Five to six families · Owner of record: 2278 MOTT AVENUE LLC · 7,920 sf lot · 0.61 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction70p · 3 filings · 20 docs
Floor 3Under Construction73p · 3 filings · 20 docs
Floor 2Under Construction68p · 3 filings · 20 docs
Floor 1Under Construction70p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
2278 MOTT AVE10509/09/2026
LCS RESTORATION CORP503/22/2026
BBB CONSTRUCTION403/22/2026
ARCONA INC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/24/2022$850K—Private party → 2278 MOTT AVENUE LLC— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GERALD CALIENDO ARCHITECTS1808/06/2026
M-CON ENGINEERING, PC103/31/2025
MJE PROFESSIONAL SERVICES110/24/2023
RAS PE CONSULTING ENGINEERS1003/29/2023
KNF SERVICES CROP207/25/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GERALD J. CALIENDO R.A., P.C.1903/21/2026
GERALD J CALIENDO ARCHITECTS RA1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BBB CONSTRUCTION INCGeneral Contractor1607/08/2026
JH CREW INCGeneral Contractor904/09/2026
PLUMB-IT MECHANICAL INCPlumbing409/09/2026
L&J PLG & HTG CO OF NY INPlumbing407/08/2026
LCS RESTORATION CORPGeneral Contractor303/21/2026
MORGAN SERVICES GROUP CORGeneral Contractor303/21/2026
AZCONA, INCGeneral Contractor203/21/2026
DYNAMIC PLBNG & SPRKR CORFire Protection107/08/2026
SUSTAINABLE STRATEGIESGeneral Contractor104/09/2026
SOURCE ELECTRIC INCElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP56161908/06/2026
M-CON ENGINEERING7341103/31/2025
Building Lifecycle
All (184)Filed (32)Permit Issued (29)Signed Off (5)Violation (5)Inspection (19)Objection (64)Special Inspection (30)
09/08/2026
Permit issued — Boiler Equipment
Q00699181-S7-BE
08/18/2026
Special inspection requirement — Permanent certificate
FAHAD FATEH
08/18/2026
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
08/18/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
FAHAD FATEH
08/18/2026
Special inspection requirement — Maintenance information
FAHAD FATEH
08/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
08/18/2026
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
08/18/2026
Special inspection requirement — Metering
FAHAD FATEH
08/17/2026
Objection resolved — Resolved
08/14/2026
Objection raised — Scope
08/06/2026
Filed — New Building
Proposed Three (3) story, Twelve (12) residential unit, new building with Ten (10) parking spots at ground floor OSP
Q00699181-A6
08/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
08/06/2026
Special inspection requirement — Metering
FAHAD FATEH
08/06/2026
Special inspection requirement — Permanent certificate
FAHAD FATEH
08/06/2026
Special inspection requirement — Maintenance information
FAHAD FATEH
08/06/2026
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
08/06/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
FAHAD FATEH
08/06/2026
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
07/16/2026
Permit issued — Plumbing
Q00699181-S4-PL
06/05/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/29/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
04/01/2026
Filed — New Building
Proposed Three (3) story, Twelve (12) residential unit, new building with Ten (10) parking spots at ground floor OSP
Q00699181-A5
04/01/2026
Special inspection requirement — Maintenance information
FAHAD FATEH
04/01/2026
Special inspection requirement — Electric vehicle service equipment requirements
FAHAD FATEH
04/01/2026
Special inspection requirement — Fenestration areas
FAHAD FATEH
04/01/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
04/01/2026
Special inspection requirement — Electrical motors and elevators
FAHAD FATEH
04/01/2026
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
04/01/2026
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
04/01/2026
Special inspection requirement — Permanent certificate
FAHAD FATEH
04/01/2026
Special inspection requirement — Concrete - Cast-In-Place
FAHAD FATEH
04/01/2026
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
FAHAD FATEH
04/01/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
04/01/2026
Special inspection requirement — Air barrier — testing
FAHAD FATEH
04/01/2026
Special inspection requirement — Subgrade Inspections
FAHAD FATEH
04/01/2026
Special inspection requirement — Lowest Floor Elevation
FAHAD FATEH
04/01/2026
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
