| Owner | Filings | Most Recent |
|---|---|---|
| TED CONTRACTING | 24 | 08/25/2026 |
| KING CONSTRUCTION NY | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ALWAYS FAST SERVICES CORP | 1 | 07/03/2026 |
| BRICOLAGE DESIGNS | 5 | 01/15/2026 |
| SELF EMPLOYED | 1 | 01/06/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| BRICOLAGE DESIGNS | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KING CONSTRUCTION NY, INC | General Contractor | 4 | 08/18/2026 |
| TED CONTRACTING CORP | General Contractor | 3 | 08/25/2026 |
| RRP PLUMBING CORP | Fire Protection | 1 | 08/20/2026 |
| ALPHA SCAFFOLDING INC | General Contractor | 1 | 07/16/2026 |
| RRP PLUMBING CORP | Plumbing | 1 | 08/20/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 5 | 01/06/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | TED CONTRACTING CORP | 08/24/2026 |
| DOB NOW | Plumbing | Permit Issued | RRP PLUMBING CORP | 08/19/2026 |
| DOB NOW | Sprinklers | Permit Issued | RRP PLUMBING CORP | 08/19/2026 |
| DOB NOW | General Construction | Permit Issued | KING CONSTRUCTION NY, INC | 08/17/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | TED CONTRACTING CORP | 08/06/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | ALPHA SCAFFOLDING INC | 07/15/2026 |
| DOB NOW | Support of Excavation | Permit Issued | KING CONSTRUCTION NY, INC | 05/12/2026 |
| DOB NOW | Construction Fence | Permit Issued | KING CONSTRUCTION NY, INC | 04/24/2026 |
| DOB NOW | General Construction | Permit Issued | KING CONSTRUCTION NY, INC | 12/17/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | TED CONTRACTING CORP | 12/08/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/15/2026 | Permit Issued | TED CONTRACTING CORP | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM36NAM-U1 36,000 BTU · Condensing Unit ×4 MXZ-SM42NAMHZ-U1 42,000 BTU · Condensing Unit ×2 MXZ-SM60NAM-U1 60,000 BTU · Condensing Unit ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/15/2026 | Permit Issued | RRP PLUMBING CORP | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2026 | Permit Issued | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/15/2026 | Permit Issued | TED CONTRACTING CORP | 2 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/03/2026 | Permit Issued | ALPHA SCAFFOLDING INC | Sidewalk Shed |
| 01/15/2026 | Permit Issued | TED CONTRACTING CORP | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/15/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 05/15/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 05/15/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/13/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/18/2025 | Construction Operations Influencing Adjacent Structures | Younes Abouyaala | special |
| 12/18/2025 | Excavations - Sheeting, Shoring, and Bracing | Younes Abouyaala | special |
| 12/18/2025 | Subgrade Inspections | Younes Abouyaala | special |
| 04/03/2025 | HVAC-R and service water heating equipment | Younes Abouyaala | energy_progress |
| 04/03/2025 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 04/03/2025 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 04/03/2025 | Maintenance information | Younes Abouyaala | energy_progress |
| 11/21/2024 | Air barrier — testing | Younes Abouyaala | energy_progress |
| 08/30/2022 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 08/30/2022 | Structural Steel - High Strength Bolting | Younes Abouyaala | special |
| 08/30/2022 | Subgrade Inspections | Younes Abouyaala | special |
| 08/30/2022 | Concrete - Cast-In-Place | Younes Abouyaala | special |
| 08/30/2022 | Exterior lighting power | Younes Abouyaala | energy_progress |
| 08/30/2022 | Metering | Younes Abouyaala | energy_progress |
| 08/30/2022 | Fenestration air leakage | Younes Abouyaala | energy_progress |
| 08/30/2022 | Protection of exposed foundation insulation | Younes Abouyaala | energy_progress |
| 08/30/2022 | Exterior Insulation and Finish Systems (EIFS) | Younes Abouyaala | special |
| 08/30/2022 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 08/30/2022 | Fire-Resistance Rated Construction | Younes Abouyaala | progress |
| 08/30/2022 | Fenestration and door U-factor and product ratings | Younes Abouyaala | energy_progress |
| 08/30/2022 | Interior lighting power | Younes Abouyaala | energy_progress |
| 08/30/2022 | Air barrier - visual inspection | Younes Abouyaala | energy_progress |
| 08/30/2022 | Maintenance information | Younes Abouyaala | energy_progress |
| 08/30/2022 | Lighting controls | Younes Abouyaala | energy_progress |
| 08/30/2022 | Fenestration areas | Younes Abouyaala | energy_progress |