| Owner | Filings | Most Recent |
|---|---|---|
| CARMIKE HOLDING LLC | 3 | 03/22/2026 |
| ABECO CONSTRUCTION | 3 | 03/22/2026 |
| TO THE OWNER OF THE PREMI | 2 | 03/22/2026 |
| TO THE OWNER OF PREMISES | 2 | 03/22/2026 |
| MAGEN DAVID YESHIVAH SCHOOL | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| IMC ARCHITECTURE DPC | 2 | 07/29/2026 |
| A&D ENGINEERING, PLLC | 4 | 01/08/2026 |
| FL&M ENGINEERING DESIGN &INSPECTION | 3 | 06/25/2025 |
| ELEVATED ENGINEERING NYC | 5 | 04/07/2025 |
| JOSELOW & ASSOCIATES, LLC | 2 | 08/31/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| CORE CONSULTANTS NYC | 9 | 03/21/2026 |
| 4444 PPPP CORP | 4 | 03/21/2026 |
| GEIGER E A GROUP | 6 | 03/21/2026 |
| SELECT TYPE | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ABECO CONSTRUCTION LLC | General Contractor | 5 | 07/08/2026 |
| INTERSTATE AIR COND & HTG | General Contractor | 3 | 03/21/2026 |
| MC SUPERSTRUCTURE INC | General Contractor | 2 | 07/08/2026 |
| S&R ELECTRICAL & MECHANIC | Electrical | 2 | 03/22/2026 |
| P.H. WORKS INC | Plumbing | 1 | 07/08/2026 |
| POWER DIRECT ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| SAFETY FIRE SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| NASH ELECTRIC SERVICES IN | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MJ ENGINEERING & DESIGN | 5546 | 10 | 07/29/2026 |
| INTEGRITY CONSULTING SERV | 666 | 2 | 08/31/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | SAFETY FIRE SPRINKLER CORP | 05/22/2025 |
| DOB NOW | Plumbing | Signed-off | P.H. WORKS INC | 05/02/2025 |
| DOB NOW | General Construction | Permit Issued | ABECO CONSTRUCTION LLC | 04/17/2025 |
| DOB NOW | Construction Fence | Signed-off | MC SUPERSTRUCTURE INC | 04/09/2025 |
| DOB NOW | Construction Fence | Signed-off | MC SUPERSTRUCTURE INC | 04/09/2025 |
| DOB NOW | Structural | Signed-off | ABECO CONSTRUCTION LLC | 04/07/2025 |
| DOB NOW | Foundation | Signed-off | ABECO CONSTRUCTION LLC | 04/07/2025 |
| DOB NOW | Support of Excavation | Signed-off | ABECO CONSTRUCTION LLC | 04/04/2025 |
| DOB NOW | Mechanical Systems | Signed-off | ABECO CONSTRUCTION LLC | 04/03/2025 |
| DOB NOW | Mechanical Systems | Signed-off | INTERSTATE AIR COND & HTG | 08/11/2023 |
| BIS | — | ISSUED | MAGEN DAVID YESHIVA | 09/01/2017 |
| BIS | OT | ISSUED | BEST ENERGY POWER LLC | 06/28/2011 |
| BIS | PL | ISSUED | DC BUILDING SERVICES INC | 06/04/2009 |
| BIS | OT | ISSUED | NATIONAL BUILDERS LLC | 06/25/2008 |
| BIS | OT | ISSUED | NATIONAL BUILDERS LLC | 06/25/2008 |
| BIS | EQ | ISSUED | NATIONAL BUILDERS LLC | 05/08/2008 |
| BIS | PL | ISSUED | DC BUILDING SERVICES INC | 05/02/2008 |
| BIS | SP | ISSUED | DC BUILDING SERVICES INC | 05/02/2008 |
| BIS | OT | ISSUED | NATIONAL BUILDERS LLC | 04/03/2008 |
| BIS | EQ | ISSUED | BAY RESTORATION CORP | 04/01/2008 |
| BIS | — | ISSUED | NATIONAL BUILDERS LLC | 03/14/2008 |
| BIS | OT | ISSUED | NATIONAL BUILDERS LLC | 02/11/2008 |
| BIS | OT | ISSUED | D. M JEFFRIES DEVE CORP. | 02/07/1997 |
| BIS | BL | ISSUED | KAPLAN-BRESLAW INC | 09/28/1994 |
| BIS | PL | ISSUED | KAPLAN-BRESLAW INC | 06/13/1994 |
| BIS | OT | ISSUED | NY BUILDERS GROUP | 05/18/1994 |
| BIS | MH | ISSUED | N.Y. BUILDERS GRP/GJF CONST CORP | 05/18/1994 |
