← Back
Three families
2166 HOMECREST AVENUE
BROOKLYN · Gravesend (East)-Homecrest · BIN 3256876
💬 Discuss this project
1910Year Built
2.75Stories
C0Building Class
R5Zoning
1,932 sfGross Floor Area
3Units
1 Open Violation ▸FDNY Report ↗
Three families · 3,000 sf lot · 0.64 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralPlumbingFire Protection
Permit Issued — active, not yet Signed-off
Roof2p · 1 filing · 4 docs
Floor 3Under Construction5p · 1 filing · 20 docs
Floor 2Under Construction48p · 2 filings · 20 docs
Floor 1Under Construction43p · 1 filing · 20 docs
CellarUnder Construction43p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RHY CONSTRUCTION103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/13/2025$1.9M—— → —$999/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GARFINKEL ARCHITECT, PLLC405/05/2026
EYAL LEVITT ARCHITECT PC101/30/2026
ADROIT ENGINEERING PLLC112/31/2025
DERMAN ENGINEERING PLLC211/04/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GARFINKEL ARCHITECT403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RHY CONSTRUCTION LLCGeneral Contractor607/08/2026
RRP PLUMBING CORPPlumbing106/27/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AZ PROFESSIONAL ENGINEERI766402/26/2026
Building Lifecycle
All (100)Filed (8)Permit Issued (5)Violation (19)Inspection (2)Objection (36)Special Inspection (30)
08/04/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
08/04/2026
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
06/23/2026
Permit issued — Plumbing
B01185649-S1-PL
05/14/2026
Special inspection requirement — Insulation placement and R values
VIJAY KUMAR
05/14/2026
Special inspection requirement — Electric vehicle service equipment requirements
VIJAY KUMAR
05/14/2026
Special inspection requirement — Air barrier - visual inspection
VIJAY KUMAR
05/14/2026
Special inspection requirement — Protection of exposed foundation insulation
VIJAY KUMAR
05/14/2026
Special inspection requirement — Fenestration areas
VIJAY KUMAR
05/14/2026
Special inspection requirement — Metering
VIJAY KUMAR
05/14/2026
Special inspection requirement — Interior lighting power
VIJAY KUMAR
05/14/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
VIJAY KUMAR
05/14/2026
Special inspection requirement — Maintenance information
VIJAY KUMAR
05/14/2026
Special inspection requirement — Permanent certificate
VIJAY KUMAR
05/14/2026
Special inspection requirement — Fenestration air leakage
VIJAY KUMAR
05/14/2026
Special inspection requirement — Preliminary
VIJAY KUMAR
05/14/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
VIJAY KUMAR
05/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
VIJAY KUMAR
05/14/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
VIJAY KUMAR
05/14/2026
Special inspection requirement — Energy Code Compliance Inspections
VIJAY KUMAR
05/14/2026
Special inspection requirement — Fire-Resistance Rated Construction
VIJAY KUMAR
05/05/2026
Filed — Alteration CO
Temporary construction fence in conjunction with B01185649-I1
B01185649-S1
04/23/2026
Violation issued (ECB, closed)
Unknown
04/23/2026
Violation issued (ECB, closed)
Unknown
04/23/2026
Violation issued (ECB, closed)
Unknown
04/23/2026
Violation issued (ECB, closed)
Unknown
04/23/2026
Special inspection requirement — HVAC-R and service water heating equipment
LEWIS GARFINKEL
04/23/2026
Special inspection requirement — Energy Code Compliance Inspections
LEWIS GARFINKEL
04/23/2026
Special inspection requirement — HVAC-R and service water heating system controls
LEWIS GARFINKEL
03/16/2026
Objection raised — Energy
03/13/2026
Objection raised — Other
03/13/2026
Objection resolved — Resolved
03/13/2026
Objection resolved — Addressed
03/12/2026
Objection raised — Admin
03/12/2026
Objection resolved — Addressed
03/12/2026
Objection raised — Zoning
03/11/2026
Objection raised — Zoning
03/11/2026
Objection resolved — Addressed
03/11/2026
Objection resolved — Addressed
03/06/2026
Objection raised — Zoning
03/05/2026
Objection resolved — Addressed
03/04/2026
Objection resolved — Addressed
03/04/2026
Objection resolved — Addressed
03/02/2026
Objection raised — Fire_Protection
03/02/2026
Objection raised — Zoning
03/02/2026
Objection raised — Fire_Protection
02/26/2026
Filed — Alteration CO
Temporary construction fence in conjunction with B01185649-I1
B01185649-P1
02/23/2026
Permit issued — Foundation
B01185649-S8-FO
02/18/2026
Special inspection requirement — Fenestration air leakage
VIJAY KUMAR
02/18/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
VIJAY KUMAR
02/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
VIJAY KUMAR
02/18/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
VIJAY KUMAR
02/18/2026
Special inspection requirement — Energy Code Compliance Inspections
VIJAY KUMAR
02/18/2026
Special inspection requirement — Fire-Resistance Rated Construction
VIJAY KUMAR
02/18/2026
Special inspection requirement — Preliminary
VIJAY KUMAR
02/18/2026
Special inspection requirement — Fenestration areas
VIJAY KUMAR
