| Owner | Filings | Most Recent |
|---|---|---|
| ATRIYA LLC | 2 | 03/22/2026 |
| 352 6TH | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/20/2023 | $2.7M | — | — → — | $545/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MIB CONSULTING | 7 | 09/05/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| 4444 PPPP | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MOSSO CONSTRUCTION INC | General Contractor | 6 | 07/08/2026 |
| APPROVED ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| SAMUEL & SONS P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MARKANICS CORP | 4600 | 7 | 09/05/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | MOSSO CONSTRUCTION INC | 12/02/2022 |
| DOB NOW | General Construction | Signed-off | MOSSO CONSTRUCTION INC | 08/03/2022 |
| DOB NOW | General Construction | Signed-off | MOSSO CONSTRUCTION INC | 08/03/2022 |
| DOB NOW | Plumbing | Signed-off | SAMUEL & SONS P & H INC | 06/01/2022 |
| DOB NOW | General Construction | Signed-off | MOSSO CONSTRUCTION INC | 05/25/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2023 | Complete | APPROVED ELECTRIC CORP. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/02/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 07/17/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 07/06/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/25/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/25/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/17/2022 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 12/09/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/15/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/01/2023 | Fire-Resistant Penetrations and Joints | Malcolm Barkan | special |
| 01/20/2023 | Energy Code Compliance Inspections | Malcolm Barkan | progress |
| 01/20/2023 | Fire-Resistant Penetrations and Joints | Malcolm Barkan | special |
| 12/28/2022 | Lighting in dwelling units | Malcolm Barkan | energy_progress |
| 12/28/2022 | Fire-Resistant Penetrations and Joints | Malcolm Barkan | special |
| 12/28/2022 | Energy Code Compliance Inspections | Malcolm Barkan | progress |
| 12/28/2022 | Interior lighting power | Malcolm Barkan | energy_progress |
| 12/28/2022 | Lighting in dwelling units | Malcolm Barkan | energy_progress |
| 12/28/2022 | Fire-Resistant Penetrations and Joints | Malcolm Barkan | special |
| 12/23/2022 | Energy Code Compliance Inspections | Malcolm Barkan | progress |
| 12/23/2022 | Fire-Resistant Penetrations and Joints | Malcolm Barkan | special |
| 04/01/2022 | Fire-Resistant Penetrations and Joints | Malcolm Barkan | special |
| 04/01/2022 | Energy Code Compliance Inspections | Malcolm Barkan | progress |
| 04/01/2022 | Interior lighting power | Malcolm Barkan | energy_progress |
| 04/01/2022 | Lighting in dwelling units | Malcolm Barkan | energy_progress |