Miscellaneous two family
217 BUEL AVENUE
STATEN ISLAND · Grasmere-Arrochar-South Beach-Dongan Hills · BIN 5050732
💬 Discuss this project
2000Year Built
2Stories
B9Building Class
R3XZoning
1,667 sfGross Floor Area
2Units
Miscellaneous two family · 3,224 sf lot · 0.52 FAR built · Flood zone X500
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC110/13/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN SOLAR ELECTL CORPElectrical103/22/2026
SUNRUN INSTALLATION SVCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272110/13/2025
Building Lifecycle
All (9)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (6)
01/07/2026
Signed off — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF-MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
S01299920-I1
10/21/2025
Permit issued — Solar
S01299920-I1-SL
10/13/2025
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF-MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
S01299920-I1
10/13/2025
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Walid Abdulla
10/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
10/08/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
10/08/2025
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
10/08/2025
Special inspection requirement — Final
Walid Abdulla
10/08/2025
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC10/21/2025
BIS—ISSUEDKDC OF STATEN ISLAND INC03/19/2001
BISPLISSUEDACCURATE PLUMBING & HEATING CORP02/17/2000
BIS—ISSUEDKDC OF STATEN ISLAND INC01/13/2000
2 projects · most recent 07/08/2026
FiledStatusContractorScope
07/08/2026Permit IssuedTRUE ELECTRIC CORP.2 meters, 2 new_meters
10/13/2025CompleteSUNRUN SOLAR ELECTL CORP—
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
10/13/2025Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Walid Abdullaspecial
10/08/2025Fire-Resistant Penetrations and JointsWalid Abdullaspecial
10/08/2025Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
10/08/2025Energy Code Compliance InspectionsWalid Abdullaprogress
10/08/2025FinalWalid Abdullaprogress
10/08/2025Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/18/2026S01299920-I1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature3
08/28/2026S01299920-I1Open ↗
08/28/2026S01299920-I1Open ↗
08/28/2026S01299920-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/28/2026S01299920-I1Open ↗
08/28/2026S01299920-I1Open ↗
08/28/2026S01299920-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S01299920-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01299920-I1Open ↗