FAHAD FATEH
04/01/2026
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
03/24/2026
Filed — New Building
Proposed Three (3) story, Twelve (12) residential unit, new building with Ten (10) parking spots at ground floor OSP
Q00699181-A4
03/18/2026
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
02/04/2026
Filed — New Building
Proposed Three (3) story, Twelve (12) residential unit, new building with Ten (10) parking spots at ground floor OSP
Q00699181-S9
02/04/2026
Filed — New Building
Proposed Three (3) story, Twelve (12) residential unit, new building with Ten (10) parking spots at ground floor OSP
Q00699181-Z1
02/04/2026
Filed — New Building
Proposed Three (3) story, Twelve (12) residential unit, new building with Ten (10) parking spots at ground floor OSP
Q00699181-A3
02/03/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
12/31/2025
Permit issued — Plumbing
Q00699181-S4-PL
12/31/2025
Permit issued — Boiler Equipment
Q00699181-S7-BE
11/28/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
11/28/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
11/21/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
11/21/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
11/21/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/21/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
10/31/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/10/2025
Permit issued — Construction Fence
Q00690109-I1-FN
04/15/2025
Permit issued — Mechanical Systems
Q00730524-I1-MS
04/08/2025
Permit issued — General Construction
Q00699181-I1-GC
04/03/2025
Permit issued — Solar
Q01193211-I1-SL
03/31/2025
Filed — Alteration
INSTALLATION OF SOLAR ELECTRIC GENERATION SYSTEM FOR UTILITY INTERCONNECTION
Q01193211-I1
02/12/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/29/2025
Signed off — New Building
Proposed Three (3) story, Twelve (12) residential unit, new building with Ten (10) parking spots at ground floor OSP
Q00699181-S8
Latest 60 of 184 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentPermit IssuedPLUMB-IT MECHANICAL INC09/08/2026
DOB NOWPlumbingPermit IssuedPLUMB-IT MECHANICAL INC07/16/2026
DOB NOWPlumbingPermit IssuedL&J PLG & HTG CO OF NY IN12/31/2025
DOB NOWBoiler EquipmentPermit IssuedL&J PLG & HTG CO OF NY IN12/31/2025
DOB NOWConstruction FencePermit IssuedJH CREW INC10/10/2025
DOB NOWMechanical SystemsPermit IssuedJH CREW INC04/15/2025
DOB NOWGeneral ConstructionPermit IssuedJH CREW INC04/08/2025
DOB NOWSolarPermit IssuedSUSTAINABLE STRATEGIES04/03/2025
DOB NOWFoundationSigned-offBBB CONSTRUCTION INC11/26/2024
DOB NOWPlumbingPermit IssuedL&J PLG & HTG CO OF NY IN06/20/2024
DOB NOWPlumbingPermit IssuedJVR PLBG AND HEATING INC05/15/2024
DOB NOWBoiler EquipmentPermit IssuedL&J PLG & HTG CO OF NY IN05/15/2024
DOB NOWBoiler EquipmentPermit IssuedJVR PLBG AND HEATING INC05/09/2024
DOB NOWFoundationSigned-offJH CREW INC05/08/2024
DOB NOWSprinklersPermit IssuedCITYWIDE PLBG, HTG &SPRKL02/15/2024
DOB NOWSupported ScaffoldPermit IssuedLCS RESTORATION CORP10/25/2023
DOB NOWGeneral ConstructionPermit IssuedBBB CONSTRUCTION INC10/23/2023
DOB NOWFoundationSigned-offBBB CONSTRUCTION INC09/22/2023
DOB NOWStructuralSigned-offBBB CONSTRUCTION INC09/20/2023
DOB NOWGeneral ConstructionPermit IssuedBBB CONSTRUCTION INC09/19/2023
DOB NOWEarth WorkSigned-offBBB CONSTRUCTION INC09/19/2023
DOB NOWConstruction FencePermit IssuedBBB CONSTRUCTION INC04/03/2023
DOB NOWEarth WorkSigned-offBBB CONSTRUCTION INC03/31/2023
DOB NOWStructuralSigned-offBBB CONSTRUCTION INC03/28/2023
DOB NOWFoundationSigned-offBBB CONSTRUCTION INC03/28/2023
DOB NOWGeneral ConstructionPermit IssuedBBB CONSTRUCTION INC03/27/2023
DOB NOWConstruction FencePermit IssuedAZCONA, INC12/20/2022
DOB NOWEarth WorkSigned-offJH CREW INC05/23/2022
DOB NOWConstruction FencePermit IssuedMORGAN SERVICES GROUP COR03/08/2022
BIS—ISSUEDAZCONA, INC01/04/2023
BISEQISSUEDAZCONA, INC12/28/2022
1 job · most recent 07/25/2022
Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
07/25/2022Permit IssuedJH CREW INCHeating Systems
Heating
Greenheck GREEENHECK MODEL SQ-95-D 500 CFM ×13
1 job · most recent 07/14/2022
FiledStatusContractorScope
07/14/2022Permit IssuedDYNAMIC PLBNG & SPRKR COR154 heads
1 job · most recent 08/06/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
08/06/2026Permit IssuedPLUMB-IT MECHANICAL INCGas, Storm, Water/Sanitary
