| Firm | Filings | Most Recent |
|---|---|---|
| MLS COMPLETE ENGINEERING | 4 | 05/29/2025 |
| EDWARD C. HICKS RA | 3 | 12/12/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| ABRIS DESIGN STUDIO | 7 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ROBKE PLUS INC | General Contractor | 6 | 07/08/2026 |
| FOUR POINTS P & H CORP | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 6 | 05/29/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | FOUR POINTS P & H CORP | 01/27/2025 |
| DOB NOW | General Construction | Signed-off | ROBKE PLUS INC | 05/29/2024 |
| DOB NOW | Construction Fence | Permit Issued | ROBKE PLUS INC | 05/29/2024 |
| DOB NOW | Plumbing | Signed-off | FOUR POINTS P & H CORP | 10/18/2023 |
| DOB NOW | Construction Fence | Permit Issued | ROBKE PLUS INC | 06/12/2023 |
| DOB NOW | General Construction | Signed-off | ROBKE PLUS INC | 06/05/2023 |
| BIS | PL | ISSUED | ISIS PLUMBING INC | 01/05/2004 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2024 | Signed-off | FOUR POINTS P & H CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/19/2025 | Complete | NAS ELECTRIC CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/15/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 05/23/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 05/02/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 04/21/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 02/24/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/20/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/04/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/24/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/09/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/08/2025 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 07/08/2025 | Fenestration areas | FAHAD FATEH | energy_progress |
| 07/08/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 07/08/2025 | Excavations - Sheeting, Shoring, and Bracing | FAHAD FATEH | special |
| 07/08/2025 | Construction Operations Influencing Adjacent Structures | FAHAD FATEH | special |
| 07/08/2025 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 07/08/2025 | Concrete - Cast-In-Place | FAHAD FATEH | special |
| 07/08/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | FAHAD FATEH | special |
| 07/08/2025 | Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components | FAHAD FATEH | special |
| 07/08/2025 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 07/08/2025 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 07/08/2025 | Interior lighting power | FAHAD FATEH | energy_progress |
| 07/08/2025 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 05/27/2025 | Concrete - Cast-In-Place | FAHAD FATEH | special |
| 05/27/2025 | Construction Operations Influencing Adjacent Structures | FAHAD FATEH | special |
| 05/27/2025 | Excavations - Sheeting, Shoring, and Bracing | FAHAD FATEH | special |
| 05/27/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 05/27/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | FAHAD FATEH | special |
| 05/27/2025 | Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components | FAHAD FATEH | special |
| 05/27/2025 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 05/27/2025 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 05/27/2025 | Fenestration areas | FAHAD FATEH | energy_progress |
| 05/27/2025 | Interior lighting power | FAHAD FATEH | energy_progress |
| 05/27/2025 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 05/27/2025 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |