← Back
Court house
Bronx Family and Criminal Court
217 EAST 161 STREET · Concourse-Concourse Village · BIN 2002704
💬 Discuss this project
1968Year Built
10Stories
Z1Building Class
C4-6Zoning
689,840 sfGross Floor Area
3Units
LL97 Covered43 Open Violations 38 unresolved · 5 paperwork only ▸FISP: SAFE
Court house · 70,400 sf lot · 9.8 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingEquipmentCivilGeneral
Permit Issued — active, not yet Signed-off
Roof1 filing · 13 docs
Floor 4Under Construction6p · 3 filings · 20 docs
Floor 3Under Construction2p · 2 filings · 20 docs
Floor 2Under Construction4p · 1 filing · 18 docs
Floor 11 filing · 4 docs
Site & exterior1 filing · 3 docs
Filed — no permit issued1 filing · 14 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DCAS8307/08/2026
CITIDENT303/21/2026
CITY OF NEW YORK DCAS203/21/2026
DEPT OF GENERAL SERVICES203/21/2026
DASNY103/21/2026
DGS103/21/2026
DEPARTMENT OF CITYWIDE ADMIN SER103/21/2026
DEPT GENERAL SERVICES103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JMV ASSOCIATES1203/21/2026
SUPERSTRUCTURES ENG + ARCH103/21/2026
YSRAEL A SEINUK P C203/21/2026
AC BUILDING CONSULTANTS603/21/2026
ARISTAR GROUP203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
AAA WINDOWS & DOORS CORPGeneral Contractor1407/08/2026
VANGUARD CONSTRUCTION ANDGeneral Contractor907/08/2026
CONTRACT & HOSPITALITYGeneral Contractor506/28/2026
J & N CONSTRUCTION GROUPGeneral Contractor407/08/2026
PHILIP MISHENElectrical203/21/2026
GEORGE BRESLAW PLBNG LLCPlumbing207/08/2026
MP & L METAL INCElectrical103/21/2026
PIMPINELLA, FRANKElectrical103/21/2026
PISULA, KONRADElectrical103/21/2026
RICHARD SAJIUNElectrical103/21/2026
YOUNG, CHRISTOPHERElectrical103/21/2026
AWL INDUSTRIES INCGeneral Contractor104/09/2026
BEKKERMAN, MIKHAILElectrical103/21/2026
MAC FELDER INCPlumbing107/08/2026
FRANCIS RICHARDSElectrical103/21/2026
FRANK MERESHENSKYElectrical103/21/2026
GARCIA, ROBERTElectrical103/21/2026
JOSEPH RUBELElectrical103/21/2026
KING, ARTHURElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TECTONIC ENGINEERING CONS106602/04/2026
JOADEM CORPORATION4350112/09/2024
RYAN SPECIAL ENGINEERING2018304/18/2024
SUPERSTRUCTURES ENGINEERI374104/04/2023
Building Lifecycle
All (182)Filed (15)Permit Issued (27)Signed Off (3)Facade (FISP) (16)Violation (60)Inspection (1)Objection (30)Special Inspection (30)
03/13/2026
Permit issued — Mechanical Systems
X00913620-I1-GC
02/04/2026
Filed — Alteration
Replace AC-5 and RF-5 in 3rd FL M.E.R. Replace existing VAV, FTR and install new AC-6 in 4th floor and AC-6s condenser on 4th floor roof.
X00703679-P2
12/23/2025
Objection resolved — Addressed
10/31/2025
Special inspection requirement — Energy Code Compliance Inspections
GEORGE GHEBRYAL
10/31/2025
Special inspection requirement — Fire-Resistance Rated Construction
GEORGE GHEBRYAL
10/31/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
10/30/2025
Objection resolved — Addressed
10/27/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
GEORGE GHEBRYAL
10/27/2025
Special inspection requirement — HVAC-R and service water heating system controls
GEORGE GHEBRYAL
10/27/2025
Special inspection requirement — Fire-Resistance Rated Construction
GEORGE GHEBRYAL
10/27/2025
Special inspection requirement — HVAC-R and service water heating equipment
GEORGE GHEBRYAL
10/27/2025
Special inspection requirement — Shutoff dampers
GEORGE GHEBRYAL
10/27/2025
Special inspection requirement — Final
GEORGE GHEBRYAL
10/27/2025
Special inspection requirement — Maintenance information
GEORGE GHEBRYAL
10/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
10/27/2025
Special inspection requirement — Mechanical Systems
GEORGE GHEBRYAL
10/27/2025
Special inspection requirement — Energy Code Compliance Inspections
GEORGE GHEBRYAL
09/09/2025
Objection resolved — Addressed
09/09/2025
Objection resolved — Addressed
08/11/2025
Objection raised — Other
08/11/2025
Objection raised — Other
08/11/2025
Objection raised — Other
08/07/2025
Filed — Alteration
Interior renovation, including floor finishes, ceiling finishes, limited wall and layout changes, and 2 single use bathroom fixtures and accessory replacements.
