← Back
Two stories - detached, small or mid-size
2159 EAST 71 STREET
BROOKLYN · BIN 3237684
💬 Discuss this project
1960Year Built
1Stories
A1Building Class
R3-1Zoning
2,576 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 4,000 sf lot · 0.64 FAR built · Flood zone X500
Locations of Work
ArchitectureGeneral
Roof3p · 1 filing · 11 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/25/2021$250K—— → —$97/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
UNISOLAR205/27/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CENTURION SOLAR ENERGYGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CENTURION SOLAR ENERGY LL9475205/27/2025
Building Lifecycle
All (10)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (6)
06/13/2025
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
B01186929-I1
05/27/2025
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
B01186929-P1
05/22/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Andres Arias Londono
05/22/2025
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Andres Arias Londono
05/22/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Andres Arias Londono
05/22/2025
Special inspection requirement — Energy Code Compliance Inspections
Andres Arias Londono
05/22/2025
Special inspection requirement — Final
Andres Arias Londono
05/22/2025
Special inspection requirement — Air barrier - visual inspection
Andres Arias Londono
03/07/2025
Permit issued — Solar
B01186929-I1-SL
02/27/2025
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
B01186929-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offCENTURION SOLAR ENERGY03/07/2025
1 project · most recent 02/24/2025
FiledStatusContractorScope
02/24/2025CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
05/22/2025Fire-Resistant Penetrations and JointsAndres Arias Londonospecial
05/22/2025Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Andres Arias Londonospecial
05/22/2025Structural Stability – Alterations of existing buildingsAndres Arias Londonospecial
05/22/2025Energy Code Compliance InspectionsAndres Arias Londonoprogress
05/22/2025FinalAndres Arias Londonoprogress
05/22/2025Air barrier - visual inspectionAndres Arias Londonoenergy_progress
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/21/2026B01186929-I1Request digital key ↗
08/21/2026B01186929-P1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/21/2026B01186929-I1Open ↗
08/21/2026B01186929-P1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026B01186929-P1Open ↗
08/27/2026B01186929-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/27/2026B01186929-P1Open ↗
08/27/2026B01186929-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/21/2026B01186929-P1Open ↗
08/21/2026B01186929-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01186929-I1Open ↗