2 jobs · most recent 06/17/2025
General Wiring
FiledStatusContractorScope
06/17/2025CompleteSOURCE ELECTRIC INC1 meters, 1 new_meters
10/10/2023Permit IssuedBRANDL ELECTRIC INC.General Wiring
1 job · most recent 08/06/2026
Concrete
FiledStatusContractorScope
08/06/2026Permit IssuedPLUMB-IT MECHANICAL INCConcrete
1 job · most recent 03/31/2025
FiledStatusContractorScope
03/31/2025Permit IssuedSUSTAINABLE STRATEGIES12 panels, 4.2 kw, 3,145 roof_area_sqft
1 job · most recent 03/28/2022
Fence
FiledStatusContractorScope
03/28/2022Permit IssuedJH CREW INCFence
▾Field Inspections (DOB CAP) — 19
DateTypeResultReport
06/05/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/29/2026Pass-Final General Construction Non-Directive 14PassView ↗
03/18/2026Fail-Final General Construction Non-Directive 14FailView ↗
02/03/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/28/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
11/28/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
11/21/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
11/21/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
11/21/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/21/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
10/31/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/12/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
12/20/2024Pass-Final CND-Occupancy InspectionPassView ↗
07/03/2024Pass-Final CND-Occupancy InspectionPassView ↗
06/29/2024Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
06/28/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
06/28/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
06/28/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
03/04/2024Fail-Final CND-Occupancy InspectionFailView ↗
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
08/18/2026Permanent certificateFAHAD FATEHenergy_progress
08/18/2026MeteringFAHAD FATEHenergy_progress
08/18/2026Maintenance informationFAHAD FATEHenergy_progress
08/18/2026Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
08/18/2026HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
08/18/2026HVAC-R and service water piping design and insulationFAHAD FATEHenergy_progress
08/18/2026HVAC-R and service water heating system controlsFAHAD FATEHenergy_progress
08/06/2026MeteringFAHAD FATEHenergy_progress
08/06/2026HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
08/06/2026Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
08/06/2026Maintenance informationFAHAD FATEHenergy_progress
08/06/2026HVAC-R and service water heating system controlsFAHAD FATEHenergy_progress
08/06/2026Permanent certificateFAHAD FATEHenergy_progress
08/06/2026HVAC-R and service water piping design and insulationFAHAD FATEHenergy_progress
04/01/2026Subgrade InspectionsFAHAD FATEHspecial
04/01/2026Air barrier — testing FAHAD FATEHenergy_progress
04/01/2026Air barrier - visual inspectionFAHAD FATEHenergy_progress
04/01/2026Permanent certificateFAHAD FATEHenergy_progress
04/01/2026Electrical motors and elevatorsFAHAD FATEHenergy_progress
04/01/2026Lowest Floor ElevationFAHAD FATEHprogress
04/01/2026Wall Panels, Curtain Walls, and VeneersFAHAD FATEHspecial
04/01/2026Concrete - Cast-In-PlaceFAHAD FATEHspecial
04/01/2026Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
04/01/2026Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)FAHAD FATEHspecial
04/01/2026Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
Latest 25 of 150.
▾Documents — 233 on file (BIS + DOB NOW)
▸Plans & Drawings32
▸DOB NOWPlans/Sketch32
08/26/2026Q00690109-P1Request digital key ↗
08/26/2026Q00738935-I1Request digital key ↗
08/25/2026Q00699181-P8Request digital key ↗
Showing 3 of 32 on file for this type
▸Applications & Permits7
▸BISPLAN / WORK APPROVAL APPLICATION4
06/27/2025421839274Open ↗
01/31/2023421806326Open ↗
05/19/2022440710679Open ↗
Showing 3 of 4 on file for this type
▸BISWORK PERMIT APPLICATION2
03/02/2023421806326Open ↗
03/02/2023421806326Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
04/05/2022440710679Open ↗
▸Zoning, Tax Lot & Property Records19
▸DOB NOWZD1: DOB Zoning Diagram6
08/13/2026Q00699181-A2Open ↗
08/13/2026Q00699181-P9Open ↗
08/13/2026Q00699181-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWZoning Exhibit form (1-5)6
08/13/2026Q00699181-A2Open ↗
08/13/2026Q00699181-P6Open ↗
08/13/2026Q00699181-P3Open ↗
Showing 3 of 6 on file for this type