X00569307-P1
07/15/2025
Objection resolved — Addressed
07/14/2025
Objection raised — Admin
07/14/2025
Objection raised — Zoning
07/09/2025
Permit issued — Mechanical Systems
X00913620-I1-GC
07/08/2025
Filed — Alteration
Replacement of storm drains. No change to use, egress or occupancy.
X01015634-S2
07/08/2025
Filed — Alteration
Replacement of storm drains. No change to use, egress or occupancy.
X01015634-S3
07/01/2025
Special inspection requirement — Post-installed Anchors
07/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/24/2025
Permit issued — General Construction
X00569307-I1-GC
06/24/2025
Permit issued — Mechanical Systems
X00703679-I1-MS
05/23/2025
Filed — Alteration
Replace AC-5 and RF-5 in 3rd FL M.E.R. Replace existing VAV, FTR and install new AC-6 in 4th floor and AC-6s condenser on 4th floor roof.
X00703679-P1
05/21/2025
Special inspection requirement — HVAC-R and service water heating system controls
GEORGE GHEBRYAL
05/21/2025
Special inspection requirement — Mechanical Systems
GEORGE GHEBRYAL
05/21/2025
Special inspection requirement — Energy Code Compliance Inspections
GEORGE GHEBRYAL
05/21/2025
Special inspection requirement — Final
GEORGE GHEBRYAL
05/21/2025
Special inspection requirement — Fire-Resistance Rated Construction
GEORGE GHEBRYAL
05/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
05/21/2025
Special inspection requirement — Maintenance information
GEORGE GHEBRYAL
05/21/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
GEORGE GHEBRYAL
05/21/2025
Special inspection requirement — HVAC-R and service water heating equipment
GEORGE GHEBRYAL
05/21/2025
Special inspection requirement — Shutoff dampers
GEORGE GHEBRYAL
01/24/2025
Permit issued — Mechanical Systems
X00913620-I1-GC
01/24/2025
Permit issued — Mechanical Systems
X00913620-S1-MS
01/02/2025
Objection resolved — Addressed
12/11/2024
Objection raised — Other
12/09/2024
Filed — Alteration
Replacement of storm drains. No change to use, egress or occupancy.
X01015634-I1
12/09/2024
Filed — Alteration
Replacement of storm drains. No change to use, egress or occupancy.
X01015634-S1
12/09/2024
Objection resolved — Addressed
11/26/2024
Special inspection requirement — Final
11/26/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
11/26/2024
Special inspection requirement — Post-installed Anchors
11/26/2024
Special inspection requirement — Structural Steel - Welding
11/26/2024
Special inspection requirement — Structural Steel - High Strength Bolting
09/18/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
X00845231-I1
06/13/2024
Permit issued — Mechanical Systems
X00703679-I1-MS
06/13/2024
Permit issued — General Construction
X00569307-I1-GC
04/19/2024
Objection raised — Fire_Protection
Latest 60 of 182 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedCONTRACT & HOSPITALITY03/13/2026
DOB NOWMechanical SystemsPermit IssuedCONTRACT & HOSPITALITY07/09/2025
