▸BISSCHEDULE A - OCCUPANCY / USE1
02/25/2020421615112Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
08/16/2021421615112Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
08/07/2017421536519Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
08/07/2017421536519Open ↗
▸Filing & Intake Forms7
▸BISADDITIONAL INFORMATION3
11/22/2024421615112Open ↗
10/23/2024421615112Open ↗
04/06/2023421615112Open ↗
▸BISBOROUGH INTAKE FORM2
02/22/2018421536519Open ↗
02/22/2018421536519Open ↗
▸BISEFILING COVER SHEET2
02/25/2020421615112Open ↗
08/07/2017421536519Open ↗
▸Other Documents5
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
11/08/2024421615112Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
04/24/2025421615112Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
02/14/2022421615112Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026Q01116466-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01027642-I1Open ↗