← Back
Two stories - detached, small or mid-size
219-31 114 AVENUE
QUEENS · Cambria Heights · BIN 4242268
💬 Discuss this project
1925Year Built
2.5Stories
A1Building Class
R3AZoning
1,558 sfGross Floor Area
1Units
3 Open Violations 0 unresolved · 3 paperwork only ▸FDNY Report ↗
Two stories - detached, small or mid-size · 3,000 sf lot · 0.52 FAR built · Flood zone X
Locations of Work
ArchitectureGeneral
Filed — no permit issued9p · 1 filing · 6 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC104/11/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
S R SOLAR DESIGN203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244104/11/2024
Building Lifecycle
All (9)Filed (1)Violation (3)Special Inspection (5)
04/11/2024
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. NO CHANGE IN BULK.
Q01034161-I1
04/11/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
04/11/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
04/11/2024
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
04/11/2024
Special inspection requirement — Final
NARESH MAHANGU
04/11/2024
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
09/12/2012
Violation issued (ECB, open)
Construction
10/19/2006
Violation issued (ECB, open)
Quality of Life
10/19/2006
Violation issued (ECB, open)
Quality of Life
Nothing on file for this building.
1 project · most recent 04/02/2024
FiledStatusContractorScope
04/02/2024Permit IssuedGMJ ELECTRIC CORP—
1 project · most recent 04/11/2024
FiledStatusContractorScope
04/11/2024——13 panels, 5.27 kw, 555 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
04/11/2024Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
04/11/2024Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
04/11/2024Energy Code Compliance InspectionsNARESH MAHANGUprogress
04/11/2024FinalNARESH MAHANGUprogress
04/11/2024Air barrier - visual inspectionNARESH MAHANGUenergy_progress
▾Documents — 6 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/22/2026Q01034161-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/28/2026Q01034161-I1Open ↗
08/28/2026Q01034161-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01034161-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/28/2026Q01034161-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01034161-I1Open ↗