1955Year Built
1.5Stories
A2Building Class
R3-1Zoning
1,020 sfGross Floor Area
1Units
One story - permanent living quarter · 6,000 sf lot · 0.17 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralPlumbing
Floor 216p · 1 filing · 20 docs
Floor 115p · 2 filings · 20 docs
Cellar16p · 2 filings · 20 docs
1 job · most recent 06/24/2025
Gas Water/Sanitary
FiledStatusContractorScope
06/24/2025Permit IssuedJOHN FITZGERALD PLBG &HTGGas, Water/Sanitary
1 job · most recent 08/10/2026
Steel
FiledStatusContractorScope
08/10/2026Permit IssuedDIG YOU OUT INCSteel
Building Lifecycle
All (55)Filed (7)Permit Issued (6)Objection (32)Special Inspection (10)
08/12/2026
Permit issued — Structural
B01237410-S6-ST
08/10/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
Footings and foundation work in conjunction with new 3 story enlargement
B01237410-S6
08/05/2026
Special inspection requirement — Structural Steel - Welding
SAVERIO TARANTINO
08/05/2026
Special inspection requirement — Post-installed Anchors
SAVERIO TARANTINO
08/05/2026
Special inspection requirement — Structural Cold-Formed Steel
SAVERIO TARANTINO
08/05/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
SAVERIO TARANTINO
08/05/2026
Special inspection requirement — Structural Steel - Details
SAVERIO TARANTINO
08/04/2026
Special inspection requirement — Final
RONNY BECKER
03/15/2026
Permit issued — General Construction
B01237410-I1-GC
03/12/2026
Permit issued — Foundation
B01237410-S5-FO
01/20/2026
Objection resolved — Addressed
12/22/2025
Objection resolved — Addressed
12/18/2025
Objection raised — Structural
12/09/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
Footings and foundation work in conjunction with new 3 story enlargement
B01237410-S5
10/06/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
08/28/2025
Objection resolved — Addressed
08/28/2025
Objection resolved — Addressed
08/15/2025
Objection resolved — Addressed
07/17/2025
Objection resolved — Addressed
07/17/2025
Objection resolved — Addressed
07/16/2025
Objection resolved — Addressed
07/16/2025
Objection resolved — Addressed
07/16/2025
Objection resolved — Addressed
07/02/2025
Objection raised — Zoning
07/02/2025
Objection raised — Admin
07/02/2025
Objection raised — Structural
07/02/2025
Objection raised — Zoning
07/02/2025
Objection raised — Zoning
07/02/2025
Objection raised — Zoning
07/02/2025
Objection raised — Zoning
07/02/2025
Objection raised — Scope
07/02/2025
Objection raised — Structural
07/02/2025
Objection raised — Zoning
07/02/2025
Objection raised — Zoning
07/02/2025
Objection raised — Cost
07/02/2025
Objection raised — Scope
07/02/2025
Objection raised — Zoning
07/02/2025
Objection raised — Fire_Protection
06/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
06/28/2025
Special inspection requirement — Final
RONNY BECKER
06/24/2025
Filed — Alteration
INTERIOR & EXTERIOR DEMOLITION WORK, INCLUDING BUT NOT LIMITED TO REMOVING INTERIOR AND EXTERIOR WALLS, CEILINGS, FINISHED FLOORING, TILE, EXISTING FIXTURES ETC.. AS PER PLANS SUBMITTED. EXISTING FOUNDATIONS TO REMAIN. NO CHANGE IN USE, EGRESS OR OCCUPAN
B01200305-P1
06/23/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
06/23/2025
Special inspection requirement — Final
RONNY BECKER
06/17/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
Footings and foundation work in conjunction with new 3 story enlargement
B01237410-I1
04/15/2025
Permit issued — Plumbing
B01200305-S1-PL
03/31/2025
Permit issued — General Construction
B01200305-I1-GC
03/26/2025
Filed — Alteration
INTERIOR & EXTERIOR DEMOLITION WORK, INCLUDING BUT NOT LIMITED TO REMOVING INTERIOR AND EXTERIOR WALLS, CEILINGS, FINISHED FLOORING, TILE, EXISTING FIXTURES ETC.. AS PER PLANS SUBMITTED. EXISTING FOUNDATIONS TO REMAIN. NO CHANGE IN USE, EGRESS OR OCCUPAN
