ECB08/07/2026Respondent has failed to provide a pe report as requested by the department in dobvio 24-02209 for the structural stability of the building., comply with commissioner's order; hire nyspe to submit report to exe$2K due
ECB02/05/2026Failure to obey a vacate order from the commissioner. Observed premises is illegally occupied with three (3) male occupants and vehicles while on an active full vacate order vac Q297/2024, which was issued on 0$10K due
ECB02/05/2026Unlawfully continued work while on notice of a stop work order. Premises were issued with a full stop work order on 06/16/2022. Observed 100% completed building with new facade, windows, plumbing works, and int$10K due
ECB02/03/2026Unlawful acts. Failure to comply with commissioner's order for summons 39064274N., comply with commissioner's order$2K due
ECB02/03/2026Failure to comply with commissioner's order to file a certificate of correction with department of building for summons 39119369L., file a certificate of correction$1K due
ECB02/03/2026Failure to comply with commissioner's order to file a certificate of correction with department of building for summons 39124257N., file a certificate of correction$1K due
ECB02/03/2026Unlawful acts. Failure to comply with commissioner's order for summons 39120854N. Observed 100% completed occupied building with no engineers report nor all necessary permits on file. Non-compliant with full st$6K due
ECB02/03/2026Failure to comply with commissioner's order to file a certificate of correction with department of building for summons 39084128N., file a certificate of correction$1K due
ECB09/08/2024Failure to comply with a commissioners order: occupying a premise contrary to a vacate order issued on 08/05/2024 #VACQ296/2024, comply with commissioner's order; comply with vacate order$2K due
ECB09/08/2024Failure to comply with a commissioners order: workers were doing electrical and plumbing work contrary to a stop work order at time of inspection, comply with stop work order; comply with order$12K due
DOB08/06/2024Structure stability report. Illegal steel frame structure creating 2ND story vertical and horizontal enlargement with no permits on top of an existing 1-story commercial building without an engineer's report for structural stability. Property has active swo and has unlawfully continued work and is occupied.
ECB08/05/2024Unlawful acts. Failure to comply with commissioner's order. Noted; an illegal steel frame structure creating 2ND story vertical and horizontal enlargement with no permits on top of an existing 1-story commercia$2K due
ECB07/17/2024Unlawfully continued work while on notice of a stop work order noted: violation #390642274 issued on 06/16/22 for fswo at time of inspection observed workers installing sheetrock, cutting metal frames and doing$5K due
ECB05/25/2023At time of inspection, observation was made inside of commercial ground floor building space, a auto body repair shop with a new mechanical car spray booth attached exhaust connections, and mechanical control d$1K due
ECB04/19/2023Unlawfully continued work while on notice of a stop work order. Premises was issued a full swo on 6/16/2022, at time of inspection building now fully enclosed with new facade and commercial windows. More than 5$5K due
ECB06/16/2022Work without permit. Noted; new steel frame erected creating a new 2ND story extension with roof onto existing 1 story commercial property. Approx. 50% completed. Stop all work immediately., obtain permit; stop$2K due