RoofProposed roof protectionUnder Construction10p · 2 filings · 7 docs
ArchitectureDMEquipmentMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods
Project M01310336Permit Issued · 10/16/2026
Mechanical means to assist with demolition, and chute will be used to lower debris from floor to floor.
On file for this project
5 documents
Project M01390125Permit Issued · 08/06/2026
INSTALLATION OF TEMPORARY ROOF PROTECTION OVER ADJACENT PROPERTIES AS PER PLANS. TEMPORARY PROTECTION SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
2 documents
BulkheadUnder Construction3p · 1 filing · 5 docs
ArchitectureDM
Project M01310336Permit Issued · 10/16/2026
Mechanical means to assist with demolition, and chute will be used to lower debris from floor to floor.
On file for this project
5 documents
Floor 4Interior non-structural demolition of 4 story buildingUnder Construction39p · 2 filings · 12 docs
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods
Project M01310336Permit Issued · 10/16/2026
Mechanical means to assist with demolition, and chute will be used to lower debris from floor to floor.
On file for this project
5 documents
Project M01392608Permit Issued · 06/08/2026
INTERIOR NON-STRUCTURAL DEMOLITION OF A 4 STORY WITH BASEMENT PER PLANS
On file for this project
7 documents
Floor 3Interior non-structural demolition of 4 story buildingUnder Construction39p · 2 filings · 12 docs
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods
Project M01310336Permit Issued · 10/16/2026
Mechanical means to assist with demolition, and chute will be used to lower debris from floor to floor.
On file for this project
5 documents
Project M01392608Permit Issued · 06/08/2026
INTERIOR NON-STRUCTURAL DEMOLITION OF A 4 STORY WITH BASEMENT PER PLANS
On file for this project
7 documents
Floor 2Interior non-structural demolition of 4 story buildingUnder Construction39p · 2 filings · 12 docs
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods
Project M01310336Permit Issued · 10/16/2026
Mechanical means to assist with demolition, and chute will be used to lower debris from floor to floor.
On file for this project
5 documents
Project M01392608Permit Issued · 06/08/2026
INTERIOR NON-STRUCTURAL DEMOLITION OF A 4 STORY WITH BASEMENT PER PLANS
On file for this project
7 documents
Floor 1Interior non-structural demolition of 4 story buildingUnder Construction39p · 2 filings · 12 docs
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods
Project M01310336Permit Issued · 10/16/2026
Mechanical means to assist with demolition, and chute will be used to lower debris from floor to floor.
On file for this project
5 documents
Project M01392608Permit Issued · 06/08/2026
INTERIOR NON-STRUCTURAL DEMOLITION OF A 4 STORY WITH BASEMENT PER PLANS
On file for this project
7 documents
MezzanineInterior non-structural demolition of 4 story buildingUnder Construction1p · 1 filing · 7 docs
DMFire Protection
Project M01392608Permit Issued · 06/08/2026
INTERIOR NON-STRUCTURAL DEMOLITION OF A 4 STORY WITH BASEMENT PER PLANS
On file for this project
7 documents
BasementInterior non-structural demolition of 4 story buildingUnder Construction3p · 2 filings · 12 docs
DMEquipmentFire Protection
Project M01310336Permit Issued · 10/16/2026
Mechanical means to assist with demolition, and chute will be used to lower debris from floor to floor.
On file for this project
5 documents
Project M01392608Permit Issued · 06/08/2026
INTERIOR NON-STRUCTURAL DEMOLITION OF A 4 STORY WITH BASEMENT PER PLANS
On file for this project
7 documents
Sub-BasementInterior non-structural demolition of 4 story buildingUnder Construction9p · 1 filing · 7 docs
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods
Project M01392608Permit Issued · 06/08/2026
INTERIOR NON-STRUCTURAL DEMOLITION OF A 4 STORY WITH BASEMENT PER PLANS
On file for this project
7 documents
Site & exteriorSidewalk shed and pipe scaffoldingUnder Construction35p · 2 filings · 7 docs
ArchitectureDMEquipmentGeneralMechanicalStructural
Issued Permit Scope
Construction Fence · Sidewalk Shed · Supported Scaffold
Project M01310336Permit Issued · 10/16/2026
Mechanical means to assist with demolition, and chute will be used to lower debris from floor to floor.
On file for this project
5 documents
Project M01389561Permit Issued · 08/06/2026
INSTALLATION OF PIPE SCAFFOLDING AND HEAVY DUTY SIDEWALK SHED AS PER PLANS. TEMPORARY EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
2 documents