| Owner | Filings | Most Recent |
|---|---|---|
| Ocean Drive Realty | 15 | 03/22/2026 |
| Gershon & Company | 4 | 03/21/2026 |
| 215 East 23rd St | 3 | 03/21/2026 |
| 215 E 23 St | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| New York & Company | 3 | 09/03/2026 |
| Always Fast Services | 1 | 04/27/2026 |
| George J. Xerakias, PE | 1 | 04/08/2026 |
| Lawless & Mangione | 1 | 07/18/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| New York & Company | 4 | 03/21/2026 |
| Boyd Consulting | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| WCK Electric | Electrical | 3 | 03/21/2026 |
| Alpha Scaffolding | Scaffold | 2 | 09/17/2026 |
| Bell Fuel Oil | Plumbing | 2 | 06/27/2026 |
| Laura Electrical Lighting | Electrical | 1 | 03/21/2026 |
| Ajp Contracting | General Contractor | 1 | 08/08/2026 |
| Warshaw Gramercy East | Electrical | 1 | 03/21/2026 |
| Prospect Electric Service | Electrical | 1 | 03/21/2026 |
| P.S. Marcato Elev. Co | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| New York Engineering Associates | 851 | 2 | 03/11/2026 |
| Metric Consulting and Ins | 1803 | 1 | 07/18/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | Alpha Scaffolding | 09/16/2026 |
| DOB NOW | General Construction | Permit Issued | Ajp Contracting | 08/07/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | Ajp Contracting | 07/27/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Alpha Scaffolding | 04/28/2026 |
| DOB NOW | Boiler Equipment | Signed-off | Approved Energy | 03/19/2026 |
| DOB NOW | Plumbing | Permit Issued | Approved Energy | 03/19/2026 |
| BIS | EQ | ISSUED | Intersystem S&S | 04/29/2016 |
| BIS | EQ | ISSUED | Vikrant Contracting & Builder | 10/21/2014 |
| BIS | EQ | ISSUED | Vikrant Contracting & Builder | 10/17/2014 |
| BIS | OT | ISSUED | FM Kelly Construction Group | 05/14/2013 |
| BIS | PL | ISSUED | Plumbing P & H | 08/13/2004 |
| BIS | — | ISSUED | RSF Csontruction | 08/05/2004 |
| BIS | SP | ISSUED | Armon Mechanical | 06/27/2003 |
| BIS | MH | ISSUED | William L. Rumsey Construction | 06/19/2003 |
| BIS | OT | ISSUED | William L. Rumsey Construction | 03/27/2003 |
| BIS | PL | ISSUED | Blau Mechnl | 07/06/2001 |
| BIS | EQ | ISSUED | J.E. Levine Builders | 06/26/2001 |
| BIS | — | ISSUED | J.E. Levine Builders | 06/26/2001 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting Co | 04/30/2001 |
| BIS | EQ | RE-ISSUED | Regional Scaffold & Hoisting | 04/19/2001 |
| BIS | SD | ISSUED | Aljer Plumbing & Heating | 02/01/2001 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting Co | 12/12/2000 |
| BIS | EQ | ISSUED | J.E. Levine Builders | 11/22/2000 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting Co | 11/03/2000 |
| BIS | EQ | ISSUED | J.E. Levine Builders | 11/01/2000 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting | 09/13/2000 |
| BIS | — | ISSUED | J.E. Levine Builders | 06/15/2000 |
| BIS | PL | ISSUED | Blau Mechnl | 06/06/2000 |
| BIS | — | RE-ISSUED | J.E. Levine Builders | 12/03/1999 |
| BIS | EQ | ISSUED | J.E. Levine Builders | 12/03/1999 |
| BIS | OT | ISSUED | Richard C. Mugler Co | 10/19/1999 |
| BIS | EQ | ISSUED | Big Apple Wrecking & Construction | 09/08/1999 |
| BIS | — | ISSUED | Big Apple Wrecking & Construction | 08/26/1999 |
| BIS | EQ | ISSUED | Big Apple Wrecking & Construction | 08/26/1999 |
| BIS | — | ISSUED | Big Apple Wrecking & Construction | 08/26/1999 |
| BIS | EQ | ISSUED | Big Apple Wrecking & Construction | 08/26/1999 |
| BIS | EQ | ISSUED | Big Apple Wrecking & Construction | 04/26/1999 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2026 | Signed-off | Bell Fuel Oil | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/23/2026 | Permit Issued | Richard Neu | — |
| 03/19/2026 | Permit Issued | Laura Electrical Lighting | Boiler Controls |
| 06/03/2024 | Complete | P.S. Marcato Elev. Co | — |
| 06/07/2021 | Complete | Prospect Electric Service | HVAC Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/27/2026 | Permit Issued | Alpha Scaffolding | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/08/2026 | Permit Issued | Ajp Contracting | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/02/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/03/2026 | Energy Code Compliance Inspections | LOUIS ARENA | progress |
| 09/03/2026 | Tenant Protection Plan Compliance | — | special |
| 04/08/2026 | Alternative Materials - OTCR Buildings Bulletin Number | George Xerakias | special |
| 01/27/2026 | Tenant Protection Plan Compliance | LOUIS ARENA | special |
| 01/27/2026 | Tenant Protection Plan Compliance | LOUIS ARENA | special |
| 01/23/2026 | HVAC-R and service water piping design and insulation | LOUIS ARENA | energy_progress |
| 01/23/2026 | Energy Code Compliance Inspections | LOUIS ARENA | progress |
| 01/23/2026 | Heating Systems | LOUIS ARENA | special |
| 01/23/2026 | HVAC-R and service water heating system controls | LOUIS ARENA | energy_progress |
| 01/23/2026 | HVAC-R and service water heating equipment | LOUIS ARENA | energy_progress |
| 01/23/2026 | Maintenance information | LOUIS ARENA | energy_progress |
| 05/08/2025 | Preliminary | — | progress |
| 05/08/2025 | Energy Code Compliance Inspections | William Struth | progress |
| 05/08/2025 | Masonry | SAMI HAJJAR P.E | special |
| 05/08/2025 | Tenant Protection Plan Compliance | SAMI HAJJAR P.E | special |
| 05/05/2025 | Final | William Struth | progress |