| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/11/2022 | $1.8M | — | Private party → Private party | $772/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| J.K.DESIGN | 5 | 10/27/2023 |
| LEVIN ENGINEERING PLLC | 1 | 05/09/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| LEVIN ENGINEERING PLLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TCS CONSTRUCTION CORP | General Contractor | 12 | 03/21/2026 |
| ALTAIR PLUMBING AND HEAT | Plumbing | 5 | 07/08/2026 |
| VILLAGE P & H NY INC | Fire Protection | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STEEL CORE ENGINEERING PL | 1098 | 5 | 10/27/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | ALTAIR PLUMBING AND HEAT | 12/12/2023 |
| DOB NOW | Plumbing | Signed-off | ALTAIR PLUMBING AND HEAT | 11/29/2023 |
| DOB NOW | Mechanical Systems | Signed-off | TCS CONSTRUCTION CORP | 11/17/2023 |
| DOB NOW | Mechanical Systems | Signed-off | TCS CONSTRUCTION CORP | 11/17/2023 |
| DOB NOW | General Construction | Permit Issued | TCS CONSTRUCTION CORP | 08/22/2023 |
| DOB NOW | Sprinklers | Signed-off | VILLAGE P & H NY INC | 01/09/2023 |
| DOB NOW | Plumbing | Signed-off | ALTAIR PLUMBING AND HEAT | 11/29/2022 |
| DOB NOW | Plumbing | Signed-off | ALTAIR PLUMBING AND HEAT | 11/16/2022 |
| DOB NOW | Plumbing | Signed-off | ALTAIR PLUMBING AND HEAT | 10/20/2022 |
| DOB NOW | Plumbing | Signed-off | VILLAGE P & H NY INC | 10/14/2022 |
| DOB NOW | General Construction | Permit Issued | TCS CONSTRUCTION CORP | 09/22/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/28/2023 | Signed-off | TCS CONSTRUCTION CORP | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-4C35NA3-UI 28,400 BTU · Heat Pump Outdoor ×2 MXZ3C30NA3-UI 36,000 BTU · Heat Pump Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/25/2023 | Complete | AE ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/28/2023 | Signed-off | TCS CONSTRUCTION CORP | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/17/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/14/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/29/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/16/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/06/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/17/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/01/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/01/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/27/2023 | Fire-Resistant Penetrations and Joints | Alexander Sheyman | special |
| 10/27/2023 | Energy Code Compliance Inspections | Alexander Sheyman | progress |
| 10/26/2023 | Energy Code Compliance Inspections | Alexander Sheyman | progress |
| 10/26/2023 | Fire-Resistant Penetrations and Joints | Alexander Sheyman | special |
| 09/11/2023 | Maintenance information | Alexander Sheyman | energy_progress |
| 09/11/2023 | Structural Steel - Details | Alexander Sheyman | special |
| 09/11/2023 | Structural Stability – Alterations of existing buildings | Alexander Sheyman | special |
| 09/11/2023 | Mechanical Systems | Alexander Sheyman | special |
| 09/11/2023 | Structural Steel - Welding | Alexander Sheyman | special |
| 09/11/2023 | Fire-Resistant Penetrations and Joints | Alexander Sheyman | special |
| 09/11/2023 | Final | Alexander Sheyman | progress |
| 09/11/2023 | Fire-Resistance Rated Construction | Alexander Sheyman | progress |
| 09/11/2023 | Energy Code Compliance Inspections | Alexander Sheyman | progress |
| 09/11/2023 | HVAC-R and service water heating equipment | Alexander Sheyman | energy_progress |
| 09/11/2023 | Insulation placement and R values | Alexander Sheyman | energy_progress |
| 09/11/2023 | HVAC-R and service water piping design and insulation | Alexander Sheyman | energy_progress |
| 09/11/2023 | Air barrier - visual inspection | Alexander Sheyman | energy_progress |
| 09/11/2023 | Fenestration air leakage | Alexander Sheyman | energy_progress |
| 09/11/2023 | Fenestration and door U-factor and product ratings | Alexander Sheyman | energy_progress |
| 09/11/2023 | Fenestration areas | Alexander Sheyman | energy_progress |
| 09/11/2023 | HVAC-R and service water heating system controls | Alexander Sheyman | energy_progress |
| 09/11/2023 | Interior lighting power | Alexander Sheyman | energy_progress |
| 07/31/2022 | Fire-Resistant Penetrations and Joints | — | special |
| 07/31/2022 | Energy Code Compliance Inspections | — | progress |
| 07/31/2022 | Final | — | progress |