▸BISZONING EXHIBIT I: CERTIFICATION2
02/20/2024421839274Open ↗
04/25/2022421808565Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT2
02/21/2024421839274Open ↗
04/25/2022421808565Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED2
02/20/2024421839274Open ↗
04/05/2022440710679Open ↗
▸BISTAX LOT: FINAL LOT NUMBER ISSUED1
05/19/2022440710679Open ↗
▸Seals & Professional Certifications93
▸DOB NOWSpecial Inspector Seal & Signature37
09/23/2026Q00699181-S7Open ↗
09/01/2026Q00699181-S2Open ↗
09/01/2026Q00699181-S2Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature32
08/26/2026Q00690109-I1Open ↗
08/26/2026Q00690109-P1Open ↗
08/25/2026Q00699181-A6Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWProgress Inspector Seal & Signature22
09/23/2026Q00699181-S7Open ↗
09/01/2026Q00699181-S2Open ↗
09/01/2026Q00699181-A6Open ↗
Showing 3 of 22 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
04/05/2022440710679Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
04/05/2022440710679Open ↗
▸Trade Schedules & Equipment9
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)5
08/13/2026Q00699181-P3Open ↗
08/13/2026Q00699181-A2Open ↗
08/13/2026Q00699181-P9Open ↗
Showing 3 of 5 on file for this type
▸BISSEWER CUT-OFF2
03/02/2023421806326Open ↗
03/02/2023421806326Open ↗
▸BISGAS CUT-OFF1
03/02/2023421806326Open ↗
▸BISELECTRIC CUT-OFF1
03/02/2023421806326Open ↗
▸Safety & Tenant Protection10
▸DOB NOWStreet Tree Checklist6
08/13/2026Q00699181-P9Open ↗
08/13/2026Q00699181-P6Open ↗
08/13/2026Q00699181-P3Open ↗
Showing 3 of 6 on file for this type
▸BISSTREET TREE CHECKLIST1
05/13/2022440710679Open ↗
▸BISSRO MD ANTI-HARASSMENT CHECKLIST1
03/02/2023421806326Open ↗
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
03/02/2023421806326Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00699181-I1Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
03/02/2023421806326Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
04/05/2022440710679Open ↗
▸Inspections & Test Reports8
▸DOB NOWSOIL REPORT5
08/13/2026Q00699181-P1Open ↗
08/13/2026Q00699181-P7Open ↗
08/13/2026Q00699181-S1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram2
08/13/2026Q00699181-S1Open ↗
08/13/2026Q00738935-I1Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026Q00738935-I1Open ↗
▸Approvals, Objections & Sign-offs7
▸BISLETTERS - SUPPORTING DOCUMENTATION5
03/02/2023421806326Open ↗
03/02/2023421806326Open ↗
03/02/2023421806326Open ↗
Showing 3 of 5 on file for this type
▸BISTAP LETTER - DOM SVC : DEP-DOM1
03/02/2023421806326Open ↗
▸BISDOB APPROVAL FOR NEW CC1
05/13/2022440710679Open ↗
▸Cost, Insurance & Ownership2
▸BISDEPT OF FINANCE VERIFICATION1
03/02/2023421806326Open ↗
▸BISPROJECT SPECIFIC GENERAL LIABILITY INSURANCE1
03/02/2023421806326Open ↗
▸Filing & Intake Forms8
▸BISBOROUGH INTAKE FORM3
03/02/2023421806326Open ↗
02/28/2023421806326Open ↗
01/31/2023421806326Open ↗
▸BISEFILING COVER SHEET3
07/03/2025421839274Open ↗
01/31/2023421806326Open ↗
05/19/2022440710679Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
04/05/2022440710679Open ↗
▸BISADDITIONAL INFORMATION1
04/25/2022421808565Open ↗
▸Other Documents36
▸DOB NOWProperty Ownership Certification8
08/25/2026Q00699181-A5Open ↗
08/25/2026Q00699181-A2Open ↗
08/25/2026Q00699181-P6Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSite Survey: Initial6
08/13/2026Q00699181-P6Open ↗
08/13/2026Q00699181-P9Open ↗
08/13/2026Q00699181-A5Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone6
08/13/2026Q00699181-P6Open ↗
08/13/2026Q00699181-P9Open ↗
08/13/2026Q00699181-P3Open ↗
Showing 3 of 6 on file for this type
▸BISSupporting Document: Fee Exempt4
04/25/2022421808565Open ↗
04/25/2022421808565Open ↗
04/25/2022421808565Open ↗
Showing 3 of 4 on file for this type
▸BISPLOT DIAGRAM3
02/21/2024421839274Open ↗
02/21/2024421839274Open ↗
02/21/2024421839274Open ↗
▸DOB NOWFEMA Elevation Certificate (086-0-33)/Flood Proofing Certificate (086-0-34)3
08/13/2026Q00699181-S2Open ↗
08/13/2026Q00699181-S4Open ↗
08/13/2026Q00699181-S1Open ↗
▸DOB NOWAdjoining Owners Notification3
08/13/2026Q00738935-I1Open ↗
08/13/2026Q00699181-S5Open ↗
08/13/2026Q00699181-S8Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
02/21/2024421839274Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
04/05/2022440710679Open ↗
▸BISVERIFY DOB PLAN NAMING STANDARD IS MET1
02/21/2024421839274Open ↗