| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/23/2026 | Signed-off | CAPITAL CONTR P&H CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/21/2025 | Complete | RIDGE ELECTRIC CORP. | General Wiring |
| 10/21/2025 | Complete | RIDGE ELECTRIC CORP. | — |
| Owner | Filings | Most Recent |
|---|---|---|
| TUNNEL TO TOWERS FOUNDATION | 13 | 07/08/2026 |
| PHASE ONE CONSTRUCTION | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| VMT DESIGN WORKSHOP INC. | 7 | 06/23/2026 |
| A TECH ENGINEERING NYC, PLLC. | 1 | 10/22/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| A TECH ENGINEERING NYC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JON ADAMO | General Contractor | 2 | 07/08/2026 |
| RIDGE ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| FIVE BORO ASSOCIATES INC | Fire Protection | 1 | 07/08/2026 |
| CAPITAL CONTR P&H CORP | Plumbing | 1 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CNS INSPECTION SERVICES | 7566 | 7 | 06/23/2026 |
| A TECH ENGINEERING NYC, P | 6738 | 1 | 10/22/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 10/06/2025 |
| DOB NOW | Mechanical Systems | Signed-off | JON ADAMO | 12/20/2024 |
| DOB NOW | Sprinklers | Signed-off | FIVE BORO ASSOCIATES INC | 12/19/2024 |
| DOB NOW | Plumbing | Signed-off | CAPITAL CONTR P&H CORP | 12/11/2024 |
| DOB NOW | General Construction | Permit Issued | JON ADAMO | 12/09/2024 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/20/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/29/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/15/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/10/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 09/05/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/13/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/11/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/27/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/22/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/26/2025 | Certified Water Pressure - WP - PL - Underground Test | Certified | View ↗ |
| 01/28/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 09/17/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/01/2026 | Lighting controls | John Nucatola | energy_progress |
| 05/01/2026 | Structural Stability – Alterations of existing buildings | John Nucatola | special |
| 05/01/2026 | Energy Code Compliance Inspections | John Nucatola | progress |
| 05/01/2026 | Fire-Resistance Rated Construction | John Nucatola | progress |
| 05/01/2026 | Air barrier - visual inspection | John Nucatola | energy_progress |
| 05/01/2026 | Insulation placement and R values | John Nucatola | energy_progress |
| 05/01/2026 | Interior lighting power | John Nucatola | energy_progress |
| 05/01/2026 | Fire-Resistant Penetrations and Joints | John Nucatola | special |
| 06/08/2025 | Energy Code Compliance Inspections | John Nucatola | progress |
| 06/08/2025 | HVAC-R and service water heating equipment | John Nucatola | energy_progress |
| 06/08/2025 | Maintenance information | John Nucatola | energy_progress |
| 06/08/2025 | HVAC-R and service water heating system controls | John Nucatola | energy_progress |
| 06/08/2025 | HVAC-R and service water piping design and insulation | John Nucatola | energy_progress |
| 06/08/2025 | Fire-Resistant Penetrations and Joints | John Nucatola | special |
| 01/22/2025 | Fire-Resistant Penetrations and Joints | John Nucatola | special |
| 01/22/2025 | Structural Stability – Alterations of existing buildings | John Nucatola | special |
| 01/22/2025 | Energy Code Compliance Inspections | John Nucatola | progress |
| 01/22/2025 | Fire-Resistance Rated Construction | John Nucatola | progress |
| 01/22/2025 | Insulation placement and R values | John Nucatola | energy_progress |
| 01/22/2025 | Air barrier - visual inspection | John Nucatola | energy_progress |
| 01/22/2025 | Lighting controls | John Nucatola | energy_progress |
| 01/22/2025 | Interior lighting power | John Nucatola | energy_progress |
| 01/22/2025 | Fire-Resistant Penetrations and Joints | John Nucatola | special |
| 01/22/2025 | Energy Code Compliance Inspections | John Nucatola | progress |
| 01/22/2025 | HVAC-R and service water piping design and insulation | John Nucatola | energy_progress |