DOB NOWGeneral ConstructionPermit IssuedVANGUARD CONSTRUCTION AND06/24/2025
DOB NOWMechanical SystemsPermit IssuedVANGUARD CONSTRUCTION AND06/24/2025
DOB NOWMechanical SystemsPermit IssuedCONTRACT & HOSPITALITY01/24/2025
DOB NOWMechanical SystemsPermit IssuedAWL INDUSTRIES INC01/24/2025
DOB NOWMechanical SystemsPermit IssuedVANGUARD CONSTRUCTION AND06/13/2024
DOB NOWGeneral ConstructionPermit IssuedVANGUARD CONSTRUCTION AND06/13/2024
DOB NOWPlumbingSigned-offGEORGE BRESLAW PLBNG LLC02/02/2024
DOB NOWGeneral ConstructionPermit IssuedVANGUARD CONSTRUCTION AND06/14/2023
DOB NOWMechanical SystemsPermit IssuedVANGUARD CONSTRUCTION AND06/14/2023
DOB NOWGeneral ConstructionSigned-offJ & N CONSTRUCTION GROUP05/05/2023
DOB NOWSidewalk ShedSigned-offJ & N CONSTRUCTION GROUP03/17/2023
DOB NOWPlumbingSigned-offGEORGE BRESLAW PLBNG LLC02/09/2023
DOB NOWPlumbingSigned-offMAC FELDER INC01/23/2023
DOB NOWMechanical SystemsPermit IssuedVANGUARD CONSTRUCTION AND01/20/2023
DOB NOWGeneral ConstructionPermit IssuedVANGUARD CONSTRUCTION AND01/17/2023
DOB NOWSidewalk ShedSigned-offAAA WINDOWS & DOORS CORP10/28/2022
DOB NOWSidewalk ShedSigned-offAAA WINDOWS & DOORS CORP08/26/2021
DOB NOWSidewalk ShedSigned-offAAA WINDOWS & DOORS CORP03/24/2021
DOB NOWSidewalk ShedSigned-offAAA WINDOWS & DOORS CORP11/25/2020
DOB NOWSidewalk ShedSigned-offAAA WINDOWS & DOORS CORP04/07/2020
DOB NOWSidewalk ShedSigned-offAAA WINDOWS & DOORS CORP03/05/2019
DOB NOWSidewalk ShedSigned-offAAA WINDOWS & DOORS CORP11/20/2018
DOB NOWSidewalk ShedSigned-offAAA WINDOWS & DOORS CORP08/15/2018
DOB NOWSidewalk ShedSigned-offAAA WINDOWS & DOORS CORP07/25/2018
DOB NOWSidewalk ShedSigned-offAAA WINDOWS & DOORS CORP03/19/2018
BISOTISSUEDAFL CONSTRUCTION CO INC03/12/2019
BISMHISSUEDMEC-CON ASSOCIATES INC03/07/2019
BISOTISSUEDAFL CONSTRUCTION CO INC08/31/2018
BISMHISSUEDMEC-CON ASSOCIATES INC08/08/2018
BISOTISSUEDAFL CONSTRUCTION CO INC04/18/2018
BISSPISSUEDACE CONTRACTING, INC09/12/2017
BISFSISSUEDJACK PICCINI, INC02/10/2017
BISEQISSUEDSAFWAY ATLANTIC, LLC10/19/2016
BISOTISSUEDCONSTRUCTOMICS LLC09/29/2016
BISOTISSUEDCONSTRUCTOMICS LLC09/29/2016
BISPLISSUEDACE CONTRACTING, INC09/07/2016
BISSPISSUEDACE CONTRACTING, INC09/07/2016
BISMHISSUEDNORTH STAR MECHANICAL COR08/26/2016
+ 37 more permits on file
3 projects · most recent 02/04/2026
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
02/04/2026Permit IssuedVANGUARD CONSTRUCTION ANDAir Conditioning Systems, Heating Systems
Cooling
Trane PLA-A24EAB 24,000 BTU · Vrf Indoor ×5
SLZKF12NA 14,500 BTU · Vrf Indoor ×5
TPLA0A0241EA70A &TRUZA0241HA70(N/B)A 24,000 BTU ×5
Mitsubishi Electric TPLA0A0241EA70A &TRUZA0241HA70(N/B)A 24,000 BTU ×1
Heating
Trane TPLA0A0241EA70A & TRUZA0241HA70(N/B)A 26,000 BTU · Split System ×5
Mitsubishi Electric TPLA0A0241EA70A & TRUZA0241HA70NA 26,000 BTU · Split System ×1
07/08/2025——Air Conditioning Systems
Cooling
Carrier 50FC-M12A6A6-8W1C0 4,000 CFM · Fan Coil Indoor ×1
50FC-M16A6A6-8W1C0 6,000 CFM · Fan Coil Indoor ×1
04/18/2024Permit IssuedCONTRACT & HOSPITALITY*Ventilation Systems
Ventilation
Titus DESV 150 CFM · Vav Box ×6
Ducts & Piping
Titus DESV 150 CFM · Vav Box ×6
2 projects · most recent 07/08/2025
Storm Water/Sanitary
FiledStatusContractorScope
07/08/2025——Storm
04/29/2022Signed-offGEORGE BRESLAW PLBNG LLCWater/Sanitary
9 projects · most recent 05/02/2025
General Wiring Lighting
FiledStatusContractorScope
05/02/2025CompleteC.B. MILLS ELECTRIC LLCGeneral Wiring
03/16/2023Permit IssuedAMIN ELECTRICAL CORP—
03/16/2023Permit IssuedAMIN ELECTRICAL CORP—
10/13/2020CompleteELMHURST ELECTRIC CORPGeneral Wiring
07/09/2019Permit IssuedP & M ELECT'L CONTR. CORPGeneral Wiring
03/25/2019CompleteELMHURST ELECTRIC CORPGeneral Wiring
11/15/2018Permit IssuedHERTZ ELECTRIC LLC—
04/03/2018Permit IssuedSELECTRIC ELECL CONT CO IGeneral Wiring, Lighting
03/09/2018Permit IssuedHERTZ ELECTRIC LLC—
1 project · most recent 07/08/2025
Steel Concrete
FiledStatusContractorScope
07/08/2025——Steel, Concrete
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
06/14/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 46
DateRequirementInspectorRole
10/31/2025Energy Code Compliance InspectionsGEORGE GHEBRYALprogress
10/31/2025Fire-Resistance Rated ConstructionGEORGE GHEBRYALprogress
10/31/2025Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
10/27/2025HVAC-R and service water piping design and insulationGEORGE GHEBRYALenergy_progress
10/27/2025HVAC-R and service water heating system controlsGEORGE GHEBRYALenergy_progress
10/27/2025Fire-Resistance Rated ConstructionGEORGE GHEBRYALprogress
10/27/2025HVAC-R and service water heating equipmentGEORGE GHEBRYALenergy_progress
10/27/2025Shutoff dampersGEORGE GHEBRYALenergy_progress
10/27/2025FinalGEORGE GHEBRYALprogress
10/27/2025Maintenance informationGEORGE GHEBRYALenergy_progress
10/27/2025Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
10/27/2025Mechanical SystemsGEORGE GHEBRYALspecial
10/27/2025Energy Code Compliance InspectionsGEORGE GHEBRYALprogress
07/01/2025Post-installed Anchors—special
07/01/2025Fire-Resistant Penetrations and Joints—special
05/21/2025HVAC-R and service water heating system controlsGEORGE GHEBRYALenergy_progress
05/21/2025Mechanical SystemsGEORGE GHEBRYALspecial
05/21/2025Energy Code Compliance InspectionsGEORGE GHEBRYALprogress
05/21/2025FinalGEORGE GHEBRYALprogress
05/21/2025Fire-Resistance Rated ConstructionGEORGE GHEBRYALprogress
05/21/2025Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
05/21/2025Maintenance informationGEORGE GHEBRYALenergy_progress
05/21/2025HVAC-R and service water piping design and insulationGEORGE GHEBRYALenergy_progress
05/21/2025HVAC-R and service water heating equipmentGEORGE GHEBRYALenergy_progress
05/21/2025Shutoff dampersGEORGE GHEBRYALenergy_progress
Latest 25 of 46.
