| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/06/2023 | $2.8M | — | — → — | $1,000/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| GREEN SOLUTIONS ENGINEERING & ENERG | 3 | 08/20/2026 |
| NY BUILDING ASSOCIATES INC | 1 | 08/13/2025 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 06/04/2025 |
| REBUILD ARCHITECTURE | 4 | 05/01/2025 |
| ALBANO | 1 | 03/26/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| BROOKLYN SOLARWORKS | 1 | 03/21/2026 |
| THE VILNITS GROUP LLC | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| REBUILD WORKSHOP LLC | General Contractor | 16 | 07/08/2026 |
| MC SUPERSTRUCTURE INC | General Contractor | 4 | 03/21/2026 |
| DYNAMIC BLUE WATER MECH | Plumbing | 2 | 07/08/2026 |
| ELPO ELECTRICAL CONTG INC | Electrical | 1 | 03/22/2026 |
| NASH ELECTRIC SERVICES IN | Electrical | 1 | 03/22/2026 |
| BROOKLYN SOLARWORKS LLC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| THE VILNITS GROUP LLC | 1223 | 4 | 08/20/2026 |
| NKM ENGINEERING PLLC | 6244 | 1 | 08/13/2025 |
| INTERNATIONAL GEOTEHCNICA | 1795 | 1 | 03/26/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | BROOKLYN SOLARWORKS LLC | 08/14/2025 |
| DOB NOW | Mechanical Systems | Signed-off | REBUILD WORKSHOP LLC | 06/30/2025 |
| DOB NOW | Supported Scaffold | Signed-off | MC SUPERSTRUCTURE INC | 06/05/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | MC SUPERSTRUCTURE INC | 06/05/2025 |
| DOB NOW | General Construction | Permit Issued | REBUILD WORKSHOP LLC | 03/24/2025 |
| DOB NOW | Construction Fence | Signed-off | REBUILD WORKSHOP LLC | 03/04/2025 |
| DOB NOW | General Construction | Permit Issued | REBUILD WORKSHOP LLC | 01/24/2025 |
| DOB NOW | Plumbing | Signed-off | SUPER PLUMBERS CORP | 08/12/2024 |
| DOB NOW | Foundation | Signed-off | REBUILD WORKSHOP LLC | 06/13/2024 |
| DOB NOW | Mechanical Systems | Signed-off | REBUILD WORKSHOP LLC | 06/13/2024 |
| DOB NOW | Construction Fence | Signed-off | REBUILD WORKSHOP LLC | 03/04/2024 |
| DOB NOW | Plumbing | Signed-off | SUPER PLUMBERS CORP | 01/30/2024 |
| DOB NOW | General Construction | Permit Issued | REBUILD WORKSHOP LLC | 01/19/2024 |
| BIS | OT | ISSUED | EXALDO TOPACIO | 12/05/2008 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/20/2026 | Signed-off | REBUILD WORKSHOP LLC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM60NAM2 5 tons · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | Signed-off | SUPER PLUMBERS CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/08/2025 | Complete | BROOKYLN SOLARWORKS, LLC | — |
| 06/09/2025 | Complete | NASH ELECTRIC SERVICES IN | — |
| 02/05/2024 | Complete | ELPO ELECTRICAL CONTG INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | Signed-off | REBUILD WORKSHOP LLC | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | Signed-off | REBUILD WORKSHOP LLC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/24/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/31/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 11/07/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/07/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/20/2026 | Final | ILYA VILNITS | progress |
| 08/20/2026 | Mechanical Systems | ILYA VILNITS | special |
| 08/20/2026 | Fire-Resistant Penetrations and Joints | ILYA VILNITS | special |
| 07/07/2025 | Final | NARESH MAHANGU | progress |
| 07/07/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 07/07/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 07/07/2025 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 07/07/2025 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 05/06/2025 | Fire-Resistant Penetrations and Joints | ILYA VILNITS | special |
| 05/06/2025 | Fire-Resistance Rated Construction | ILYA VILNITS | progress |
| 03/26/2025 | Fire-Resistant Penetrations and Joints | ILYA VILNITS | special |
| 03/26/2025 | Fire-Resistance Rated Construction | ILYA VILNITS | progress |
| 05/07/2024 | Post-installed Anchors | MICHAEL KARANTINIDIS, P.E. | special |
| 05/07/2024 | Fire-Resistant Penetrations and Joints | ILYA VILNITS | special |
| 02/16/2024 | Structural Steel - Details | MICHAEL KARANTINIDIS, P.E. | special |
| 02/16/2024 | Structural Cold-Formed Steel | MICHAEL KARANTINIDIS, P.E. | special |
| 02/16/2024 | Footing and Foundation | MICHAEL KARANTINIDIS, P.E. | progress |
| 02/16/2024 | Structural Stability – Alterations of existing buildings | MICHAEL KARANTINIDIS, P.E. | special |
| 02/16/2024 | Final | MICHAEL KARANTINIDIS, P.E. | progress |
| 02/16/2024 | Mechanical Systems | ILYA VILNITS | special |
| 02/16/2024 | Final | ILYA VILNITS | progress |
| 01/08/2024 | Fire-Resistant Penetrations and Joints | — | special |
| 01/08/2024 | Fire-Resistance Rated Construction | — | progress |