B01200305-I1
03/26/2025
Filed — Alteration
INTERIOR & EXTERIOR DEMOLITION WORK, INCLUDING BUT NOT LIMITED TO REMOVING INTERIOR AND EXTERIOR WALLS, CEILINGS, FINISHED FLOORING, TILE, EXISTING FIXTURES ETC.. AS PER PLANS SUBMITTED. EXISTING FOUNDATIONS TO REMAIN. NO CHANGE IN USE, EGRESS OR OCCUPAN
B01200305-S1
09/27/2024
Permit issued — Construction Fence
B01115426-I1-FN
09/24/2024
Filed — Alteration
B01115426-I1
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/12/2024$858K—— → —$841/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
REAL ESTATE & ARCHITECTURAL SERVICE608/10/2026
TARLAN DESIGN BUILD, LLC106/17/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LANCIERS ASSOCIATES1003/21/2026
TARLAN DESIGN BUILD, LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HAMOUD CONSTRUCTION CORPGeneral Contractor603/21/2026
DIG YOU OUT INCGeneral Contractor308/26/2026
JOHN FITZGERALD PLBG &HTGPlumbing106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TARLAN DESIGN BUILD, LLC3187308/10/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedDIG YOU OUT INC08/12/2026
DOB NOWGeneral ConstructionPermit IssuedDIG YOU OUT INC03/15/2026
DOB NOWFoundationPermit IssuedDIG YOU OUT INC03/12/2026
DOB NOWPlumbingPermit IssuedJOHN FITZGERALD PLBG &HTG04/15/2025
DOB NOWGeneral ConstructionPermit IssuedHAMOUD CONSTRUCTION CORP03/31/2025
DOB NOWConstruction FencePermit IssuedHAMOUD CONSTRUCTION CORP09/27/2024
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
08/05/2026Structural Steel - WeldingSAVERIO TARANTINOspecial
08/05/2026Post-installed AnchorsSAVERIO TARANTINOspecial
08/05/2026Structural Cold-Formed SteelSAVERIO TARANTINOspecial
08/05/2026Structural Stability – Alterations of existing buildingsSAVERIO TARANTINOspecial
08/05/2026Structural Steel - DetailsSAVERIO TARANTINOspecial
08/04/2026FinalRONNY BECKERprogress
06/28/2025Structural Stability – Alterations of existing buildings—special
06/28/2025FinalRONNY BECKERprogress
06/23/2025Structural Stability – Alterations of existing buildings—special
06/23/2025FinalRONNY BECKERprogress
▾Documents — 36 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/24/2026B01115426-I1Request digital key ↗
08/21/2026B01200305-P1Request digital key ↗
08/21/2026B01200305-S1Request digital key ↗
Showing 3 of 7 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B01237410-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B01237410-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B01237410-I1Open ↗
▸Seals & Professional Certifications12
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/24/2026B01115426-I1Open ↗
08/21/2026B01200305-S1Open ↗
08/21/2026B01200305-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
09/16/2026B01237410-S6Open ↗
09/01/2026B01200305-I1Open ↗
08/29/2026B01200305-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/16/2026B01237410-S6Open ↗
08/26/2026B01237410-S4Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026B01237410-I1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B01237410-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B01237410-I1Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/21/2026B01200305-S1Open ↗
08/21/2026B01200305-I1Open ↗
08/21/2026B01200305-P1Open ↗
Showing 3 of 6 on file for this type
▸Inspections & Test Reports2
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B01237410-S5Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026B01237410-S5Open ↗
▸Other Documents3
▸DOB NOWProperty Ownership Certification1
08/13/2026B01237410-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01237410-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026B01237410-I1Open ↗