▾Documents — 589 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch15
08/26/2026X00026148-I1Request digital key ↗
08/24/2026X00704381-I1Request digital key ↗
08/23/2026X00845231-I1Request digital key ↗
Showing 3 of 15 on file for this type
▸Applications & Permits133
▸BISWORK PERMIT APPLICATION74
03/13/2019220612308Open ↗
03/08/2019220612308Open ↗
09/04/2018220612308Open ↗
Showing 3 of 74 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION57
09/07/2023220612503Open ↗
01/20/2023220612503Open ↗
01/10/2023220612503Open ↗
Showing 3 of 57 on file for this type
▸BISAFTER-HOUR WORK PERMIT APPLICATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Seals & Professional Certifications162
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION95
10/12/2018220612308Open ↗
10/11/2018220612308Open ↗
07/30/2018220062795Open ↗
Showing 3 of 95 on file for this type
▸DOB NOWProgress Inspector Seal & Signature27
09/01/2026X00703679-P2Open ↗
09/01/2026X00703679-P2Open ↗
09/01/2026X00703679-P2Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature15
08/23/2026X00845231-I1Open ↗
08/23/2026X00854030-I1Open ↗
08/18/2026X00569307-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/01/2026X00703679-P2Open ↗
09/01/2026X00703679-P2Open ↗
08/31/2026X00569307-I1Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST6
10/19/2016220555691Open ↗
Showing 1 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISPC FULL REPORT3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISApplicant / Owner Signature1
11/18/2013240041432Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
10/19/2016220555691Open ↗
▸Trade Schedules & Equipment28
▸BISSELF-CERT PLUMBING NOTICE14
06/08/2015220062795Open ↗
08/15/2014220062795Open ↗
08/12/2014220062795Open ↗
Showing 3 of 14 on file for this type
▸BISSCHEDULE B - PLUMBING6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISEQUIPMENT USE PERMITS2
11/06/2017220062795Open ↗
Showing 1 of 2 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
02/16/2016220452258Open ↗
02/16/2016220452258Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT2
11/06/2017220062795Open ↗
Showing 1 of 2 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
08/18/2017220062795Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026X00913620-I1Open ↗
▸Environmental & Asbestos34
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP 20-21-5)7
04/18/2018220612308Open ↗
10/06/2017220063543Open ↗
Showing 2 of 7 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
08/15/2026X00569307-I1Open ↗
08/15/2026X00703679-I1Open ↗
08/13/2026X00913620-S1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
09/10/2013220116274Open ↗
Showing 1 of 4 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
11/18/2013240041432Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
02/21/2018220062795Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/23/2026X00854030-I1Open ↗
▸Energy Compliance30
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS11
04/17/2018220612308Open ↗
11/06/2017220159316Open ↗
08/22/2017220612308Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: ENERGY9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
11/12/2020220113883Open ↗
10/30/2020220113883Open ↗
04/28/2017220159316Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
11/12/2020220113883Open ↗
10/30/2020220113883Open ↗
▸BISTR8: Energy Code Progress Inspections2
11/18/2013240041432Open ↗
Showing 1 of 2 on file for this type
▸Inspections & Test Reports12
▸BISTECHNICAL REPORT: RESPONSIBILITY9
03/26/2021220113883Open ↗
03/26/2021220113883Open ↗
03/26/2021220113883Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
06/18/2018220062795Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs93
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST37
04/19/2021220113883Open ↗
08/01/2018220062795Open ↗
07/30/2018220062795Open ↗
Showing 3 of 37 on file for this type
▸BISADMINISTRATIVE OBJECTIONS23
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 23 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION15
03/26/2021220113883Open ↗
11/12/2020220113883Open ↗
10/19/2016220555691Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter15
08/23/2026X00854030-I1Open ↗
08/17/2026X00703679-P2Open ↗
08/17/2026X00703679-P1Open ↗
Showing 3 of 15 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION1
10/25/2018220113883Open ↗
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)1
08/13/2026X01015634-S1Open ↗
▸DOB NOWDEP Variance (V5) letter1
08/13/2026X00704381-I1Open ↗
▸Cost, Insurance & Ownership40
▸BISCOST AFFIDAVIT40
04/19/2021220113883Open ↗
11/12/2020220113883Open ↗
10/30/2020220113883Open ↗
Showing 3 of 40 on file for this type
▸Filing & Intake Forms38
▸BISEFILING COVER SHEET20
08/22/2017220612503Open ↗
08/22/2017220612308Open ↗
08/22/2017220612308Open ↗
Showing 3 of 20 on file for this type
▸BISBOROUGH INTAKE FORM10
07/30/2018220062795Open ↗
06/18/2018220062795Open ↗
02/21/2018220062795Open ↗
Showing 3 of 10 on file for this type
▸BISADDITIONAL INFORMATION7
11/06/2017220062795Open ↗
11/06/2017220062795Open ↗
12/23/2013240041432Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
11/18/2013240041432Open ↗
▸Other Documents3
▸BISSupporting Document: Fee Exempt1
11/12/2020220113883Open ↗
▸DOB NOWBSA Meeting Minutes/BSA Resolution1
08/13/2026X00026148-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026X01015634-I1Open ↗