02/18/2026
Special inspection requirement — Air barrier - visual inspection
VIJAY KUMAR
02/18/2026
Special inspection requirement — Insulation placement and R values
VIJAY KUMAR
02/13/2026
Permit issued — Structural
B01185649-S7-ST
02/12/2026
Objection resolved — Addressed
02/11/2026
Objection raised — Admin
Latest 60 of 100 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedRRP PLUMBING CORP06/23/2026
DOB NOWFoundationPermit IssuedRHY CONSTRUCTION LLC02/23/2026
DOB NOWStructuralPermit IssuedRHY CONSTRUCTION LLC02/13/2026
DOB NOWGeneral ConstructionPermit IssuedRHY CONSTRUCTION LLC11/10/2025
DOB NOWConstruction FencePermit IssuedRHY CONSTRUCTION LLC10/31/2025
1 project · most recent 05/05/2026
Sprinkler System
FiledStatusContractorScope
05/05/2026——Sprinkler System
1 project · most recent 05/05/2026
FiledStatusContractorScope
05/05/2026Permit IssuedRRP PLUMBING CORP—
1 project · most recent 07/28/2026
General Wiring
FiledStatusContractorScope
07/28/2026Permit IssuedFABCO ELECTRICAL CONT.INCGeneral Wiring
1 project · most recent 05/05/2026
Steel Wood
FiledStatusContractorScope
05/05/2026Permit IssuedRRP PLUMBING CORPSteel, Wood
1 project · most recent 05/05/2026
Fence
FiledStatusContractorScope
05/05/2026Permit IssuedRRP PLUMBING CORPFence
1 project · most recent 05/05/2026
Earthwork
FiledStatusContractorScope
05/05/2026Permit IssuedRRP PLUMBING CORPEarthwork
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
08/04/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/04/2026Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 49
DateRequirementInspectorRole
05/14/2026Insulation placement and R valuesVIJAY KUMARenergy_progress
05/14/2026Electric vehicle service equipment requirementsVIJAY KUMARenergy_progress
05/14/2026Air barrier - visual inspectionVIJAY KUMARenergy_progress
05/14/2026Protection of exposed foundation insulationVIJAY KUMARenergy_progress
05/14/2026Fenestration areasVIJAY KUMARenergy_progress
05/14/2026MeteringVIJAY KUMARenergy_progress
05/14/2026Interior lighting powerVIJAY KUMARenergy_progress
05/14/2026Fenestration and door U-factor and product ratingsVIJAY KUMARenergy_progress
05/14/2026Maintenance informationVIJAY KUMARenergy_progress
05/14/2026Permanent certificateVIJAY KUMARenergy_progress
05/14/2026Fenestration air leakageVIJAY KUMARenergy_progress
05/14/2026PreliminaryVIJAY KUMARprogress
05/14/2026Exterior Insulation and Finish Systems (EIFS)VIJAY KUMARspecial
05/14/2026Fire-Resistant Penetrations and JointsVIJAY KUMARspecial
05/14/2026Structural Stability – Alterations of existing buildingsVIJAY KUMARspecial
05/14/2026Energy Code Compliance InspectionsVIJAY KUMARprogress
05/14/2026Fire-Resistance Rated ConstructionVIJAY KUMARprogress
04/23/2026HVAC-R and service water heating equipmentLEWIS GARFINKELenergy_progress
04/23/2026Energy Code Compliance InspectionsLEWIS GARFINKELprogress
04/23/2026HVAC-R and service water heating system controlsLEWIS GARFINKELenergy_progress
02/18/2026Fenestration air leakageVIJAY KUMARenergy_progress
02/18/2026Exterior Insulation and Finish Systems (EIFS)VIJAY KUMARspecial
02/18/2026Fire-Resistant Penetrations and JointsVIJAY KUMARspecial
02/18/2026Structural Stability – Alterations of existing buildingsVIJAY KUMARspecial
02/18/2026Energy Code Compliance InspectionsVIJAY KUMARprogress
Latest 25 of 49.
▾Documents — 54 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/17/2026B01185649-S8Request digital key ↗
08/17/2026B01185649-S7Request digital key ↗
08/17/2026B01185649-S3Request digital key ↗
Showing 3 of 7 on file for this type
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026B01185649-I1Open ↗
08/13/2026B01185649-P1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/13/2026B01185649-P1Open ↗
08/13/2026B01185649-I1Open ↗
▸Seals & Professional Certifications23
▸DOB NOWProgress Inspector Seal & Signature10
08/27/2026B01185649-S7Open ↗
08/26/2026B01185649-I1Open ↗
08/26/2026B01185649-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/17/2026B01185649-S7Open ↗
08/17/2026B01185649-S3Open ↗
08/17/2026B01185649-S1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
08/27/2026B01185649-S7Open ↗
08/26/2026B01185649-I1Open ↗
08/26/2026B01185649-I1Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
08/13/2026B01185649-I1Open ↗
08/13/2026B01185649-P1Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/17/2026B01185649-S7Open ↗
08/17/2026B01185649-S3Open ↗
08/17/2026B01185649-S1Open ↗
Showing 3 of 7 on file for this type
▸Other Documents11
▸DOB NOWPlot Diagram3
08/13/2026B01185649-S8Open ↗
08/13/2026B01185649-P1Open ↗
08/13/2026B01185649-I1Open ↗
▸DOB NOWProperty Ownership Certification3
08/17/2026B01185649-P1Open ↗
08/17/2026B01185649-I1Open ↗
08/13/2026B01332547-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026B01185649-P1Open ↗
08/13/2026B01185649-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026B01185649-P1Open ↗
08/13/2026B01185649-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026B01332547-I1Open ↗