| BIS | OT | ISSUED | N.Y. BUILDERS GRP/GJF CONST CORP | 04/12/1994 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/29/2026 | Permit Issued | ABECO CONSTRUCTION LLC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Lg ARUM144BTE5 162,000 BTU · Vrf Outdoor ×4 Ventilation S&P Usa Ventilation Systems TRC1600 1,300 CFM · Erv ×4 Greenheck G-100-VG 580 CFM · Exhaust Fan ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Signed-off | SAFETY FIRE SPRINKLER COR | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Signed-off | P.H. WORKS INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2025 | Permit Issued | S&R ELECTRICAL & MECHANIC | General Wiring |
| 06/24/2025 | Complete | NASH ELECTRIC SERVICES IN | — |
| 06/18/2025 | Permit Issued | S&R ELECTRICAL & MECHANIC | — |
| 06/06/2025 | Permit Issued | POWER DIRECT ELECTRIC INC | — |
| 08/18/2023 | Permit Issued | ACCURATE ELEC'L CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Signed-off | SAFETY FIRE SPRINKLER COR | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Signed-off | SAFETY FIRE SPRINKLER COR | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/22/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/05/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/02/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/06/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 06/05/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 06/05/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/10/2026 | Exterior Insulation and Finish Systems (EIFS) | Magdy Youssef | special |
| 07/10/2026 | Insulation placement and R values | Magdy Youssef | energy_progress |
| 07/10/2026 | Air barrier - visual inspection | Magdy Youssef | energy_progress |
| 07/10/2026 | Fire-Resistance Rated Construction | Magdy Youssef | progress |
| 07/10/2026 | Energy Code Compliance Inspections | Magdy Youssef | progress |
| 07/10/2026 | Sprayed fire-resistant materials | Magdy Youssef | special |
| 07/10/2026 | Fire-Resistant Penetrations and Joints | Magdy Youssef | special |
| 04/04/2026 | Energy Code Compliance Inspections | Magdy Youssef | progress |
| 04/04/2026 | Final | Magdy Youssef | progress |
| 04/04/2026 | Mechanical Systems | Magdy Youssef | special |
| 04/04/2026 | Fire-Resistant Penetrations and Joints | Magdy Youssef | special |
| 04/04/2026 | Heating Systems | Magdy Youssef | special |
| 04/04/2026 | HVAC-R and service water heating equipment | Magdy Youssef | energy_progress |
| 04/04/2026 | HVAC-R and service water piping design and insulation | Magdy Youssef | energy_progress |
| 04/04/2026 | HVAC-R and service water heating system controls | Magdy Youssef | energy_progress |
| 04/04/2026 | Maintenance information | Magdy Youssef | energy_progress |
| 04/04/2026 | Shutoff dampers | Magdy Youssef | energy_progress |
| 04/04/2026 | Duct leakage testing, insulation and design | Magdy Youssef | energy_progress |
| 01/08/2026 | Final | Magdy Youssef | progress |
| 01/08/2026 | Shutoff dampers | Magdy Youssef | energy_progress |
| 01/08/2026 | Maintenance information | Magdy Youssef | energy_progress |
| 01/08/2026 | HVAC-R and service water heating equipment | Magdy Youssef | energy_progress |
| 01/08/2026 | HVAC-R and service water piping design and insulation | Magdy Youssef | energy_progress |
| 01/08/2026 | Duct leakage testing, insulation and design | Magdy Youssef | energy_progress |
| 01/08/2026 | Fire-Resistant Penetrations and Joints | Magdy Youssef | special |